J. E. Hathman, Inc. v. Sigma Alpha Epsilon Club of Columbia

491 S.W.2d 261, 1973 Mo. LEXIS 805
CourtSupreme Court of Missouri
DecidedMarch 12, 1973
Docket55718
StatusPublished
Cited by222 cases

This text of 491 S.W.2d 261 (J. E. Hathman, Inc. v. Sigma Alpha Epsilon Club of Columbia) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J. E. Hathman, Inc. v. Sigma Alpha Epsilon Club of Columbia, 491 S.W.2d 261, 1973 Mo. LEXIS 805 (Mo. 1973).

Opinions

FINCH, Chief Justice.

Plaintiff contractor brought suit to enforce a mechanic’s lien for labor and materials furnished pursuant to a written contract for reconstruction of the Sigma Alpha Epsilon fraternity house at Columbia, Missouri. Plaintiff’s position was that the contract between the parties was an unambiguous contract whereby the contractor was to be paid cost of labor, materials and other construction expenses (with certain specified exceptions) plus 6% of the cost of construction. Plaintiff’s total claim was for $413,276.97. It had received payments of $269,692.98 and sought a lien for an additional $143,583.99.

On the theory that the contract was ambiguous and to support a counterclaim seeking reformation of the contract, defendant Sigma Alpha Epsilon (SAE) offered, and the trial court admitted, evidence to show that the maximum guaranteed cost of the job was $300,000.00 plus a fee of 6% thereof, or a total of $318,000.-00. The trial court made findings wherein he held that the contract provided for a maximum of $318,000.00 and entered judgment establishing a lien for $48,307.02, the difference between $318,000.00 and payments previously made. Plaintiff then appealed. We reverse and remand with directions.

We have jurisdiction on the basis of the amount involved, this appeal having been lodged here prior to January 1, 1972. Mo. Const. Art. V, § 31.

An opinion was written in division affirming the judgment of the trial court, but a dissenting opinion was filed and the case was transferred to the court en banc. Following reargument, the divisional opinion was not adopted and the case was reassigned.

The basic issue for decision is whether or not the written contract was an unambiguous cost plus fee contract. The applicable rules of law are stated in Kalen v. [264]*264Steele, 341 S.W.2d 343, 346 (Mo.App.1960):

“The cardinal rule in the interpretation of a contract is to ascertain the intention of the parties and to give effect to that intention. Where there is no ambiguity in the contract the intention of the parties is to be gathered from it and it alone, and it becomes the duty of the court and not the jury to state its clear meaning. McFarland v. Gillioz, 327 Mo. 690, 37 S. W.2d 911; National Corporation v. Allan, Mo.App., 280 S.W.2d 428(3). A court will not resort to construction where the intent of the parties is expressed in clear and unambiguous language for there is nothing to construe. Mickelberry’s Food Products Co. v. Haeussermann, Mo.Sup., 247 S.W.2d 731(5). It is only where the contract is ambiguous and not clear that resort to extrinsic evidence is proper to resolve the ambiguity. See 17 C.J.S. Contracts § 321, p. 749; 12 Am.Jur., Contracts, Section 229, page 753.

“A contract is not rendered ambiguous by the fact that the parties do not agree upon the proper construction to be given it. Mickelberry’s Food Products Co. v. Haeussermann, supra, 247 S.W.2d 731(6). A contract is ambiguous only when it is reasonably susceptible of different constructions. In determining whether or not there is such an ambiguity as calls for construction, the whole instrument must be considered. Writings made a part of the contract by annexation or reference are to be considered in determining whether or not it is ambiguous.

“Presumptively, the intent of the parties to a contract is expressed by the natural and ordinary meaning of the language referable to it. Even seeming contradictions must be harmonized away if that be reasonably possible. State Mutual Life Assur. Co. of Worchester v. Dischinger, Mo.Sup., 263 S.W.2d 394(5); Mathews v. Modern Woodmen of America, 236 Mo. 326,139 S.W. 151,155.”

On February 14, 1965, the fraternity house was heavily damaged by fire, a portion of the building having been totally destroyed. SAE immediately hired plaintiff to do the demolition, salvage and clearing. Shortly thereafter it employed the architectural firm of Marshall & Brown to prepare plans and specifications for rebuilding the house and without taking bids arranged with plaintiff to do the reconstruction work. SAE proceeded at once with actual reconstruction, even though final plans and specifications and a contract had not been prepared, because it wanted to reoccupy the house as quickly as possible. Plans and drawings were prepared and submitted throughout the period of construction. Ultimately, in November, 1965 a written contract (dated April 1, 1965) was prepared by the architect and presented by SAE to plaintiff for signature. The job was completed in August, 1966.

