Blackburn v. Texarkana Gas & Electric Co.

143 S.W. 588, 102 Ark. 152, 1912 Ark. LEXIS 24
CourtSupreme Court of Arkansas
DecidedJanuary 29, 1912
StatusPublished
Cited by9 cases

This text of 143 S.W. 588 (Blackburn v. Texarkana Gas & Electric Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blackburn v. Texarkana Gas & Electric Co., 143 S.W. 588, 102 Ark. 152, 1912 Ark. LEXIS 24 (Ark. 1912).

Opinion

Frauenthal, J.

This is an action instituted by J. E. Blackburn to recover the balance which he claimed was due him for drilling a well for the defendant. In the complaint it was alleged that the well was drilled and completed in compliance with the terms of a written contract, and that defendant had accepted same and made a partial payment thereon; that thereafter a verbal agreement was made, whereby the plaintiff was to drill the well to a greater depth, and that defendant agreed to pay the cost of the labor for such additional drilling, and of certain appliances which were furnished. He claimed that there was under the written contract payable to him the sum of $840, upon which he had received $400, leaving a balance of $440 thereon still due; that for the work and cost of certain appliances in drilling the well beyond the contract depth there was due $277.50; thus making a total of $717.50 due, for which he sought judgment.

The defendant denied that plaintiff had completed the well in compliance with the terms of the written contract, or that it had made any verbal contract for additional drilling, and claimed that it was not due the plaintiff anything for the drilling of the well. It also pleaded as a counterclaim the amount of $400 which it had paid to plaintiff, alleging that the same was paid 'upon condition that the well was or would be completed in full compliance with the terms of the written contract, which was not done; and it sought a recovery of the said counterclaim.

The case was tried by a jury, and the court gave a peremptory instruction by which it directed them to return a verdict in favor of defendant for the amount of such counterclaim, less a small cost of some appliances for which defendant admitted it had agreed to pay. The jury returned a verdict in accordance with said instruction.

The defendant owned a plant run by steam, and desired a well drilled which would supply it with a sufficient quantity of water for its boilers in the operation of its engines. Considering the evidence adduced upon the trial of the case most favorably to the contention of plaintiff, it established the following facts:

On November 17, 1909, the parties entered into a written contract for the drilling of a well, which is as follows:

“At a price of $4 per foot complete for all work, material and superintendence I propose to drill upon the premises occupied by your electric light plant, south of the Cotton Belt tracks at some point designated by your general manager, a well for water, same to be encased with the standard 8-inch well casing and to be equipped with one or more strainers as the necessities of the case may demand for getting the water from the different strata. I agree that at a depth not to exceed 145 feet that this will produce a minimum flow of 40,000 gallons of water per day of 24 hours. Should you decide to go beyond 145 feet, we guarantee to you that at a depth not exceeding 210 feet that the minimum flow of water will be 60,000 gallons per day of 24 hours. You to make no payment on this contract at all until it is shown to the satisfaction of your general manager that the well will furnish the amount of water stated as per above. We further agree that if we find it necessary to drill to any greater depth than 145 feet to obtain 40,000 gallons per day or 210 feet to obtain 60,000 gallons per day that we will make no charge for material beyond a depth of 145 feet for 40,000 gallons or 210 feet for 60,000 gallons. We are to commence immediately upon receipt of notice from you and work to be completed with all possible dispatch. You to furnish steam and water for drilling said well. ”

At the time this contract was entered into, plaintiff was actually a member of a partnership composed of himself and J. H. Schley, which firm was engaged in the well-drilling business; and the contract, though signed alone by plaintiff, was really made for the partnership. But it appears that subsequently the partnership was dissolved, or by mutual consent said Schley withdrew from it, and that Blackburn continued as its owner and representative. In the lower court no objection was made to Blackburn proceeding as the sole plaintiff, or to the counterclaim being asserted solely against him; no objection was made on account of any defect of parties, either as to the cause of action prosecuted solely by said Blackburn or as to the action on the counterclaim against him individually; nor is any such question raised here. We only note that Schley was a partner of Blackburn at the execution of the contract in order to explain the use of some terms in the contract indicating that the drilling was to be done by more than one person.

The plaintiff proceeded under said written contract to drill the well until December 11, 1909, when he claimed he had drilled it to a depth of 210 feet. He then requested defendant’s manager to measure the depth of the well, which he did and found that it had been drilled to the depth claimed. The water was then running out of the top of the well, and the plaintiff claimed that it would produce the quantity of water per day guaranteed by said contract. He asked for a payment upon the work in order to satisfy some indebtedness incurred by him during the drilling. It appears that the defendant’s manager then made a payment to him of $400; but we think that the undisputed evidence shows that defendant’s manager did not then accept the well or any work done thereon. The plaintiff testified that he told the manager that he had drilled the well to a depth of 210 feet, and that the manager then measured its depth and found his statement correct; that the manager then paid him $400 and said: “I don’t want to pay anymore until I let Mr. Markley know about the well.” He said that he did not want to take all the responsibility on himself in accepting the well. He further testified that no test had been made of the quantity of water which the well would produce, and that he did not know what amount of water it would furnish at the depth of 210 feet.

W. L. Wood, the defendant’s manager, testified that the plaintiff told him that he had the well down 210 feet, with full capacity as required by the contract, and that he desired him to measure it, which he did. He stated that the plaintiff represented that the well was all right, and that it would furnish the amount of water per day as guaranteed by the contract, and that this would be shown when the test thereof was made; that he paid the $400 relying upon this representation made by plaintiff, and with the understanding that the test which would thereafter be made would show that the well would produce the quantity of water guaranteed by the contract.

Neither of the parties testified that the defendant’s manager accepted the well, or any work that was done thereon; and it clearly appears from the undisputed evidence that the payment was only made pending the test that should be thereafter made of the capacity of the well.

About that time, or shortly thereafter, a question arose between the parties as to whether the plaintiff should encase the well for its entire depth. It appears that the plaintiff had drilled the well with a diameter of 10-5-8 inches from its top .to the depth of 75 feet, and for that depth had encased it with eight-inch well casing. At that depth he claimed that he had struck hard rock formation, and for that reason it was not necessary to encase the well to a further depth.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall v. Hawkins Oil & Gas, Inc.
715 S.W.2d 462 (Court of Appeals of Arkansas, 1986)
Morris v. Perkins
603 S.W.2d 711 (Missouri Court of Appeals, 1980)
Andriola v. Milligan
191 P.2d 716 (New Mexico Supreme Court, 1948)
Ylijarvi v. Brockphaler
7 N.W.2d 314 (Supreme Court of Minnesota, 1942)
Northcross v. Miller
43 S.W.2d 734 (Supreme Court of Arkansas, 1931)
Betts v. Brundidge
32 S.W.2d 818 (Supreme Court of Arkansas, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
143 S.W. 588, 102 Ark. 152, 1912 Ark. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blackburn-v-texarkana-gas-electric-co-ark-1912.