This text of 265 A.D.2d 234 (F.W. Sims, Inc. v. T. Moriarty & Son, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
—Judgment, Supreme Court, New York County (Martin Evans, J.H.O.), entered September 2, 1998, after a nonjury trial, which, to the extent appealed from, limited plaintiffs recovery of delay damages to the principal sum of $4,095, unanimously affirmed, without costs.
We agree with the trial court that “total cost” method of calculating construction delay damages (see, Fehlhaber Corp. & Horn Constr. Co. v State of New York, 69 AD2d 362, 368) was inapplicable under the particular circumstances of this case, and that plaintiff did not otherwise sufficiently prove [235]*235delay-caused labor costs by non-speculative evidence (see, Mid-State Precast Sys. v Corbetta Constr. Co., 202 AD2d 702, 704, lv dismissed 84 NY2d 923, 86 NY2d 855). We have considered plaintiffs remaining arguments and find them unavailing. Concur — Sullivan, J. P., Nardelli, Tom, Mazzarelli and Friedman, JJ.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
265 A.D.2d 234, 696 N.Y.S.2d 453, 1999 N.Y. App. Div. LEXIS 10647, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fw-sims-inc-v-t-moriarty-son-inc-nyappdiv-1999.