Shipman v. State

43 Wis. 381
CourtWisconsin Supreme Court
DecidedAugust 15, 1877
StatusPublished
Cited by22 cases

This text of 43 Wis. 381 (Shipman v. State) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shipman v. State, 43 Wis. 381 (Wis. 1877).

Opinion

Ryan, C. J.

After issue in this cause had been sent down for trial, the attorney general procured the return of the record by stipulation; and moves for leave to file seven amended answers, three of them in the way of counter claim.

The original answer admits the contract set up in the com[385]*385plaint between tbe plaintiff and the building commissioners; admits the plaintiff’s presentation of his claim to the legislature, and their refusal to allow it; and denies every other averment of the complaint.

The first amended answer again admits the contract, but denies the plaintiff’s performance of it. This is covered by the general denial, and is unnecessary. It admits the discharge of the plaintiff by the building commissioners, but traverses the reasons for it assigned in the complaint. It was held on the demurrer that the commissioners always had absolute right to discharge the plaintiff, with or without reason. The reason is therefore immaterial, and on that ground an averment of it was stricken out of the original answer. And so all the averments of the first amended answer are immaterial or redundant.

The second amended answer pleads only the plaintiff’s discharge and the reasons for it, and is immaterial.

The third amended answer pleads generally payment of the plaintiff for all services up to the time of his discharge, and specially that he was paid five per cent, on the cost of the entire building except the south wing. These averments do not appear quite consistent, in view of the judgment on the demurrer, that the plaintiff, if entitled to recover, would be entitled to quantum valebat for his plan of the south wing, in addition to five per cent, on the cost of the building of which he superintended the construction. It is difficult to say whether or not the averment is intended to cover the plans of the entire building. If not, it still appears uncertain and evasive. The complaint pleads the cost of the building superintended by the plaintiff, and admits payments of less than five per cent, on the amount. A plea of payment, in excess of the payment admitted in the complaint, would be good. Martin v. Pugh, 23 Was., 184. An answer of payment, partial or total, should plead the amount paid; and especially in a case like this, where the amount payable is dependent on another amount also [386]*386traversable. It is impossible to tell here whether the averment goes upon a less cost of the building or a greater payment to the plaintiff. If the original answer had contained an averment so framed, the court would have granted a motion of the plaintiff to make it more definite and certain. And it would be improper to allow so ambiguous an issue by way of amendment. Indeed, as there is a subsequent averment in this answer attacking the value of the plaintiff’s plan of the building, it may be that the general averment of payment is intended to go upon a quantum merwit for all the plaintiff’s services.

Put this answer is not confined to payment. It proceeds, in not very apparent connection, to aver that the plaintiff did not superintend the construction of the south wing, which is admitted in the complaint; that he did not furnish working drawings or specifications, but only a general plan of the south wing, an averment unnecessary with the general denial; that the general plan of the south wing was a duplicate of the general plan of the north wing, and became the property of the state in 1870, manifestly immaterial; that the building constructed on the plaintiff’s plan was not as represented by the •plaintiff, and did not answer the purpose for which it was constructed ; and that therefore the plaintiff’s, general plan for .the south wing was worthless, and only partially used. So far as these averments bear on the quantum valebat of the plan of the south wing, that is, on the amount of the plaintiff’s damages, they are, of course, unnecessary. So far as they bear on the plaintiff’s responsibility for his plans, their materiality will be more conveniently considered later. It is sufficient to say here that the third amended answer properly raises no material issue.

The fourth amended answer denies that the state has ever refused to pay the plaintiff his just claim, if any. The complaint avers, and the original answer admits, the presentation of the plaintiff’s claim to the legislature and the refusal of that body to allow it. This answer does not imply a traverse of [387]*387the averment in the complaint, and has the appearance of an evasive play upon the word just. If intended as a traverse of presentation to and refusal by the legislature, it is insufficient, being neither direct nor certain. The answer proceeds to aver the willingness of the board of trustees to settle with the plaintiff; the plaintiff’s refusal to appear before them for that purpose, and his failure to demand payment of them; denies their refusal to pay him; avers their performance of the contact; and denies waiver on their part of performance by the plaintiff. All this seems to go upon a misconstruction of the statute governing actions against the state in this court; appearing to substitute the hoard of trustees for the legislature. This answer presents no material issue.