The contract was on a printed form which recited at the outset that it was issued by the American Institute of Architects (AIA) “for use when the cost of the work plus a fee forms the basis of payment.” It provided that the contractor was to provide all labor and materials and to do all things necessary to complete construction of the house according to plans, specifications and changes listed.

Article 2 authorized the owner to make changes, issue additional instructions, require additional work or omission of work previously ordered, and contained the additional provision that “Maximum cost of the work will be adjusted in accordance with changes ordered.”

Article 3 specified the contractor’s duties and imposed the obligation on it to complete the work “in the most expeditious and economical manner consistent with the interests of the Owner.”

Article 3A was typed in the contract as an additional Article, and subparagraph (a) thereof provided as follows: “Estimated maximum cost of this work is Three [265]*265Hundred Thousand Dollars and no cents ($300,000.00).”

Article 4 provided that in consideration for its performance, contractor was to be paid “6% of cost of construction.”

Under Article 5 the owner agreed “to reimburse the Contractor in current funds all costs necessarily incurred for the proper execution of the work and paid by the Contractor, such costs to include the following items, and to be at rates not higher than the standard paid in the locality of the work except with prior consent of the Owner:” The Article then spelled out in considerable detail items included, consisting of such items as labor, certain salaries, materials, permit fees, losses and expenses not compensated by insurance which were not due to fault or neglect of the contractor, sub-contracts, premiums on bonds and insurance, rentals of certain equipment, including transportation thereof, cost of hand tools consumed in the prosecution of the work, and certain other expenses.

Article 6 listed certain costs for which the contractor was not to be reimbursed Subsequent Articles contained various provisions not pertinent to the issue here presented.

It is abundantly clear that the printed provisions in the AIA form provided for an unambiguous contract wherein the contractor would receive reimbursement of costs of construction plus a fee for its services.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Al A. Catalano
E.D. Missouri, 2021
Lekander v. Estate of Lekander
345 S.W.3d 282 (Missouri Court of Appeals, 2011)
DeBaliviere Place Ass'n v. Veal
337 S.W.3d 670 (Supreme Court of Missouri, 2011)
West v. Sharp Bonding Agency, Inc.
327 S.W.3d 7 (Missouri Court of Appeals, 2010)
Vest v. Kansas City Homes, L.L.C.
288 S.W.3d 304 (Missouri Court of Appeals, 2009)
Vidacak v. Oklahoma Farmers Union Mutual Insurance Co.
274 S.W.3d 487 (Missouri Court of Appeals, 2008)
Rabius v. Brandon
257 S.W.3d 641 (Missouri Court of Appeals, 2008)
Bores v. Domino's Pizza LLC
489 F. Supp. 2d 940 (D. Minnesota, 2007)
Shelter Mutual Insurance Co. v. Ballew
203 S.W.3d 789 (Missouri Court of Appeals, 2006)
Essex Development, Inc. v. Cotton Custom Homes, L.L.C.
195 S.W.3d 532 (Missouri Court of Appeals, 2006)
Trimble v. Pracna
167 S.W.3d 706 (Supreme Court of Missouri, 2005)
Ferguson v. Gateway Insurance Co.
151 S.W.3d 911 (Missouri Court of Appeals, 2004)
Bailey v. Federated Mutual Insurance Co.
152 S.W.3d 355 (Missouri Court of Appeals, 2004)
Ary Jewelers, L.L.C. v. Krigel
82 P.3d 460 (Supreme Court of Kansas, 2003)
SD Investments, Inc. v. Michael-Paul, L.L.C.
90 S.W.3d 75 (Missouri Court of Appeals, 2002)
Sonoma Management Co., Inc. v. Boessen
70 S.W.3d 475 (Missouri Court of Appeals, 2002)
Atlas Reserve Temporaries, Inc. v. Vanliner Insurance Co.
51 S.W.3d 83 (Missouri Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
491 S.W.2d 261, 1973 Mo. LEXIS 805, Counsel Stack Legal Research, https://law.counselstack.com/opinion/j-e-hathman-inc-v-sigma-alpha-epsilon-club-of-columbia-mo-1973.