Derby Road Building Co. v. Commonwealth, Department of Highways

317 S.W.2d 891, 1958 Ky. LEXIS 116
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedJune 13, 1958
StatusPublished
Cited by20 cases

This text of 317 S.W.2d 891 (Derby Road Building Co. v. Commonwealth, Department of Highways) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Derby Road Building Co. v. Commonwealth, Department of Highways, 317 S.W.2d 891, 1958 Ky. LEXIS 116 (Ky. 1958).

Opinion

STANLEY, Commissioner.

Derby Road Building Company contracted with the State Department of Highways to construct a certain part of the Watter-son Expressway in Jefferson County for the sum of $484,048.03. The work was to be commenced by November 3, 19S2, and completed by December 8, 19S3. Before the work could be started it was necessary that the right of way be cleared of electric, telephone, gas and water lines on, under and across the right of way. This suit was instituted by Derby against the Department and the several utility companies charging that completion of the work had been delayed beyond the stipulated date because the utility companies had failed to remove their installations and the Department had failed to provide a clear and unobstructed right of way. The complaint alleged that because of its inability to begin and complete the job on time the plaintiff had become liable for liquidated damages at the rate of $30 a day and had suffered additional damages of $75,000, the total being $117,258.-68, for which judgment was asked.

The court at first entered a summary judgment dismissing the complaint against the utility companies. The plaintiff filed an appeal from that order, but we held that the judgment was not appealable since there had been no complete and final adjudication of the case. Derby Road Building Company v. Louisville Gas & Elec. Co., Ky., 299 S.W.2d 122. During the course of the proceedings below the Department of Highways filed amended answers and third party complaints against the utility companies.

The present appeal by Derby is from a judgment which confirmed the previous summary judgment and on a motion of the Department dismissed the complaint in its entirety, the order reciting that all the multiple claims were being disposed of finally. The decision was based upon the conclusion that the Commonwealth and its agency are *893 immune from suit, and, particularly, that they may not be held liable for damages by implication of an indebtedness. The trial court’s opinion also points out that the possibility of becoming liable for liquidated damages does not afford a cause of action. It is here conceded that the claim of liquidated damages has gone out of the case since the Department extended the time for completing the job. There remains, however, the plaintiff’s claim of other damages for breach of contract by the Department, in having failed to have the right of way cleared in time for the contractor to have started and completed its work in accordance with its contract, the delay resulting in considerable damages being sustained. The action against the three utility companies rests on allegations of interference with the contract relation by having failed to remove their obstructions as they were obligated and notified to do.

We lay aside for the present the case against the utility companies, and turn our attention to the case against the Department of Highways and the Commissioner.

The appellant, Derby, maintains (1) that the cloak of immunity does not cover the liability asserted, and (2) that its cause of action does not rest upon any implied contract but (a) upon the terms of the ex'press contract with the Highway Department, or (b) if that be not sufficiently definite, then upon a condition which is implicit in every construction contract that the owner will have the premises in such shape that the contractor can perform his contract without hindrance or delay. This condition, it is argued, is an essential part of the express contract between the company and the Department.

On the other side the Department contends (1) that this is not such an action as can be maintained agaifast the Commonwealth or its agency, and (2) that the appellant’s rights and remedies must be determined by the express written contract between the parties without any implications.

The construction contract provided that the work would be done “in strict conformity with the plans and specifications therefor prepared by the Department of Highways,” stated to be attached and made a part of the contract the same as if expressly copied therein. The contract further says that the reference is to the “Standard Specifications for State and Federal road and bridge construction.” The complaint alleges “it was the duty of the Department of Highways and W. P. Curlin, Commissioner of Highways, to provide a clear and unobstructed right of way within which said construction contract might be performed.” The Department entered a general denial of “each and every affirmative allegation” of the complaint. The specifications referred to as an exhibit filed with the complaint are not in the record, although the main contract is so filed. Ordinarily an appellate court will not consider exhibits not actually and properly made a part of the record and shown therein although they may otherwise appear or are shown, as in a brief. Clark v. Cincinnati, N. O. & T. P. Ry. Co., 258 Ky. 197, 79 S.W.2d 704 ; 4A C.J.S. Appeal and Error § 1209. But the trial court’s opinion says that upon •request a copy of the specifications was placed before him. The appellees make no point of the omission from the record. On the contrary, the Department’s brief quotes and relies upon as one of its defenses an extract from the Standard Specifications. •We may, therefore, regard this as operating as a waiver and cure of the irregularity. Louisville Woolen Mills v. Kindgen, 191 Ky. 569, 231 S.W. 202, 207; 4A C.J.S. Appeal and Error §§ 1130, 1131. The quotation is as follows:

