Cable Belt Conveyors, Inc. v. Alumina Partners of Jamaica

669 F. Supp. 577, 7 Fed. R. Serv. 3d 1210, 1987 U.S. Dist. LEXIS 1678
CourtDistrict Court, S.D. New York
DecidedMarch 5, 1987
Docket86 Civ. 7980 (WCC)
StatusPublished
Cited by11 cases

This text of 669 F. Supp. 577 (Cable Belt Conveyors, Inc. v. Alumina Partners of Jamaica) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cable Belt Conveyors, Inc. v. Alumina Partners of Jamaica, 669 F. Supp. 577, 7 Fed. R. Serv. 3d 1210, 1987 U.S. Dist. LEXIS 1678 (S.D.N.Y. 1987).

Opinion

OPINION AND ORDER

WILLIAM C. CONNER, District Judge.

Petitioners Cable Belt Conveyors, Inc. (“Cable Belt”) and Paul N. Howard Company, (“Paul Howard”) have moved, pursuant to the Federal Arbitration Act, 9 U.S.C. § 2 et seq. (1982), Section 206 of the Convention on the Recognition and Enforcement of Foreign Arbitral Awards, and Rule 42(a) and 81(a)(3), Fed.R.Civ.P., for an order consolidating the arbitration proceedings now pending before the American Arbitration Association between Paul Howard and Cable Belt (AAA Case No. 13-110-0452-85) and between Cable Belt and Alumina Partners of Jamaica (“Alpart”) (AAA Case No. 13-110-0113-86). Defendant has cross-moved for an order dismissing the petition on the grounds that: (1) this Court lacks the authority to order the consolidation of these arbitrations; (2) consolidation would be highly prejudicial to Alpart; (3) under applicable New York state law, any judicial applications involving the arbitration between Alpart and Cable Belt must be made in New York Supreme Court since a special proceeding has been commenced there; and *578 (4) collateral estoppel bars the petitioners from seeking this relief.

Background

On March 31,1981 Alpart and Cable Belt entered into a contract whereby Cable Belt agreed to supply and install a conveyor system to transport bauxite from Alpart’s mine to a storage dome at Alpart’s plant site in Manchester Plateau, Jamaica. The contract required Alpart’s express consent to the subcontracting of any part of the contract work by Cable Belt and required that Cable Belt make the terms and conditions of the main contract (so far as they were applicable) the terms and conditions of any such subcontract. On April 9, 1982, Cable Belt entered into a subcontract with Paul Howard for the installation and commissioning of the conveyor system described above, as well as certain related work. The subcontract contained an arbitration clause similar to that of the prime contract, though there is some dispute as to whether a partial copy of the subcontract sent by Cable Belt to Alpart included the provision relating to the arbitration of disputes which was contained in the subcontract.

As a result of costs allegedly incurred due to delays and disruptions in the subcontract work, Paul Howard demanded arbitration against Cable Belt before the American Arbitration Association in June 1985 for claims totalling approximately $33,000,-000 plus $12,000,000 in interest costs. Cable Belt has denied liability to Paul Howard for its claims as stated but, in a separate demand for arbitration, has claimed over against Alpart for such portions of Paul Howard’s claims which may be justified pursuant to the terms of the Subcontract which are found to be the responsibility of Alpart. On January 23, 1986 Cable Belt served this demand for arbitration on Al-part pursuant to the arbitration clause in the Contract. All of Cable Belt’s claims against Alpart and all of Paul Howard’s claims against Cable Belt relate to the installation of the conveyor system for Al-part in Jamaica. Further, resolution of both Paul Howard’s claims against Cable Belt and Cable Belt’s claims against Alpart requires a determination regarding the responsibility as between Alpart and Cable Belt under Section 35(d) of the Subcontract (the “pass-through” provision) for the cost of delays, extra expenses and disruptions of work on such project.

