Lower Baraboo River Drainage District v. Schirmer

225 N.W. 331, 199 Wis. 230, 63 A.L.R. 1165, 1929 Wisc. LEXIS 223
CourtWisconsin Supreme Court
DecidedJune 24, 1929
StatusPublished
Cited by19 cases

This text of 225 N.W. 331 (Lower Baraboo River Drainage District v. Schirmer) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lower Baraboo River Drainage District v. Schirmer, 225 N.W. 331, 199 Wis. 230, 63 A.L.R. 1165, 1929 Wisc. LEXIS 223 (Wis. 1929).

Opinion

The following opinion was filed April 30, 1929:

Doerfler, J.

The contract for the construction of the drainage ditch, entered into between the commissioners and the contractor, among other things contained the following provision:

“All work under this contract shall be done to the satisfaction of the engineer employed by the party of the first part, who shall in all cases determine the amount, quality, acceptability, and fitness of the several amounts of work which are to be paid for hereunder, and shall decide all questions which may arise as to the measurements of quantities and the fulfilment of this contract cm the part of the party [234]*234of the second part, and shall determine all questions respecting the true construction or meaning of the plans and specifications. In case of dispute between the district engineer and the contractor, the decision of the state engineer shall be taken, and his determination and decision thereon shall be final and conclusive.”

It is strenuously argued by counsel for the contestants that this provision of the contract is invalid; that sec. 1379 — 10c of the Statutes contemplates that the court shall at all times have supervisory power over all acts of the commissioners and of all proceedings in the creation, establishment, and construction of the drainage district; that such a contract provision deprives the court of its supervisory power, and attempts to vest in the arbitrator a power which under' the district drainage law must reside in the commissioners and the court; that the authority thus created by the arbitration provision amounts to an invalid delegation of power, in that it substitutes the award of the arbitrator in place of that of the board and of the judicial decision of the court.

The important fundamental issue which is raised in connection with the alleged deprivation of the court of its jurisdiction, under circumstances like those involved in the instant case, is not a new one. It was raised in the case of Fox v. Masons’ F. Acc. Asso. of America, 96 Wis. 390, 71 N. W. 363, in connection with the submission to arbitration of questions arising under an accident insurance policy. It was there held;

"On grounds of public policy, all agreements between parties to submit the whole subject matter of their differences to arbitration, wholly stipulating away the rights of each or either party to resort to the tribunals created by the law of the land for a determination of such differences, are void and have been uniformly so held. (Citing Hamilton v. Liverpool & L. & G. Ins. Co. 136 U. S. 242, 10 Sup. Ct. 945; May, Insurance, § 492; Leach v. Republic F. Ins. Co. 58 N. H. 245.) Agreements to arbitrate special matters, such as, under an insurance policy, the amount of the loss, some[235]*235thing that does not go to the whole groundwork of the controversy, have been as universally sustained. (Citing Viney v. Bignold, L. R. 20 Q. B. Div. 172; Scott v. Avery, 5 H. L. Cas. 811; Delaware & H. Canal Co. v. Penn. Coal Co. 50 N. Y. 250; Reed v. Washington F. & M. Ins. Co. 138 Mass. 572; Wolff v. Liverpool & L. & G. Ins. Co. 50 N. J. L. 453, 14 Atl. 561; Hall v. Norwalk F. Ins. Co. 57 Conn. 105, 17 Atl. 356.)”

The arbitration clause in the instant case does not submit all matters in controversy to the arbitrators, with the effect of ousting the court of jurisdiction. The quoted contract provision belongs to the second class of cases above referred to, and not to the first. This provision of the contract in form is like innumerable contracts which have come before the court, where a third person, like an architect or an engineer, is appointed, who possesses expert knowledge upon the subject, and who is ordinarily better able to solve the issues involved than the parties directly concerned. The findings of such arbitrators are not absolutely conclusive, but may be impeached for fraud, actual or constructive, by the courts. Keachie v. Starkweather D. Dist. 168 Wis. 298, 170 N. W. 236; Montgomery v. American Cent. Ins. Co. 108 Wis. 146, 84 N. W. 175; Borgnis v. Falk Co. 147 Wis. 327, 133 N. W. 209. In the Keachie Case, supra, it was held by this court: “The effect of a provision of this kind is not doubtful. It is well settled in the law. It is not void because it ousts the court of jurisdiction, as ea.rnestly contended by respondents.”

