MECO SYSTEMS, INC., Plaintiff-Appellant,
and
Artisan Construction Services, Inc., Intervenor Plaintiff-Cross-Claimant-Respondent,
v.
DANCING BEAR ENTERTAINMENT, INC., Defendant,
Empire Bank, Defendant-Respondent,
and
William A.R. Dalton, Trustee for Empire Bank, Defendant-Respondent,
and
Delvan Mitchell Ceiling Company, John O'Neal d/b/a John O'Neal Sheet Metal, Table Rock Asphalt, and William J. Zickel, Intervenors-Respondents,
and
Ronald C. Middleton, et al., Defendants.

No. 23093.

Missouri Court of Appeals, Southern District, Division One.

February 14, 2001.
Motion for Rehearing and Transfer Denied March 22, 2001.
Application to Transfer Denied April 24, 2001.

*798 Lincoln J. Knauer and Lee J. Viorel, Springfield, for Appellant.

Joseph A. Bohrer, Springfield, for Respondent Artisan Construction Services, Inc.

Lynn C. Rodgers, Springfield, for Respondents Empire Bank and Trustee.

Douglas S. Evans and Robert G. Asperger, II, Springfield, for Respondents Delvan Mitchell and William J. Zickel Company.

Christopher J. Stark, Springfield, for Respondent John O'Neal.

Richard L. Schnake, Springfield, and David L. Smith, Branson, for Table Rock Asphalt, Inc.

SHRUM, Judge.

This appeal arises from a mechanic's lien case and suit for damages by MECO Systems, Inc. ("MECO") against Dancing Bear Entertainment, Inc. ("DBE"), owner of the Charley Pride Theater at Branson, Missouri. In a counterclaim, DBE sought liquidated damages per a contract clause because of MECO's alleged failure to timely complete construction. Other parties to this case who have filed briefs with this *799 court are Empire Bank (holder of first deed of trust), its trustee, and some of MECO's subcontractors who joined the litigation as intervenors. The trial court (a) denied MECO's request for a mechanic's lien, (b) entered judgment for MECO against DBE for unpaid construction costs, (c) rendered money judgments for subcontractors against MECO, (d) awarded liquidated damages to DBE and against MECO, (e) gave some subcontractors first lien status, and (f) denied MECO's claim for unjust enrichment. MECO appeals advancing multiple claims of trial court error. We affirm.

REVIEW STANDARDS

Review of mechanic's lien and contract suits is under Rule 84.13(d). White River Dev. v. Meco Systems, 806 S.W.2d 735, 736 (Mo.App.1991).[1] As that rule is construed, we are to affirm the judgment unless there is no substantial evidence to support it, the judgment is against the weight of the evidence, erroneously declares the law, or erroneously applies the law. Id. at 736-737. "A judgment is to be set aside because it is against the weight of the evidence only with caution and with a firm belief that the ... judgment is wrong." Id. at 737.

The phrase "weight of the evidence" refers to "its weight in probative value, not its quantity." Id. The weight of evidence is determined by its effect in inducing belief, not by mathematics. Id.

Appellate courts give due regard to the trial court's determination on the credibility of witnesses. Id. "The trial judge as the trier of fact can disbelieve testimony even where uncontradicted." Id.

FACTUAL SYNOPSIS—MECO'S MECHANIC'S LIEN CLAIM

On August 25, 1993, MECO and DBE entered into a contract under which MECO, a corporation, would build a theater at Branson, Missouri, for DBE, a corporation. The August 25, 1993, document (herein the "Main Contract") had two parts, namely, a "Standard Form of Agreement Between Owner and Contractor" produced by the American Institute for Architects ("AIA") and an "Amendment" prepared by DBE's lawyer. MECO's work under the Main Contract was described as "site preparation, parking lot paving, parking lot lighting, and construction of the Theater Building, complete." In return, DBE agreed to pay MECO for "Cost of the Work," defined as the cost of labor, materials, equipment, payments made under MECO's subcontracts, and incidental costs as described therein. Also, DBE agreed to pay MECO a contractor's fee of six and one-half percent of the total job cost.

When the AIA contract form was signed, the parties were awaiting a building permit from the city of Branson. Also, DBE's financing needs had not been met. The parties addressed these issues in the Amendment, as follows:

"2.... In the event [the] building permit is obtained prior to the close of [DBE's] construction financing, the date of commencement shall be no later than five (5) days following the date of closing of [DBE's] construction financing.
....
"7. The parties ... agree that the Agreement shall be contingent and conditioned *800 upon the closing and funding of all financing to be provided to [DBE] for acquisition of the site and construction of the improvements described herein."