On February 10, 1986, Alpart moved by order to show cause in the Supreme Court of the State of New York to stay Cable Belt’s arbitration against it on the ground that Cable Belt had failed to satisfy a condition precedent to arbitration. That motion was denied on April 4, 1986. On appeal, Paul Howard moved for leave to intervene in the state court proceeding on the ground that it had a right to participate in a consolidated arbitration. Alpart opposed that motion which was denied by the Appellate Division, First Department on August 14, 1986. On October 14, 1986, the Appellate Division, First Department unanimously affirmed the trial court’s denial of Al-part’s motion to stay arbitration and ordered the arbitration to proceed. On December 16, 1986, that same court denied Alpart’s motion for reargument or leave to appeal to the Court of Appeals.

Discussion

The Court of Appeals for the Second Circuit has stated unequivocally that a federal court has the authority to compel the consolidation of arbitration proceedings. See, e.g., Compania Espanola de Petroleos, S.A. v. Nereus Shipping, S.A., 527 F.2d 966 (2d Cir.1975), cert. denied, 426 U.S. 936, 96 S.Ct. 2650; 49 L.Ed.2d 387 (1976); See also Sociedad Anonima de Navegacion Petrolera v. CIA de Petroleos de Chile, S.A., 634 F.Supp. 805 (S.D.N.Y.1986); In Matter of Czarnikow-Rionda Co., 512 F.Supp. 1308 (S.D.N.Y.1981); Lavino Shipping Co. v. Santa Cecilia Co., 1972 A.M.C. 2454 (S.D.N.Y.1972). The court in Nereus noted that “we think the liberal purposes of the Federal Arbitration Act clearly require that this Act be interpreted so as to permit and even to encourage the consolidation of arbitration proceedings in proper cases.” Id. 527 F.2d at 974-75. Consolidation has been deemed to be proper where there are common ques *579 tions of law or fact and a possibility of conflicting awards or inconsistent results. See Nereus, at 974; Sociedad Anonima, at 807; Matter of Czarnikow, at 1309. Accord Conoco Shipping Co. v. Norse Shipping Co. (PTE), 1983 A.M.C. 1146 (S.D.N.Y.1983). Further, to resist a motion for consolidation of arbitrations, a party must show prejudice that “is sufficiently substantial to outweigh the advantages of resolving the dispute in a consolidated proceeding.” Sociedad Anonima, 634 F.Supp. at 809 quoting Insco Lines, Ltd. v. Cypromar Navigation Co., 1975 A.M.C. 2233, 2235 (S.D.N.Y.1975); Vigo S.S. Corp. v. Mership Corp. of Monrovia, 26 N.Y.2d 157, 257 N.E.2d 624, 309 N.Y.S.2d 165, cert. denied, 400 U.S. 819, 91 S.Ct. 36, 27 L.Ed.2d 46 (1970).

In this action, the dispute between Cable Belt and Alpart as well as the dispute between Cable Belt and Paul Howard both center on the same construction project, and a principal issue in both proceedings is the question of who is responsible for extra costs incurred in the completion of the project. It is clear that numerous questions of law and fact are identical in both disputes.

Further, a resolution of these disputes in separate arbitrations could lead to inconsistent findings. Howard, the subcontractor, has demanded arbitration against Cable Belt to recover damages for the alleged cost of changes, delays and disruptions in the performance of its subcontract with Cable Belt. Cable Belt has denied liability to Howard for its claim as stated but has claimed over against Alpart for such portions of Howard’s claims as may be established as justified.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re United Pub. Workers, Afscme, Loc. 646
244 P.3d 609 (Hawaii Intermediate Court of Appeals, 2010)
Government of the United Kingdom v. Boeing Co.
998 F.2d 68 (Second Circuit, 1993)
Matter of Coastal Shipping and Southern Petroleum
812 F. Supp. 396 (S.D. New York, 1993)
P/R CLIPPER GAS v. PPG Industries, Inc.
804 F. Supp. 570 (S.D. New York, 1992)
Cable Belt Conveyors, Inc. v. Alumina Partners of Jamaica
717 F. Supp. 1021 (S.D. New York, 1989)
Bock v. Drexel Burnham Lambert Inc.
143 Misc. 2d 542 (New York Supreme Court, 1989)
Cable Belt Conveyors v. Alumona Partners
857 F.2d 1461 (Second Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
669 F. Supp. 577, 7 Fed. R. Serv. 3d 1210, 1987 U.S. Dist. LEXIS 1678, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cable-belt-conveyors-inc-v-alumina-partners-of-jamaica-nysd-1987.