Underpinning & Foundation Skanska, Inc. v. Travelers Casualty & Surety Co. of America

726 F. Supp. 2d 339, 2010 U.S. Dist. LEXIS 74249, 2010 WL 2899786
CourtDistrict Court, S.D. New York
DecidedJuly 23, 2010
Docket07 Civ. 7348 (THK)
StatusPublished
Cited by10 cases

This text of 726 F. Supp. 2d 339 (Underpinning & Foundation Skanska, Inc. v. Travelers Casualty & Surety Co. of America) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Underpinning & Foundation Skanska, Inc. v. Travelers Casualty & Surety Co. of America, 726 F. Supp. 2d 339, 2010 U.S. Dist. LEXIS 74249, 2010 WL 2899786 (S.D.N.Y. 2010).

Opinion

MEMORANDUM OPINION AND ORDER

THEODORE H. KATZ, United States Magistrate Judge.

Plaintiff Underpinning & Foundation Skanska, Inc. (“Plaintiff’ or “Underpinning”) brought this action seeking payment under a Payment Bond issued by Defendant Travelers Casualty & Surety Company of America (“Travelers”), for work performed on a construction project (“the Project”). The parties consented to proceed before this Court for all purposes, pursuant to 28 U.S.C. § 636(c).

Presently before the Court is Underpinning’s motion for partial summary judgment, pursuant to Rule 56 of the Federal Rules of Civil Procedure. Travelers has claimed various set-offs against Underpinning’s payment claim, for delays in the *341 Project that were allegedly caused by Underpinning. Underpinning argues in its motion that there is no basis in fact or law for most of Travelers’ set-offs. Underpinning therefore claims it is entitled to a reduction in the set-offs, and a minimum payment of $433,654.78, plus interest under the Payment Bond. For the reasons that follow, Underpinning’s motion is granted in part.

BACKGROUND

This action arises out of the construction of the pile foundation for two residential buildings at the Project, located at 270 Greenwich Street in Manhattan. The real property on which the construction took place was owned by 270 Greenwich Street Associates LLC (“the Owner”), a company controlled by Edward J. Minskoff Equities, Inc. (“Minskoff’). (See Defendant’s Statement of Material Facts Pursuant to Rule 56.1 of the Local Civil Rules of the Southern District of New York (“Def.’s 56.1 St.”), ¶ 2.)

The Owner hired HRH Construction LLC (“HRH”) as its general contractor for the Project. HRH entered into a written subcontract with Urban Foundation Engineering, LLC (“Urban”), to excavate the site and construct the foundation. (See id. ¶ 3.) Urban, in turn, entered into a subcontract or Purchase Order with Underpinning to perform pile driving work and related services for the Project. (See Plaintiffs Statement of Material Facts Pursuant to Rule 56.1 of the Local Civil Rules of the Southern District of New York (“PL’s 56.1 St.”), ¶ 1.) Under the Purchase Order, Underpinning was required to furnish approximately 600 Tapertube piles, each driven to a capacity of 240 tons. (See Def.’s 56.1 St. ¶ 5; Purchase Order, Exhibit (“Ex.”) A to David van Leeuwen Affidavit in Opposition to Plaintiffs Motion for Partial Summary Judgment, dated June 4, 2010 (“Leeuwen Aff.”).) The Purchase Order specified that Underpinning was to complete the driving of the production of the piles in six (6) weeks, using two rigs. (See Def.’s 56.1 St. ¶ 6; Leeuwen Aff. ¶ 12.) The agreed price for the Subcontract and five items of extra work performed by Underpinning was $3,411,450. (See PL’s 56.1 St. ¶ 2.)

Urban issued six checks to Underpinning, totaling $2,294,000, for Underpinning’s work on the Project. (See id. ¶ 3.) However, Urban failed to issue the remaining $1,117,050 to Underpinning, and, in this action, it is that deficiency that Underpinning seeks from Travelers, from whom Urban secured a Payment Bond. The Payment Bond covers the claims of Urban’s unpaid subcontractors on the Project. (See Declaration of Alan Winkler, Esq., dated Apr. 16, 2010 (“Winkler Deck”), Ex. D.)

One of Travelers’ defenses to Underpinnings’ claim for payment consists of a number of set-offs, denominated as Urban backcharges, with a total value of $1,151,761. (See Def.’s 56.1 St. ¶ 15.) Travelers argues that, because of delays caused by Underpinning, Urban incurred the additional costs contained in the backcharges. Travelers contends that Underpinning commenced driving the production piles on April 18, 2006, with one pile rig, rather than two. Travelers admits, however, that by June 23, 2 006, Underpinning had furnished and installed 626 of the 758 required piles 1 and, at that point, was on or close to schedule. After that date, Underpinning’s production ceased, until August 11, 2006 — a seven-week period. (See Def.’s 56.1 St. ¶¶ 7-8; Leeuwen Aff. ¶¶ 13- *342 14.) Urban and Travelers concede that one week of that delay was due to an industry-wide strike. (See Leeuwen Aff. ¶ 14.) But, they contend that the remainder of the delay was due to material supply problems Underpinning experienced. (See id. ¶ 15.) Underpinning argues that the delays were due to adverse field conditions and the absence of areas to store its piles. However, that issue is not the subject of the instant motion, and remains to be resolved at trial.

The instant motion is premised on the contention that Travelers failed to submit competent proof that Urban actually incurred certain of the costs that gave rise to the set-offs.

DISCUSSION

I. Summary Judgment Standards

Under Rule 56(c) of the Federal Rules of Civil Procedure, a motion for summary judgment should be granted “if the pleadings, the discovery and disclosure materials on file, and any affidavits show that there is no genuine issue as to any material fact and that the movant is entitled to judgment as a matter of law.” Fed. R.Civ.P. 56(c); see also Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 2552-53, 91 L.Ed.2d 265 (1986); Shannon v. N.Y. City Transit Auth., 332 F.3d 95, 98 (2d Cir.2003). The burden of demonstrating the absence of any genuine dispute as to material facts rests upon the party seeking summary judgment. See Adickes v. S.H. Kress & Co., 398 U.S. 144, 157, 90 S.Ct. 1598, 1608, 26 L.Ed.2d 142 (1970); Weinstock v. Columbia Univ., 224 F.3d 33, 41 (2d Cir.2000). Once a properly supported motion for summary judgment has been submitted, the burden shifts to the non-moving party to make a sufficient showing to establish the essential elements of the claims on which it bears the burden of proof at trial. See Hayut v. State Univ. of N.Y., 352 F.3d 733, 743 (2d Cir.2003); Peck v. Pub. Serv. Mut. Ins. Co., 326 F.3d 330, 337 (2d Cir.2003) (citing Celotex, 477 U.S. at 323, 106 S.Ct. at 2553).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

523 IP LLC v. CureMD.Com
48 F. Supp. 3d 600 (S.D. New York, 2014)
Agence France Presse v. Morel
293 F.R.D. 682 (S.D. New York, 2013)
American International Group, Inc. v. Bank of America Corp.
943 F. Supp. 2d 1035 (C.D. California, 2013)
MPM Silicones, LLC v. Union Carbide Corp.
931 F. Supp. 2d 387 (N.D. New York, 2013)
TURBON INTERNATIONAL, INC. v. Hewlett-Packard Co.
769 F. Supp. 2d 262 (S.D. New York, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
726 F. Supp. 2d 339, 2010 U.S. Dist. LEXIS 74249, 2010 WL 2899786, Counsel Stack Legal Research, https://law.counselstack.com/opinion/underpinning-foundation-skanska-inc-v-travelers-casualty-surety-co-nysd-2010.