Independent School District No. 877 v. Loberg Plumbing & Heating Co.

123 N.W.2d 793, 266 Minn. 426, 1963 Minn. LEXIS 751
CourtSupreme Court of Minnesota
DecidedOctober 11, 1963
Docket38,735
StatusPublished
Cited by54 cases

This text of 123 N.W.2d 793 (Independent School District No. 877 v. Loberg Plumbing & Heating Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Independent School District No. 877 v. Loberg Plumbing & Heating Co., 123 N.W.2d 793, 266 Minn. 426, 1963 Minn. LEXIS 751 (Mich. 1963).

Opinion

Rogosheske, Justice.

Plaintiff, upon dismissal of its action as to certain defendants, appeals from an order denying its motion for a new trial.

The problem presented concerns the interpretation of a building construction contract to ascertain the intention of the parties with respect to the contractor’s liability for alleged negligence in causing a fire which extensively damaged a school building after the construction was substantially completed and the budding was accepted and in use by plaintiff.

In the spring of 1956, plaintiff entered into a contract with Patch and Erickson, architects, relating to the construction of a new elementary school in the city of Buffalo, Minnesota. Under this contract, plans and specifications were drafted by Robert D. Hanson, an employee of Patch and Erickson. After approval of such plans by the school board of plaintiff, bids were solicited and accepted. Thereafter, in November 1956, pursuant to the contract with the architects, construction contracts incorporating the plans and specifications were similarly drafted and executed by the plaintiff and the successful bidders. Defendant Loberg Plumbing & Heating Company (hereinafter Loberg) contracted for the plumbing and heating work. Defendants Edward S. Kern and Frank Persons, doing business as The Kerntile Company, furnished the acoustical tile used in the construction as a subcontractor.

In September 1957, the building was occupied for school purposes although construction was not completed. On November 13, 1957, plaintiff, by its school board, inspected the new building and accepted it as completed, subject to “punch lists” of certain items which inspection revealed were to be corrected by various contractors, including Loberg, before final payment. On December 27, 1958, Lo-berg’s “punch list” items were certified as completed, and final payment was authorized and made to Loberg shortly after January 20, *428 1958. Sometime after payment, on January 30, 1958, a leak developed in the plumbing. Plaintiff called upon Loberg to make repairs in accordance with § 2.30 of the construction contract under which the contractors guaranteed all workmanship and material for a period of one year after acceptance of the work. (The guarantee required the contractors, upon notice, to immediately proceed to repair any defects or replace any faulty material during the guarantee period.) Sometime after completion of the repairs, a fire occurred which damaged the building to the extent of $173,366.92.

At the time of the fire, plaintiff was insured against loss by fire and other named perils under several policies of insurance in which it alone was named as insured. After the insurers had made full payment for all damages claimed, plaintiff commenced this action against Loberg, one of it employees, several other contractors, and the architect, alleging that the fire was caused by negligence in repairing the defect in the plumbing and in specifying and installing nonfireproof acoustical the. Defendants denied liability and interposed various defenses, including the defense that the terms of the construction contract exonerated them from liability to plaintiff for damage or destruction of the property by fire, however caused. The two defendants involved in this appeal also counterclaimed for damages claimed to result from plaintiff’s breach of the construction contract by fading to maintain fire insurance in which they were named as joint insureds with the plaintiff. 1 As the matter comes before us, we are concerned solely with reviewing the trial court’s decision that the contract exonerated the defendants from liability for negligently causing the fire. The court, with the parties’ acquiescence, declined at this time to rule on the merits of defendants’ counterclaim.

