North Moore Street Developers, LLC v. Meltzer/Mandl Architects, P.C.

23 A.D.3d 27, 799 N.Y.S.2d 485, 2005 N.Y. App. Div. LEXIS 8316
CourtAppellate Division of the Supreme Court of the State of New York
DecidedAugust 4, 2005
StatusPublished
Cited by7 cases

This text of 23 A.D.3d 27 (North Moore Street Developers, LLC v. Meltzer/Mandl Architects, P.C.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Moore Street Developers, LLC v. Meltzer/Mandl Architects, P.C., 23 A.D.3d 27, 799 N.Y.S.2d 485, 2005 N.Y. App. Div. LEXIS 8316 (N.Y. Ct. App. 2005).

Opinion

OPINION OF THE COURT

Sullivan, J.

Contrary to Supreme Court’s reasoning in dismissing the third and fourth causes of action, the liquidating agreement that plaintiff relies upon in asserting these claims, in accordance with the well-settled standard for such agreements, does not prohibit plaintiff, as owner, from asserting its own claims in addition to the nonparty general contractor’s pass-through claims against its architect, defendant herein. Nor does this well-settled standard prohibit plaintiff from assuming liability to the general contractor in the liquidating agreement, regardless of whether plaintiff had any independent contractual liability to the general contractor.

In 1998, plaintiff, the owner/developer, undertook a renovation and rehabilitation of its eight-story building. Pursuant to an April 24, 1998 written agreement, plaintiff retained defendant Meltzer/Mandl Architects to provide architectural and related design services for a fee of $615,000. Thereafter, by written agreement dated June 7, 1999, plaintiff retained nonparty R.C. Dolner, Inc. to perform the general contracting services for the project. Both parties and nonparty Dolner retained the services of numerous subcontractors, named as third-party defendants.

Plaintiff commenced this action in November 2001, alleging in the first two causes that it had sustained damages in the amount of $4.1 million due to defendant’s breach of the April 1998 agreement and its professional malpractice. The third and fourth causes of action asserted similar claims on behalf of Dolner in the amount of $2.45 million.

The first and second causes of action alleged that defendant’s breach of contract and negligence caused plaintiff to “(i) make substantial additional payments to the Contractor for change orders, as well as incur additional obligations for payment” due to defendant’s errors and omissions; “and (ii) incur substantial additional expenses including, but not limited to, real estate taxes, mortgage interest, common charges, general conditions!,] costs and attorneys’ fees.” The third and fourth causes of action alleged that as a result of defendant’s breach of contract and negligence, “the performance of the work by the Contractor [29]*29was delayed and impeded and was required to be performed in an inefficient, non-sequential, uneconomic and piecemeal manner causing the Contractor to incur additional and increased costs of construction for labor, supervision, materials, equipment and overhead.” These causes further recited that “Plaintiff has entered into a Liquidating Agreement with the Contractor, providing inter alia that Plaintiff admits and acknowledges liability to the Contractor, that the amount of such liability shall be liquidated to the amount of recovery by Plaintiff in this action, and that Plaintiff may prosecute said Contractor’s claims on its behalf.”

As the record shows, in or about April 2001, plaintiff entered into a liquidating agreement with Dolner, by which plaintiff admitted and acknowledged, inter alia, liability to Dolner for increased costs due to certain defects, errors or omissions caused by defendant; that a portion of any recovery by plaintiff against defendant would be passed through to Dolner; and that the amount of such liability would be liquidated to the amount recovered by plaintiff in any action against defendant asserting Dolner’s claims.

When the third-party defendants moved for dismissal of the third-party complaint, defendant cross-moved, inter alia, for summary judgment dismissing the third and fourth causes of action on the ground that they failed to state a cause of action as a matter of law, arguing that throughout the duration of the project, the owner and general contractor had blamed each other for causing the delays and cost overruns that were required to complete the project. Ultimately, the owner and general contractor entered into a completion contract in August 2001, wherein they agreed on terms to complete the outstanding work on the project, waiving any and all claims against each other subject to a “Liquidating Agreement.” Defendant alleged that notwithstanding the Liquidating Agreement, it was clear that “the third and fourth causes of action [sought] to recover damages solely on behalf of [the general contractor],” and “as [the general contractor] has no cognizable claim against [defendant], [plaintiff] cannot bring [the general contractor’s] claims on behalf of [the general contractor].”

Plaintiff opposed defendant’s cross motion, arguing that the lack of privity between the architect and the general contractor did not bar it from asserting the general contractor’s claims since the very purpose of a liquidating agreement is to bridge the privity gap. Plaintiff analogized the facts here to cases where [30]*30a general contractor confesses liability to an owner for damages caused by a subcontractor’s delay in performing work on the project, thereby enabling the owner to proceed directly against the subcontractor. Here, plaintiff argued, the owner has accepted responsibility for the general contractor’s damages caused by the owner’s architect. In addition, plaintiff argued, even absent the liquidating agreement, the owner could assert the fourth cause of action for professional malpractice on the general contractor’s behalf given the relationship, sufficiently equivalent to privity, that existed between the architect and the general contractor.

Supreme Court granted defendant’s motion for partial summary judgment dismissing the third and fourth causes of action, finding (i) that the liquidation agreement was unenforceable because plaintiff had asserted its own claims against defendant and not just claims on behalf of Dolner, and (ii) that the complaint failed to allege any delay caused by plaintiff, and that such delay exceeded either 50 or 70 days in the aggregate, as required under plaintiffs contract with Dolner, for plaintiff to be liable for any delay or suspension of the work. We reverse.

The courts of New York and other jurisdictions

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JDS Constr. Group LLC v. Copper Servs., LLC
2025 NY Slip Op 01576 (Appellate Division of the Supreme Court of New York, 2025)
A. Servidone, Inc./B. Anthony Constr. Corp., J v. v. State of New York
2019 NY Slip Op 82 (Appellate Division of the Supreme Court of New York, 2019)
RAD & D'Aprile Inc. v. Arnell Construction Corp.
49 Misc. 3d 189 (New York Supreme Court, 2015)
KSW Mechanical Services v. Johnson Controls, Inc.
992 F. Supp. 2d 135 (E.D. New York, 2014)
Travelers Casualty & Surety Co. v. Dormitory Authority-State
735 F. Supp. 2d 42 (S.D. New York, 2010)
Eastern Electric Corp. v. Shoemaker Construction Co.
657 F. Supp. 2d 545 (E.D. Pennsylvania, 2009)
RLI Insurance v. King Sha Group
598 F. Supp. 2d 438 (S.D. New York, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
23 A.D.3d 27, 799 N.Y.S.2d 485, 2005 N.Y. App. Div. LEXIS 8316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-moore-street-developers-llc-v-meltzermandl-architects-pc-nyappdiv-2005.