enXco Development Corporation v. Northern States Power Company

758 F.3d 940, 2014 U.S. App. LEXIS 13032, 2014 WL 3361174
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 10, 2014
Docket13-1918
StatusPublished
Cited by5 cases

This text of 758 F.3d 940 (enXco Development Corporation v. Northern States Power Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
enXco Development Corporation v. Northern States Power Company, 758 F.3d 940, 2014 U.S. App. LEXIS 13032, 2014 WL 3361174 (8th Cir. 2014).

Opinions

SMITH, Circuit Judge.

enXco Development Corp. (“enXco”) and Northern States Power Co. (NSP) contracted for the construction of a wind-energy project in North Dakota. enXco did not obtain a permit by a date certain, thus failing to satisfy a condition precedent to the contract. NSP then terminated the contract. enXco suffered several million dollars in losses.

enXco sued NSP for breach of contract. The district court1 granted NSP’s motion for summary judgment. On appeal, enXco contends that the district court erred in granting NSP’s motion for summary judgment because the doctrines of temporary impracticability and disproportionate forfeiture prevent the district court from strictly enforcing the relevant condition precedent. We affirm.

I. Background

enXco develops renewable energy projects throughout the United States, especially solar and wind projects. NSP is an electric and gas company that provides energy to customers throughout Minnesota and the Dakotas.

enXco and NSP entered into two contracts in October 2008. The contracts in[942]*942volved a wind-energy-generation project in North Dakota known as the Merricourt Project (“Project”). The parties termed the first contract the Developed Wind Project Purchase and Sale Agreement (PSA). Under the PSA, enXco agreed to develop the Project site, which included obtaining the requisite permits. During this initial phase of the Project, enXco owned the Project’s real estate and assets. Upon closing of the PSA, NSP would essentially purchase the Project’s real estate and assets for $15 million.

The second, much larger contract was the Engineering, Procurement, and Construction Agreement (EPCA). Pursuant to the EPCA, NSP agreed to pay enXco over $350 million for engineering, procurement of infrastructure, construction, commissioning, start-up, and testing of the Project. The parties agree that one of the principal benefits of this two-contract structure was that neither party had an obligation to proceed with the EPCA until the parties closed the PSA, which would not occur unless the Project developed according to their expectations.

The PSA included various conditions precedent that each party had to satisfy prior to the “Long-Stop Date” set for March 31, 2011. According to enXco, the Long-Stop Date was not a point of contention during contract negotiations. In fact, enXco selected the actual date without argument from NSP. enXco contends that “[t]he purpose of a long-stop date is to serve as a milestone against which to measure whether a project is ‘buildable’ ... and such dates are regularly extended.” In fact, in two of the parties’ previous wind-farm projects, the parties agreed to modify their contracts to postpone the applicable long-stop date.

The PSA also provided that “[t]he obligation of [NSP] to consummate the transactions contemplated by this [PSA] shall be subject to fulfillment at or prior to the Closing of each of the following conditions.” One condition precedent required enXco to obtain a Certificate of Site Compatibility (CSC). The CSC is a permit that the North Dakota Public Service Commission (NDPSC) issues that must be obtained before the parties could begin construction on the Project. See N.D. Cent. Code § 49-22-02. The PSA also included a provision that stated “that in no event shall the Closing occur later than the Long-Stop Date.” It also included the following termination clause:

This Agreement may be terminated pri- or to the Closing: (i) by either [NSP], on the one side, or [enXco], on the other side, upon written notice to the other Party of such termination, in the event the Closing has not occurred or the conditions precedent to Closing in favor of the terminating Party have not been fulfilled or waived on or before the Long-Stop Date....

It also provided that termination could occur without any liability accruing to the terminating party. Finally, the EPCA provided that the parties could terminate the EPCA should they fail to close the PSA.

enXco had approximately 29 months after the execution of the contracts until the Long-Stop Date to obtain the CSC. Under North Dakota law, a party must submit a letter to the NDPSC, stating that it intends to construct an energy conversion facility. See N.D. Admin. Code 69-06-03-01. After an applicant like NSP submits this letter, it must wait one year before submitting its CSC application. See N.D. Admin. Code 69-06-03-01 (2011) (amended in 2013 to omit the one-year wait period). enXco requested and received from the NDPSC a waiver of the one-year requirement in January 2009; thus, enXco could have submitted its application as early as January 2009.

[943]*943A CSC application must demonstrate that the project would have a limited impact on endangered species. See N.D. Cent.Code § 49-22-09(10). Unfortunately for enXeo, the United States Fish and Wildlife Service (USFWS) warned enXeo that the Project could have a deleterious effect on two species of birds because of the proposed physical locations of the wind turbines. Chris Sternhagen, enXco’s Project Development Manager, testified that this problem delayed its submission of the CSC application. He would later testify, however, that the turbine layout actually “played very little impact as to the schedule.”

In any event, almost two years expired before enXeo submitted the CSC application in October 2010. Thus, enXeo had less than six months to obtain the CSC by the Long-Stop Date. North Dakota law, however, allowed the NDPSC to consider the completed CSC application for up to six months after its receipt. See N.D. Cent.Code § 49-22-08(5). Nonetheless, Sternhagen testified that a NDPSC staff member informed him that a decision would be reached in two-to-four months.

The NDPSC scheduled a statutorily mandated public hearing on the permit for December 21, 2010. Unfortunately, the hearing was postponed due to a snowstorm. The NDPSC conducted the hearing on February 10, 2011, but on March 17, 2011, the NDPSC discovered that the hearing occurred in the wrong county contrary to North Dakota law. See N.D. Cent.Code § 49-22-13(1). As a result, a new hearing had to be scheduled, but North Dakota law also required a 20-day public notice. See N.D. CentCode § 49-22-13(4). Thus, the hearing was not rescheduled to occur until after the Long-Stop Date. enXeo petitioned the NDPSC to waive the 20-day notice requirement. In support of this petition, Sternhagen informed the NDPSC that, unless the NDPSC waived the 20-day requirement, “NSP can terminate the [PSA] between the parties, effectively terminating this Project.” At the resulting NDPSC meeting on the petition, enXco’s counsel informed the NDPSC that “NSP would have the contractual ability to terminate April 1 and there’s nothing that we can do as enXeo to prevent that” if enXeo did not obtain the CSC prior to the Long-Stop Date. The NDPSC denied the petition. On April 1, 2011, NSP terminated the PSA and thus the EPCA as well after the Long-Stop Date passed. enXeo nonetheless obtained the CSC on June 8, 2011.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
758 F.3d 940, 2014 U.S. App. LEXIS 13032, 2014 WL 3361174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/enxco-development-corporation-v-northern-states-power-company-ca8-2014.