Morse/diesel, Inc. v. Trinity Industries, Inc. Mosher Steel Company, and Aetna Insurance Company

67 F.3d 435, 1995 U.S. App. LEXIS 27614
CourtCourt of Appeals for the Second Circuit
DecidedSeptember 27, 1995
Docket1860, 1791, Dockets 95-7063, 95-7069
StatusPublished
Cited by41 cases

This text of 67 F.3d 435 (Morse/diesel, Inc. v. Trinity Industries, Inc. Mosher Steel Company, and Aetna Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morse/diesel, Inc. v. Trinity Industries, Inc. Mosher Steel Company, and Aetna Insurance Company, 67 F.3d 435, 1995 U.S. App. LEXIS 27614 (2d Cir. 1995).

Opinion

PARKER, Circuit Judge:

Major construction projects generate major construction litigation. Management of either is perilous.

Morse/Diesel, Inc., the general contractor for the construction of the Marriott Marquis Hotel in Manhattan’s Times Square, sued the project’s structural steel subcontractor, Mosher Steel Company, a division of Trinity Industries, Inc. (collectively “Trinity”), and Trinity’s bonding company, Aetna Insurance Company, for damages arising from late performance on the subcontract. Trinity counterclaimed. After a lengthy jury trial in the United States District Court for the Southern District of New York (Loretta A. Preska, Judge), judgment was entered in favor of Morse/Diesel against Trinity and Aetna. Trinity and Aetna appeal.

This litigation has gone on for over ten years, and has surely cost millions of dollars in attorneys’ fees and imposed innumerable demands on the district court. The jury trial alone lasted six and a half weeks. The work of the district judge in this case appears from our appellate distance to have been, in large part, exemplary. Nevertheless, we find that in one critical respect the jury was prevented from fairly evaluating Trinity’s counterclaim. Because the error may have infected the jury’s consideration of the case as a whole, we must reverse the judgment and remand for a new trial.

Background to Trinity’s Appeal

The steel subcontract for the hotel project was executed in August 1982. It called for Trinity (and its sub-subcontractor, Helena Erectors, Inc., which erected the steel members fabricated by Trinity) to complete the erection work within 13 months, excluding inclement weather. In fact, the job took 20 months, from January 1983 to September 1984, and the final Helena crane was not *438 removed from the site until December 1984. Responsibility for that delay is the central question in this litigation.

Morse/Diesel blamed Trinity, and produced evidence of fabrication errors, shipping mishaps, crane failures, and so on. Morse/Diesel sought damages of over $37 million, consisting primarily of the costs of instituting an acceleration program designed to “recapture” the delay, as well as losses suffered by the hotel owner, the architect, and other subcontractors. The jury substantially agreed with Morse/Diesel and awarded the company almost $26 million in damages, to which the court added an additional $27 million in prejudgment interest.

Trinity blamed Morse/Diesel, attributing responsibility for much of the delay to the project’s architect (John Portman & Associates) and structural engineer (Weidlinger Associates) (collectively “Architect”) who made, in Trinity’s estimation, unwarranted demands regarding the installation of certain special steel trusses, known as Vierendeel trusses, and the use of additional bracing during erection. Trinity also argued that inclement weather caused substantial delay. On appeal, Trinity contends that the district court unfairly limited its ability to present these two defenses.

Trinity also counterclaimed against Morse/Diesel for its own damages arising from additional work and delay in completing the subcontract, and appeals on the ground that the district court deprived it of a fair trial on the counterclaim. Further, Trinity claims the district court erred in refusing to allow Trinity’s expert to challenge Morse/Diesel’s evidence of damages. Finally, Trinity argues that the court miscalculated prejudgment interest.

We agree with Trinity that it was unfairly precluded from presenting its counterclaim to the jury. While it is not necessary to reach the other issues raised by Trinity’s appeal, we nonetheless address those issues below in order to provide guidance for proceedings upon remand.

