Washington Construction Co., Inc. v. Spinella

84 A.2d 617, 8 N.J. 212, 28 A.L.R. 2d 863, 1951 N.J. LEXIS 175
CourtSupreme Court of New Jersey
DecidedNovember 26, 1951
StatusPublished
Cited by60 cases

This text of 84 A.2d 617 (Washington Construction Co., Inc. v. Spinella) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Construction Co., Inc. v. Spinella, 84 A.2d 617, 8 N.J. 212, 28 A.L.R. 2d 863, 1951 N.J. LEXIS 175 (N.J. 1951).

Opinion

The opinion of the court was delivered by

Wachenebld, J.

On petition we granted certification to review a final judgment entered in the Appellate Division affirming a judgment in the Law Division wherein the contractor recovered moneys from the owner under a cost-plus-percentage construction contract entered into by the parties.

In the written contract the respondent is referred to as the contractor and that designation, for the sake of clarity, will be, employed here, while the appellant will be termed the. owner.

The contractor agreed to erect and finish a building and apartments consisting of 15 units called Building No. 2 on the plans and according to the drawings and specifications of the architect designated in the agreement. He was also obligated to “find and provide such good, proper and sufficient materials of all kinds whatsoever, as shall be proper and sufficient for the completing and finishing all the said apartments and buildings. * * *”

The owner agreed to pay to the contractor “the cost of the erection of said Building No. 2, as the same costs the contractor and to pay in addition to said cost the sum equal to 10% of the aforesaid total cost as the profit to said contractor.” A provision for payment at a particular time, for *215 the payroll of all persons actually engaged on the project was not in dispute. The payment for the materials was specified thusly:

“The contractor shall present to the owner on the first day of each month a complete list of all materials furnished in the course of construction on said building for the preceding month. The owner shall thereupon, prior to the 10th of such month, pay to the contractor the total represented by all the bills for the materials furnished, less all discounts allowed to said contractor and less all discounts that said contractor will be entitled to for having said bills paid prior to the 10th of such month.”

Paragraph 4 merely provided for the payment of the cost of all insurance carried on the project during the course of construction, while paragraph 5 recited:

“After such building has been completed and a certificate of com-X)letion obtained the parties hereto shall compute the total actual cost of said building, whereupon the owner shall pay to the contractor 10% of such total cost to represent their profit in the matter of the construction of the aforesaid.”

Paragraph 7 gave the owner the option of obtaining the materials from other sources if he thought he could secure them at a lesser price, after informing the contractor to that effect; while paragraph 9 gave the owner, “should he feel that the prices charged for labor or materials are excessive or that the conduct of any person or persons working under the supervision and direction of said contractor are doing or committing anything that he deems improper,” the right to cancel the contract upon notifying the contractor. Then follows the controversial clause:

“If such event takes place the parties hereto shall compute the total cost of construction and labor up to that date, and to pay 10% thereof to the contractor as his profit up to that date.”

Invoking the remedies reserved to him, the owner cancelled the contract on November 6, 1947, and paid for the insurance and labor and for all building materials delivered to the site.In computing the contractor’s profit, however, the owner *216 refused to include, as part of the cost basis, the value of materials which were on hand but had not yet been used in the construction of the 'building, although conceding his obligation to pay for the materials themselves. The contractor brought this action for ten per cent of that value as part of the profit specified in the contract, making the sum in controversy $2,133.93, the figure stipulated by the parties. „

The trial court directed a verdict for the contractor against the owner for this amount and the Appellate Division affirmed the judgment so rendered.

The owner is not content and insists the amount due to the contractor is limited to the agreed percentage of the actual cost of labor and materials which went into and became part of the finished product; that the phrase “cost of construction” used in the contract means the cost of labor and materials which have been combined to make the materials a part of the building; and that both courts below erred in construing the contract in the light of the previous conduct of the parties acting pursuant to it.

The first two points are closely interrelated and may best be considered together. The problem presented is the familiar one of ascertaining the intent of the parties by the construction and evaluation of the words they used in expressing the agreement between them.

Proclaiming “there is no decision in this state adjudicating the specific question presented by this point and the question is res integra here,” the owner seeks shelter in the interpretation given the phrase “cost of construction” in 17 C. J. S., p. 826:

“Under a cost-plus contract the contractor is entitled, as compensation, to the agreed percentage of the actual cost of the labor and materials that go into and become a part of the finished product, within the terms of the contract”

and similar expressions in Lytle, Campbell & Co., Inc., v. Somers, Filler & Todd Co., 276 Pa. 409, 120 A. 409, 27 *217 A. L. R. 41 (Sup. Ct. Pa. 1923), and House v. Fissell, 51 A. 2d 669 (Ct. of App. Md. 1947).

These cases bear on a controversy arising after the building was fully completed and are not applicable, as obviously under such circumstances a contrary answer may well be arrived at, depending on the wording of the instrument.

The gist of the owner’s dissatisfaction is that the Appellate Division “substituted the words 'materials furnished for the erection’ in place of the words 'cost of construction’ ” and thus “did not construe the contract of the parties but made a new one for them.”

It has been decided many times and in many cases that the court will not make a different or a better contract ■than the parties themselves have seen fit to enter into. Herbert L. Farkas Co. v. N. Y. Fire Ins. Co., 5 N. J. 604 (1950); James v. Federal Ins. Co., 5 N. J. 21 (1950); First National Bank, Fort Lee, v. Burdett, 121 N. J. Eq. 277 (E. & A. 1936); Krieg v. Phoenix Ins. Co., 116 N. J. L. 467 (E. & A. 1936); Marone v. Hartford Fire Ins. Co., 114 N. J. L. 295 (E. & A. 1934); Frisbie Throwing Co. v. London Guarantee, &c., Co., 105 N. J. L. 613 (E. & A. 1929); Kupfersmith v. Delaware Ins. Co., 84 N. J. L. 271 (E. & A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

1410 Grand Adams, LLC v. Trematore Construction, LLC
New Jersey Superior Court App Division, 2025
Portillo v. Nat'l Freight, Inc.
323 F. Supp. 3d 646 (D. New Jersey, 2018)
Henry v. New Jersey Department of Human Services
9 A.3d 882 (Supreme Court of New Jersey, 2010)
Eaton v. Grau
845 A.2d 707 (New Jersey Superior Court App Division, 2004)
East Brunswick v. East Mill Assoc. Inc.
838 A.2d 494 (New Jersey Superior Court App Division, 2004)
Great Atl. & Pac. Tea Co. v. Checchio
762 A.2d 1057 (New Jersey Superior Court App Division, 2000)
Chemical Bank of New Jersey National Ass'n v. Bailey
687 A.2d 316 (New Jersey Superior Court App Division, 1997)
Eagle Fire Protection Corp. v. First Indemnity of America Insurance
678 A.2d 699 (Supreme Court of New Jersey, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
84 A.2d 617, 8 N.J. 212, 28 A.L.R. 2d 863, 1951 N.J. LEXIS 175, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-construction-co-inc-v-spinella-nj-1951.