§ 49-22-08 — Application for a certificate - Notice of filing - Amendment - Designation of a site or corridor

North Dakota § 49-22-08
JurisdictionNorth Dakota
Title 49Public Utilities
Ch. 49-22Energy Conversion and Transmission Facility Siting Act

This text of North Dakota § 49-22-08 (Application for a certificate - Notice of filing - Amendment - Designation of a site or corridor) is published on Counsel Stack Legal Research, covering North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.D. Cent. Code § 49-22-08 (2026).

Text

site or corridor.

1.An application for a certificate must be in such form as the commission may prescribe, containing the following information:
a.A description of the size and type of facility.
b.A summary of any studies which have been made of the environmental impact of the facility.
c.A statement explaining the need for the facility.
d.An identification of the location of the preferred site for any electric energy conversion facility.
e.An identification of the location of the preferred corridor for any electric transmission facility.
f.A description of the merits and detriments of any location identified and a comprehensive analysis with supporting data showing the reasons why the preferred location is best suited for the facility.
g.A description of mitigative measures that w

Free access — add to your briefcase to read the full text and ask questions with AI

Related

enXco Development Corporation v. Northern States Power Company
758 F.3d 940 (Eighth Circuit, 2014)
5 case citations

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
North Dakota § 49-22-08, Counsel Stack Legal Research, https://law.counselstack.com/statute/nd/49-22-08.