“Sect. 1.4.9. Right of Way.
“The right of way for the highway will be obtained by the Department prior to issuing the ‘Notice to Begin Work,’ and if the right of way for the highway has not been satisfactorily cleared of poles, pipe lines, conduits, fences, buildings, or other obstructions owned by private individuals or public *894 utilities, as may interfere with construction or maintenance of the road, the Commissioner may direct the Contractor to remove such obstructions as extra work in accordance with the provisions of Article 1.9.4., page 51.”

Even without this express provision of the contract, it may be said that a contract for the construction of a building or highway “implies as an essential condition that a site shall be furnished upon which the structure may be erected.” 9 Am.Jur., Building and Construction Contracts, § 16, citing in support, Guerini Stone Co. v. P. J. Carlin Construction Co., 248 U.S. 334, 39 S.Ct. 102, 63 L.Ed. 275. See, also, 12 Am. Jur., Contracts, § 239. This court recognizes the general principle that the omission from a contract of what is necessarily implied is immaterial. Slade v. City of Lexington, 141 Ky. 214, 132 S.W. 404, 32 L.R.A.,N.S., 201; Humphreys v. Central Kentucky Natural Gas Co., 190 Ky. 733, 229 S.W. 117, 21 A.L.R. 664. The implied condition or agreement as a prerequisite to the contractor performing his part of the contract is not to be confused with an implied contract, for a breach of which neither the state nor its agency in executing or performing a governmental function can be held liable in damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Invesco Institutional (N.A.), Inc. v. Paas
244 F.R.D. 374 (W.D. Kentucky, 2007)
CMI, Inc. v. Intoximeters, Inc.
918 F. Supp. 1068 (W.D. Kentucky, 1995)
First Nat. Bank of Louisville v. Lustig
809 F. Supp. 444 (E.D. Louisiana, 1992)
Steelvest, Inc. v. Scansteel Service Center, Inc.
807 S.W.2d 476 (Kentucky Supreme Court, 1991)
National Collegiate Athletic Ass'n v. Hornung
754 S.W.2d 855 (Kentucky Supreme Court, 1988)
Stearns & Foster Co. v. DePriest
587 F. Supp. 1041 (S.D. Ohio, 1984)
Illinois Central Gulf Railroad v. Graves County Fiscal Court
676 S.W.2d 470 (Court of Appeals of Kentucky, 1984)
Cesnik v. Chrysler Corp.
490 F. Supp. 859 (M.D. Tennessee, 1980)
University of Louisville v. Martin
574 S.W.2d 676 (Court of Appeals of Kentucky, 1978)
Henkin, Inc. v. Berea Bank & Trust Co.
566 S.W.2d 420 (Court of Appeals of Kentucky, 1978)
Walt Peabody Advertising Service, Inc. v. Pecora
393 F. Supp. 328 (W.D. Kentucky, 1975)
Brinkley & West, Inc. v. Foremost Insurance Company
499 F.2d 928 (Fifth Circuit, 1974)
Foley Construction Company v. Ward
375 S.W.2d 392 (Court of Appeals of Kentucky (pre-1976), 1963)
Commonwealth, Department of Highways v. Louisville Gas & Electric Co.
346 S.W.2d 536 (Court of Appeals of Kentucky, 1961)
St. Paul Dredging Co. v. State
107 N.W.2d 717 (Supreme Court of Minnesota, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
317 S.W.2d 891, 1958 Ky. LEXIS 116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/derby-road-building-co-v-commonwealth-department-of-highways-kyctapphigh-1958.