The fifth amended answer is by way of counter claim. It states at the outset that by the plaintiff’s contract he agreed to furnish to the hoard of building commissioners correct and accurate estimates of materials put in the building by the contractors. This was probably intended as a construction of the superintendent’s duty under see. 9, ch. 39 of 1870, and is not a correct one. The pleading then avers that the plaintiff’s specifications required a certain number of feet of iron coil to he placed in the north wing of the building; that the plaintiff negligently certified to the building commissioners that the required quantity of coil had been put in, and that the commissioners, relying on his certificate, paid for it; that in fact a less quantity of coil had been put in; that it was the plaintiff’s duty under his contract to know the quantity actually put in; that the commissioners did not and could not then know the fact; and that it came to their knowledge after the plaintiff’s discharge.

Probably the building commissioners might have required the plaintiff, upon completion of the building, to inspect all its details, and to report to them whether or not they complied with the contract. In that case, however, there is nothing in the statute to warrant the commissioners to accept the super[388]*388intendent’s report as conclusive, or to discharge them from their duty to the state. Even the monthly estimates of the superintendent are subject to the examination and approval of the commissioners. The statute is silent úpon any duty of the superintendent upon the final completion of the building. It provides only that the commissioners shall certify the amount due to the contractor, including the reserved percentage. This made it the duty of the commissioners to see that the building was completed according to the builder’s son-tract. The commissioners might have required the plaintiff’s aid in the performance of this duty. But they could not devolve this or any other of their duties on their superintendent alone. They owed an active duty to the state throughout, in procuring a proper plan, in appointing a competent superintendent, in making a proper building contract, and in procuring the proper completion of the building. The employment of the plaintiff did not fulfill all these duties or discharge the commissioners from them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Wisconsin Telephone Co.
284 N.W.2d 41 (Wisconsin Supreme Court, 1979)
Vester J. Thompson, Jr., Inc. v. CITMOCO SERV. INC.
371 So. 2d 35 (Court of Civil Appeals of Alabama, 1977)
A. E. Investment Corp. v. Link Builders, Inc.
214 N.W.2d 764 (Wisconsin Supreme Court, 1974)
J. E. Hathman, Inc. v. Sigma Alpha Epsilon Club of Columbia
491 S.W.2d 261 (Supreme Court of Missouri, 1973)
Palmer v. Brown
273 P.2d 306 (California Court of Appeal, 1954)
U. S. F. & G. Co. v. Attala County Drainage Dist. No. 2
146 So. 460 (Mississippi Supreme Court, 1933)
Lower Baraboo River Drainage District v. Schirmer
225 N.W. 331 (Wisconsin Supreme Court, 1929)
Simpson Bros. Corp. v. Merrimac Chemical Co.
142 N.E. 922 (Massachusetts Supreme Judicial Court, 1924)
P. M. Hennessey Construction Co. v. Hart
170 N.W. 597 (Supreme Court of Minnesota, 1919)
Branting v. Salt Lake City
153 P. 995 (Utah Supreme Court, 1915)
Kortz v. Kimberlin
165 S.W. 654 (Court of Appeals of Kentucky, 1914)
Gratz v. City of Kirk-Wood
145 S.W. 870 (Missouri Court of Appeals, 1912)
Straus v. Buchman
96 A.D. 270 (Appellate Division of the Supreme Court of New York, 1904)
Haupt v. Independent Telegraph Messenger Co.
63 P. 1033 (Montana Supreme Court, 1901)
Choate v. Hoogstraat
105 F. 713 (Seventh Circuit, 1901)
Chapel v. Clark
76 N.W. 62 (Michigan Supreme Court, 1898)
Corey v. Eastman
44 N.E. 217 (Massachusetts Supreme Judicial Court, 1896)
Havens v. Germania Fire Insurance
27 S.W. 718 (Supreme Court of Missouri, 1894)
Rossiter v. Schultz
22 N.W. 839 (Wisconsin Supreme Court, 1885)
State v. Homey
44 Wis. 615 (Wisconsin Supreme Court, 1878)

Cite This Page — Counsel Stack

Bluebook (online)
43 Wis. 381, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shipman-v-state-wis-1877.