Counsel for the contestants rely largely upon the following Wisconsin cases: Shipman v. State, 43 Wis. 381, and Lauenstein v. Fond du Lac, 28 Wis. 336. In the Shipman Case, supra, a board of building commissioners was authorized' by ch. 39 of the Laws of 1870 to accept plans and specifications for the construction of a part of the Northern fjospital, and to supervise such construction. The law also provided for the appointment of a building superintendent to act in an [236]*236advisory capacity as an architect. It was held in that case that the commissioners were charged with the duty not only to procure a proper plan and to enter into a proper building contract, but to see that the building was completed according to such contract, and this duty they could not wholly devolve upon the superintendent. The court held:

“They [the commissioners] might have rejected the plans submitted and called for others. They were made the jüdges of his [the superintendent’s] plans and of their sufficiency. The commissioners, not the architect, had to determine the plan. . . . They were the judges of the sufficiency of his superintendence, and could have dismissed him at pleasure. . . . But so far as the plans were equally intelligible to the commissioners and the plaintiff, . . . the commissioners assumed responsibility for the plans when they adopted them. And so far as defects of construction in the building were equally open to detection by the commissioners and the plaintiff, on the completion of the building, and so far as these pleadings disclose, the commissioners assumed responsibility for them when they accepted the building.”

It will thus appear that under the express wording of the statute the sole duty of accepting plans and of supervising the construction vested in the commissioners. This duty could not be delegated on defects which were as equally detectable by the commissioners as by the superintendent. In other words, the opinion holds expressly that where the matter involved one of expert knowledge which was possessed by the superintendent but was not within the knowledge of the commissioners, the commissioners could have relied entirely upon the expert. Furthermore, in that case there was an express delegation of power and authority in the commissioners by virtue of the statute, which does not exist in the instant case.

In the Lauenstein Case, supra, the express power to purchase a schoolhouse site was by law vested in the common council and in a board of school commissioners, and it was there held that these two bodies alone could exercise such [237]*237powers, and that they could not be delegated to a board of public works without an express grant of legislative power so to do.

Sec. 1379 — 10c, sub. 1, of the Statutes of 1919 provides as follows:

“All proceedings under the drainage district law are equitable in their nature.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loren Imhoff Homebuilder, Inc. v. Lisa Taylor
2020 WI App 80 (Court of Appeals of Wisconsin, 2020)
Diversified Management Services, Inc. v. Slotten
351 N.W.2d 176 (Court of Appeals of Wisconsin, 1984)
Johnson v. Fireman's Fund Insurance Co.
272 N.W.2d 870 (Supreme Court of Iowa, 1978)
McKenzie v. Warmka
260 N.W.2d 752 (Wisconsin Supreme Court, 1978)
Wisconsin Employment Relations Commission v. Teamsters Local No. 563
250 N.W.2d 696 (Wisconsin Supreme Court, 1977)
Goldmann Trust v. Goldmann
131 N.W.2d 902 (Wisconsin Supreme Court, 1965)
City of Madison v. Frank Lloyd Wright Foundation
122 N.W.2d 409 (Wisconsin Supreme Court, 1963)
Jefferson County Drainage Board v. Baneck
59 N.W.2d 655 (Wisconsin Supreme Court, 1953)
Waller v. Waller
49 A.2d 449 (Court of Appeals of Maryland, 1946)
McDonald v. Pritzl
93 P.2d 11 (Idaho Supreme Court, 1939)
Joyce v. Sauk County
239 N.W. 439 (Wisconsin Supreme Court, 1931)
Koepke v. E. Liethen Grain Co.
236 N.W. 544 (Wisconsin Supreme Court, 1931)
Decker v. Ladish-Stoppenback Co.
234 N.W. 355 (Wisconsin Supreme Court, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
225 N.W. 331, 199 Wis. 230, 63 A.L.R. 1165, 1929 Wisc. LEXIS 223, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lower-baraboo-river-drainage-district-v-schirmer-wis-1929.