From the evidence submitted at trial, the court determined that Loberg’s repair of the leaking pipe, although after completion, accept- *429 anee, and payment, was in the performance of a contractual obligation; that the parties to the contract intended to impose upon plaintiff the obligation to maintain fire insurance, with the contractors named as joint insureds; and that they also intended to exonerate the contracting parties from any liability for damages by fire resulting from any party’s negligence. The court thus concluded to dismiss plaintiff’s action on the merits without prejudice to defendants’ counterclaims. 2 The pertinent provisions of the contract are as follows:

“2.8 Owner
“The term ‘Owner’ as used in this specification refers to Independent School District No. 23, Buffalo, Minnesota.
* * * * *
“2.21 Terms of Payment
“On or after the first day of each month during the progress of the work, each Prime Contractor shall submit to the Architect an Application for Payment (ALA Form 702) and a Certificate for Payment (ALA Form 703). Both forms are available from the Architect and will be submitted in quadruplicate. The Application for Payment will be based on the Contractor’s Cost Breakdown and will include all labor accomplished and materials incorporated in the work or delivered to the site since the previous Application for Payment was made.
“Upon approval by the Architect, the Application and Certificate for Payment will be forwarded to the Owner, who will pay 90% of the amount of the Application and will retain 10%. The 10% retained will be paid within 30 days after the substantial completion of the work, provided the work be then completed and accepted by Owner and the contract fully performed.
*****
*430 “2.30 One Year Guarantee
“For a period of one year after acceptance of the work, each Prime Contractor shall guarantee all workmanship and materials included in his contract and if, during guarantee period, any defects or faulty materials are found, he shall immediately upon notification from Architect, proceed to replace and repair same without cost to Owner, together with any damage to finish, fixtures, equipment or furnishings that may be damaged due to defective work or materials. Considerations will be allowed for natural use of building during this time. “2.31 Contractors Liability Insurance
“Each Prime Contractor shall maintain such insurance as will protect him from claims under the Workmen’s Compensation Acts and from claims for damages because of bodily injury, including death, which may arise both out of and during operations under this contract, whether such operations be by himself or by any subcontractor or anyone directly or indirectly employed by either of them. This insurance shall be written for not less than the limits of liability as specified as follows:
“1. Contractors Public Liability Insurance $100-300 thousand.
“2. Contractors Contingent Liability Insurance $100-300 thousand.
“3. Property Damage Insurance $50-100 thousand.
“4. Automotive Insurance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gary Carlson v. Ray Barta
Court of Appeals of Minnesota, 2014
Allan Block Corp. v. County Materials Corp.
239 F.R.D. 523 (W.D. Wisconsin, 2006)
Microtek Medical, Inc. v. 3M Co.
942 So. 2d 122 (Mississippi Supreme Court, 2006)
Microtek Medical, Inc v. 3M Company
Mississippi Supreme Court, 2005
Airtel Wireless, LLC v. Montana Electronics Co.
393 F. Supp. 2d 777 (D. Minnesota, 2005)
Denelsbeck v. Wells Fargo & Co.
666 N.W.2d 339 (Supreme Court of Minnesota, 2003)
First Security Bank of Utah, N.A. v. Northwest Airlines, Inc.
43 F. Supp. 2d 136 (D. Massachusetts, 1999)
Grozdanich v. Leisure Hills Health Center, Inc.
25 F. Supp. 2d 953 (D. Minnesota, 1998)
Employers Mutual Casualty Co. v. A.C.C.T., Inc.
568 N.W.2d 530 (Court of Appeals of Minnesota, 1997)
Arrowhead Electric Cooperative, Inc. v. LTV Steel Mining Co.
568 N.W.2d 875 (Court of Appeals of Minnesota, 1997)
Christensen v. Eggen
562 N.W.2d 806 (Court of Appeals of Minnesota, 1997)
United States v. J & D Enterprises of Duluth
955 F. Supp. 1153 (D. Minnesota, 1997)
Hurlburt v. Northern States Power Co.
549 N.W.2d 919 (Supreme Court of Minnesota, 1996)
Barna, Guzy & Steffen, Ltd. v. Beens
541 N.W.2d 354 (Court of Appeals of Minnesota, 1995)
Current Technology Concepts, Inc. v. Irie Enterprises, Inc.
530 N.W.2d 539 (Supreme Court of Minnesota, 1995)
Hurlburt v. Northern States Power Co.
524 N.W.2d 546 (Court of Appeals of Minnesota, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
123 N.W.2d 793, 266 Minn. 426, 1963 Minn. LEXIS 751, Counsel Stack Legal Research, https://law.counselstack.com/opinion/independent-school-district-no-877-v-loberg-plumbing-heating-co-minn-1963.