Tentinger v. McPheters

977 P.2d 234, 132 Idaho 620, 1999 Ida. App. LEXIS 17
CourtIdaho Court of Appeals
DecidedFebruary 25, 1999
Docket24676
StatusPublished
Cited by8 cases

This text of 977 P.2d 234 (Tentinger v. McPheters) is published on Counsel Stack Legal Research, covering Idaho Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tentinger v. McPheters, 977 P.2d 234, 132 Idaho 620, 1999 Ida. App. LEXIS 17 (Idaho Ct. App. 1999).

Opinion

SCHWARTZMAN, Judge.

Steven McPheters appeals from the district court’s affirmance of the magistrate’s judgment and order awarding Terry Tenting-er $420.00 for painting services performed at the request of McPheters, together with attorney fees and costs. For the reasons stated below, we affirm.

I.

FACTUAL AND PROCEDURAL BACKGROUND

In the fall of 1995, Steven McPheters, a home builder and developer, obtained a bid from Terry Tentinger, dba New Horizon Construction, to do some touch-up and repainting on one of his “spec” homes. 1 Tentinger submitted a bid of $690.00, but the parties subsequently negotiated a per hour fee. On Tentinger’s second and final day on the job, McPheters testified that he spoke with Tentinger about some overspray on the home’s upper deck. McPheters averred that Tentinger informed him that there was not enough paint overspray on the upper deck to make a difference. McPheters testified that he did not address the issue any further with Tentinger. Tentinger, on the other hand, testified that McPheters never questioned the quality of the work or requested any touch-ups.

Thereafter, Tentinger billed McPheters $420 for the job, which represented fourteen hours of work at a $30 per hour rate. Jim McPheters, Steven McPheters’s son, objected to the number of hours Tentinger billed, but did not express dissatisfaction with the work performed. Subsequently McPheters offered Tentinger $250 in satisfaction of the debt, but Tentinger refused. Tentinger then filed a mechanic’s lien on McPheters’s home and a complaint seeking enforcement of the lien, plus attorney fees. McPheters filed an answer and counterclaim, alleging that Tentinger’s failure to perform the job in a workmanlike manner resulted in $2,500 in damages and that it would cost $500 to repair the damages caused by Tentinger’s failure to properly perform. McPheters also counterclaimed for costs and attorney fees.

A bench trial was held February 9-10, 1997. The court heard testimony from, among others, Tentinger, Steven and Jim McPheters and individuals who had prior business dealings with both parties. A number of witnesses testified that it was standard practice for a builder to provide subcontractors who perform services with a “punch list” of touch-up or follow-up work needed to complete the job. Jim McPheters testified that he never informed Tentinger or anyone in his office regarding the dissatisfaction Steven McPheters felt with respect to Tentinger’s paint job on the home. Jim McPheters further testified that “it’s not common for us to give painters punch lists.”

At the close of the evidence, the magistrate resolved the conflicting testimony in Tentinger’s favor and concluded that there was a contract between the parties, and that despite some minor defects, Tentinger had substantially performed the painting job and McPheters had waived any defects in workmanship by failing to request that Tentinger cure such defects. The court also recognized and validated the mechanic’s lien filed by *622 Tentinger to the extent of $420. Finally, the court awarded Tentinger $4,000 in attorney fees and $900.02 in costs.

Thereafter, McPheters filed an appeal to the district court. The district court heard oral argument and affirmed the magistrate’s findings of fact and conclusions of law. The district court also awarded Tentinger attorney fees on appeal in the amount of $2,873.75. McPheters appeals again, arguing that the trial court erred in concluding that Tentinger substantially performed the contract and that he waived any defects in the workmanship by failing to provide Tentinger with a “punch list” of defects.

II.

STANDARD OF REVIEW

When an action is tried to a court sitting without a jury, this Court’s review is limited to ascertaining whether the evidence supports the lower court’s findings of fact, and whether these findings support the court’s conclusions of law. I.R.C.P. 52(a); J.P. Stravens Planning Assoc., Inc., v. City of Wallace, 129 Idaho 542, 544, 928 P.2d 46, 48 (Ct.App.1996). This Court liberally construes the trial court’s findings of fact in favor of the judgment entered and will not disturb findings which are supported by substantial, albeit conflicting, evidence. Sun Valley Shamrock v. Travelers Leasing, 118 Idaho 116, 118, 794 P.2d 1389, 1391 (1990). Witness credibility and the weight to be given evidence are within the trial court’s province and will not be set aside unless clearly erroneous. Id.

III.

ANALYSIS

A. The Trial Court Correctly Concluded That Tentinger Substantially Performed His Contract With McPheters

McPheters argues that the evidence does not support the trial court’s conclusion that Tentinger substantially performed the contract. McPheters specifically asserts that the following defects in Tentinger’s workmanship preclude a finding of substantial performance: (1) paint overspray underneath the redwood decking; (2) lack of paint coverage on portions of the rain gutter and downspout; and (3) water erosion caused by one of Tentinger’s workers leaving a water hose turned on for an excessive period of time. McPheters argues that because it will cost him more to remedy these defects than Tentinger charged for the original job, Tenting-er’s work was commercially unreasonable and constitutes a material breach which excuses his own performance, i.e., the payment of Tentinger’s bill.

A breach of contract is material or substantial if it “touches the fundamental purpose of the contract and defeats the object of the parties in entering into the contract.” Ervin Constr. Co. v. Van Orden, 125 Idaho 695, 699, 874 P.2d 506, 510 (1993), citing Enterprise, Inc. v. Nampa City, 96 Idaho 734, 740, 536 P.2d 729, 735 (1975). Rescission is not available where the breach is merely incidental or subordinate to the main purpose of the contract and substantial performance has been rendered. Id. at 700, 874 P.2d at 511. “Substantial performance is performance which, despite a deviation from contract requirements, provides the important and essential benefits of the contract to the promisee.” J.P. Stravens, 129 Idaho at 545, 928 P.2d at 49. The materiality of a breach is a factual question. Ervin Constr. Co., 125 Idaho at 700, 874 P.2d at 511.

According to testimony presented at trial, the fundamental purpose of the contract was to provide touch-up painting work on McPheters’s “spec” home so that he could place it on the market for sale. The trial court found that although his workmanship was not completely free of defects, Tentinger had substantially performed his obligation pursuant to the contract and was willing to return to McPheters’s home to remedy any defects in his workmanship at no cost.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peterson v. Shore
197 P.3d 789 (Idaho Court of Appeals, 2008)
State v. Chacon
198 P.3d 749 (Idaho Court of Appeals, 2008)
Employers Insurance v. St. Clair Contractors, Inc.
223 F. App'x 644 (Ninth Circuit, 2007)
McPheters v. Maile
64 P.3d 317 (Idaho Supreme Court, 2003)
Roberts v. Wyman
23 P.3d 152 (Idaho Court of Appeals, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
977 P.2d 234, 132 Idaho 620, 1999 Ida. App. LEXIS 17, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tentinger-v-mcpheters-idahoctapp-1999.