Village of Minneota v. Fairbanks, Morse & Co.

31 N.W.2d 920, 226 Minn. 1, 1948 Minn. LEXIS 558
CourtSupreme Court of Minnesota
DecidedMarch 19, 1948
DocketNo. 34,569.
StatusPublished
Cited by18 cases

This text of 31 N.W.2d 920 (Village of Minneota v. Fairbanks, Morse & Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Village of Minneota v. Fairbanks, Morse & Co., 31 N.W.2d 920, 226 Minn. 1, 1948 Minn. LEXIS 558 (Mich. 1948).

Opinion

Frank T. Gallagher, Justice.

Appeal from an order denying plaintiff’s motion for amended findings or for a new trial.

On August 16, 1940, plaintiff, a municipal corporation, by its village council, entered into an agreement in writing with defendant, whereby the latter agreed to construct for the former an electric power plant and distribution system according to plans and specifications on file with the village clerk. Prior to the date of this agreement, the voters of the village had voted in favor of the plant, and the council had purchased a site for a powerhouse and engaged consulting engineers to prepare plans and specifications. Upon approval by the council of the plans and specifications for the plant and after submission of bids, defendant was awarded the contract. About six days after the execution of the contract, defendant filed its bond with the village clerk conditioned for the faithful performance of its part of the contract. The specifications provided that work under the contract should commence within ten days after filing the bond and should be completed within 180 days thereafter. Section 18 provides in part as follows:

“Should the contractor be delayed in the prosecution or completion of the work by the act, neglect or default'of the owner, or of any one employed by the owner, or by fire, or by general strikes, or for any other reason deemed sufficient by the Engineers, then the *3 time fixed herein for the completion of the work shall be extended for a period equivalent to the time lost by reason of any of the aforesaid causes. Such extensions of time shall be determined and fixed by the Engineer, but no such extension shall be made unless a demand is presented in writing to the Engineers within forty-eight hours of the occurrence of such delay.”

No application for an extension was made by either party. Plaintiff claims that this section is specific evidence that the parties contemplated delays beyond their control.

Prior to the execution of the written agreement of August 16, 1940, an action had been commenced against plaintiff by the Union Public Service Company, the public utility then serving the village, to obtain a declaratory judgment that it had a franchise with the village until September 1944. As a result of the commencement of that suit and before bids were received, the specifications were amended by inserting the following:

“Addendum No. 2.
“The Union Public Service Company, the Public Utility now serving the Village and its inhabitants, having instituted a lawsuit against the Village, claiming that it has a franchise for a period of five years from September, 1939, to furnish electricity to the Village and its inhabitants, the contractor will not be required to commence construction of the plant under these specifications until the said litigation has been finally determined in favor of the Village. If not so' determined, the contract shall be null and void.”

Work has never been commenced under the contract of August 16, 1940. The Union Public Service Company franchise suit was decided by this court in favor of the village on February 20, 1942. Union Public Service Co. v. Village of Minneota, 212 Minn. 92, 2 N. W. (2d) 555. On March 19, 1942, judgment was entered in the district court determining that the Union Public Service Company had no franchise rights in the village of Minneota. In the meantime, on December 8,1941, while the franchise case was pending in this court, the United States became engaged in war. On March 18, 1942, after *4 the determination of the franchise suit, plaintiff applied to the War Production Board at Washington for a preference rating certificate so as to permit defendant to construct the plant provided for in the contract. This application was denied on March 25, 1942, the following reason being assigned:

“Because of the acute shortage of critical materials needed for direct war use, it is suggested that you continue to operate with your present facilities.”

No further application was ever made by plaintiff for a preference rating certificate.

The trial court found that under the federal laws and regulations applicable in February and March 1942 and thereafter defendant could not lawfully perform the contract until such time as plaintiff could obtain a preference rating from the War Production Board. It further found that at all times from January 1942 until October 1945 regulations and orders of the War Production Board were in effect which prohibited performance of the contract without authorization from the board; that such authorization could not be obtained; and that it was impossible to commence construction of the plant during that period.

It is undisputed that wartime restrictions prevented performance of the contract before October 1945, at which time construction costs had increased considerably. Plaintiff contends, however, that it was the duty of defendant to perform after elimination of governmental priority restrictions and that defendant continued to represent to plaintiff until about December 1945 that it was anxious to perform the contract. Plaintiff also claims that it has incurred the costs of procuring a site in connection with the contract, amounting to $1,000, engineer’s fees in the sum of $2,231.57, $500 for preliminary survey, and costs of litigation approximating $1,000. It contends that these disbursements were all made in furtherance -of the contract and for the most part will be a total loss if the contract is not completed. Defendant argues that these expenses were necessarily incurred long before the contract was made between the parties, *5 since a site, plans and specifications, and an election were preliminary essentials of the project.

Plaintiff brought this action for a declaratory judgment that the contract is in full force and effect; that said contract by its terms was not discharged by reason of the intervention of wartime restrictions, but that only the time of performance was extended until the removal of such restrictions; and that defendant is under an obligation to perform its part of the contract and to complete the power plant and distribution system. Defendant calls attention to the court’s findings as to the regulations of the War Production Board which prohibited performance of the contract without authorization from the board, which authorization could not be obtained, and that as a result it was impossible for defendant to commence construction of the plant between January 1942 and October 1945, while the governmental restrictions were in force. Defendant contends that under the terms of addendum No. 2, if the Union Public Service Company franchise should be determined by the court to be in effect until September 1944 the contract between plaintiff and defendant was to be void, and that if the Union company failed in its claim of a franchise the contract was to be in effect. Defendant claims that by this provision plaintiff clearly, indicated that unless the municipal plant was in operation prior to September 1944 it would not proceed with the project. The trial court found:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fitness International, LLC v. City Center Ventures, LLC
9 N.W.3d 526 (Supreme Court of Minnesota, 2024)
In Re Mr. Movies, Inc.
287 B.R. 178 (D. Minnesota, 2002)
National Farmers Union Property & Casualty Co. v. Fuel Recovery Co.
432 N.W.2d 788 (Court of Appeals of Minnesota, 1988)
Barbarossa & Sons, Inc. v. Iten Chevrolet, Inc.
265 N.W.2d 655 (Supreme Court of Minnesota, 1978)
Colvig v. RKO General, Inc.
232 Cal. App. 2d 56 (California Court of Appeal, 1965)
Independent School District No. 877 v. Loberg Plumbing & Heating Co.
123 N.W.2d 793 (Supreme Court of Minnesota, 1963)
Automatic Alarm Corp. v. Ellis
99 N.W.2d 54 (Supreme Court of Minnesota, 1959)
Powers v. Siats
70 N.W.2d 344 (Supreme Court of Minnesota, 1955)
STANDARD CONSTRUCTION CO. INC. v. National Tea Co.
62 N.W.2d 201 (Supreme Court of Minnesota, 1953)
Marquardt v. Stark
58 N.W.2d 273 (Supreme Court of Minnesota, 1953)
Monite Waterproof Glue Co. v. Sawyer-Cleator Lumber Co.
48 N.W.2d 333 (Supreme Court of Minnesota, 1951)
Pacific Trading Co., Inc. v. Mouton Rice Milling Co
184 F.2d 141 (Eighth Circuit, 1950)
Wilcox v. Nelson
35 N.W.2d 741 (Supreme Court of Minnesota, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
31 N.W.2d 920, 226 Minn. 1, 1948 Minn. LEXIS 558, Counsel Stack Legal Research, https://law.counselstack.com/opinion/village-of-minneota-v-fairbanks-morse-co-minn-1948.