On August 26, 1993, MECO obtained a grading permit. However, neither the financing nor building permit had been obtained by August 31, 1993. Accordingly, on August 31, 1993, DBE's lawyer sent a letter to MECO that provided, inter alia:

"[DBE's] financing contingency is not yet satisfied.... Although we do not expect any problems ... [DBE] is not yet in a position to waive the contingency for the closing of financing under the Addendum. However, [DBE] ... does not want to hold up MECO ... from its time schedules. Therefore, [DBE] has instructed me to advise [MECO] to proceed with grading and work under the contract for the next ten (10) days subject to a Stop Work Order in the event any problems arise in satisfying the financing contingencies. Proceeding in this manner, [DBE] will be responsible only for the work actually performed during this period of time until a Stop Work Order is issued."

DBE's letter advised MECO if it found the proposal agreeable, it should sign and return a copy of the letter to DBE. MECO did agree, signed the letter, and returned it as directed. MECO then commenced and worked on site preparation for ten days.

On September 10, 1993, DBE's lawyer wrote to MECO and authorized an additional ten days' work "pursuant to the terms of my letter of August 31, 1993, and the above-referenced contract and the Addendum thereto." As before, DBE cautioned that its "authorization [for ten days' site work] is without waiver of any provision in the contract or its addendum."

When the second ten-day period passed without DBE's financing in place, MECO wrote DBE on September 20, 1993, as follows:

"We understand you anticipate closing... the financing ... September 21, which will enable you to waive the [financing] contingency ... and release us to proceed with all buy-out of the project. We look forward to that release.
"In the meantime, please sign and return a copy of this letter authorization for MECO ... to order ... steel ... and Building parts....
"Signing of this letter will also authorize continuance of the site preparation past today's date...."

DBE signed and returned the letter to MECO with this notation: "Authorization to continue work extended to September 30, 1993 pursuant to terms of prior correspondence authorizing commencement of work."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ware v. Allen
128 U.S. 590 (Supreme Court, 1888)
Peacock Const. Co., Inc. v. Modern Air Conditioning, Inc.
353 So. 2d 840 (Supreme Court of Florida, 1977)
Bank of Washington v. McAuliffe
676 S.W.2d 483 (Supreme Court of Missouri, 1984)
Highland Inns Corp. v. American Landmark Corp.
650 S.W.2d 667 (Missouri Court of Appeals, 1983)
White River Development Co. v. Meco Systems, Inc.
806 S.W.2d 735 (Missouri Court of Appeals, 1991)
J. E. Hathman, Inc. v. Sigma Alpha Epsilon Club of Columbia
491 S.W.2d 261 (Supreme Court of Missouri, 1973)
Willman v. Beheler
499 S.W.2d 770 (Supreme Court of Missouri, 1973)
Barr v. Snyder
294 S.W.2d 4 (Supreme Court of Missouri, 1956)
Fidelity National Title Insurance Co. v. Tri-Lakes Title Co.
968 S.W.2d 727 (Missouri Court of Appeals, 1998)
Gauzy Excavating & Grading Co. v. Kersten Homes, Inc.
934 S.W.2d 303 (Supreme Court of Missouri, 1996)
Norman v. Ballentine
627 S.W.2d 83 (Missouri Court of Appeals, 1981)
Kracman v. Ozark Electric Cooperative, Inc.
816 S.W.2d 688 (Missouri Court of Appeals, 1991)
American Drilling Service Co. v. City of Springfield
614 S.W.2d 266 (Missouri Court of Appeals, 1981)
Weeks-Maxwell Construction Co. v. Belger Cartage Service, Inc.
409 S.W.2d 792 (Missouri Court of Appeals, 1966)
Cole v. Morris
409 S.W.2d 668 (Supreme Court of Missouri, 1966)
Juengel Const. Co., Inc. v. Mt. Etna, Inc.
622 S.W.2d 510 (Missouri Court of Appeals, 1981)
DEC Elec., Inc. v. Raphael Const. Corp.
558 So. 2d 427 (Supreme Court of Florida, 1990)
OBS Co., Inc. v. Pace Const. Corp.
558 So. 2d 404 (Supreme Court of Florida, 1990)
Hawkeye-Security Insurance Co. v. Davis
6 S.W.3d 419 (Missouri Court of Appeals, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
42 S.W.3d 794, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meco-systems-v-dancing-bear-ent-moctapp-2001.