Trinity’s Right to Recover Damages

Trinity based its counterclaim for damages against Morse/Diesel on Schedule B, paragraph 53, of the subcontract, which provides:

Should the Subcontractor be obstructed or delayed in the commencement, prosecution or completion of the work, without fault on his part, by action or inaction on the part of the Owner, Architect, Engineer or Contractor, or by changes in the work, the Subcontractor shall be entitled to include as cost the cost of labor, materials, equipment, supplies and other resultant costs occasioned by such delays and changes notwithstanding any other provision contained in this agreement.

(Emphasis added.)

By virtue of the “notwithstanding” clause, paragraph 53 overrides, in part, two “no-damages-for-delay” provisions of the subcontract. Article 16-G of the subcontract’s General Conditions provides:

Should the subcontractor be obstructed or delayed in the commencement, prosecution or completion of the work, without fault on his part, by the act, failure to act, direction, order, neglect, delay or default of the Owner, the Architect, the Contractor or any other contractor employed upon the work, or by changes in the work or by reason of fire, lightning, earthquake, enemy action, act of God or similar catastrophe, or by Government restrictions in respect to materials or labor, or by a strike or lockout beyond such subcontractor’s reasonable control, then he shall be entitled to an extension of time for a period equivalent to the time lost by reason of any or all of the causes aforesaid but no claim for extension of time on account of delay shall be allowable unless a claim in writing therefor is presented to the Contractor with reasonable diligence but in any event not later than within four (4) days after the commencement of such claimed delay. The mere presentation of such claim shall not establish the validity of the cause of delay or of the extension of time for completion. The subcontractor expressly agrees not to make, and hereby waives, any claim for damages, including those resulting from increased supervision, labor or material costs, on account of any delay, *439 obstruction or hindrance for any cause whatsoever, including but not limited to the aforesaid causes, and agrees that the sole right and remedy therefor shall be an extension of time.

(Emphasis added.) And Article 3.4 of the subcontract provides in part:

All loss or damage arising from any of the Work through unforeseen or unusual obstructions, difficulties or delays which may be encountered in the prosecution of same or through the action of the elements shall be borne by the Subcontractor.

Trinity requested a jury instruction that it could recover damages under paragraph 53 for costs associated with delays caused by others. Judge Preska denied the request. Instead, she explained to the jury that Trinity’s “claim for damages on account of delays allegedly caused by Morse/Diesel and its subcontractors” was an “area of ambiguity” in the subcontract. She noted Morse/Diesel’s contention “that such damages are not recoverable” because of Article 16-G of the General Conditions and Article 3.4 of the subcontract (both quoted above), and read the pertinent provisions to the jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tardif v. City of New York
991 F.3d 394 (Second Circuit, 2021)
Linde v. Arab Bank, PLC
882 F.3d 314 (Second Circuit, 2018)
Sparta Commercial Services, Inc. v. DZ Bank
680 F. App'x 17 (Second Circuit, 2017)
Beyer v. Anchor Insulation Co.
238 F. Supp. 3d 270 (D. Connecticut, 2017)
Patterson v. Raymours Furniture Co.
96 F. Supp. 3d 71 (S.D. New York, 2015)
Two Locks, Inc. v. Kellogg Sales Co.
68 F. Supp. 3d 317 (E.D. New York, 2014)
Chesapeake Energy Corp. v. Bank of New York Mellon Trust Co.
957 F. Supp. 2d 316 (S.D. New York, 2013)
Bank of New York v. First Millennium, Inc.
607 F.3d 905 (Second Circuit, 2010)
Levi Strauss & Co. v. Esprit US Distribution Ltd.
588 F. Supp. 2d 1076 (N.D. California, 2008)
DEUTSCHE BANK SECURITIES INC. v. Rhodes
578 F. Supp. 2d 652 (S.D. New York, 2008)
Armada Bulk Carriers v. ConocoPhillips Co., Inc.
505 F. Supp. 2d 621 (N.D. California, 2007)
Rahm v. Halpin (In Re Halpin)
370 B.R. 45 (N.D. New York, 2007)
CBS Broadcasting Inc. v. Jones
460 F. Supp. 2d 500 (S.D. New York, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
67 F.3d 435, 1995 U.S. App. LEXIS 27614, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morsediesel-inc-v-trinity-industries-inc-mosher-steel-company-and-ca2-1995.