Voight v. Jones

404 N.W.2d 830, 1987 Minn. App. LEXIS 4273
CourtCourt of Appeals of Minnesota
DecidedApril 21, 1987
DocketC6-86-1277
StatusPublished

This text of 404 N.W.2d 830 (Voight v. Jones) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Voight v. Jones, 404 N.W.2d 830, 1987 Minn. App. LEXIS 4273 (Mich. Ct. App. 1987).

Opinion

OPINION

FORSBERG, Judge.

Appellant John Voigt sued respondents to foreclose a mechanic’s lien in the amount of $16,623.65, against property owned by D. Edward Jones and Mary R. Jones. The trial court found that appellant was entitled to no more than $2,000 for his work. We affirm in part and reverse in part.

FACTS

In August of 1984, respondent Mary Jones acquired student rental property which she wished to have remodeled before renting. Appellant walked through the house with respondents and gave an estimate of cost. Jones, acting through her brother, David Regner, then hired appellant to do the work. Although Regner himself was a contractor, he could not do the remodeling for his sister because of prior commitments. Respondents testified that they informed appellant that Jones had a remodeling budget of $10,000. They further testified that Voigt then told them that his work would cost around $6,000.00, not including subcontractors’ charges for *832 electrical, plumbing, heating and stucco work.

The contract prepared by appellant provided:

VOIGT CONSTRUCTION shall furnish all materials and perform all work shown on drawings and described in the specifications: Repair and remodeling of rental house to be done on material, labor, and subcontracting basis.
* * * * * ⅜
Subject to credit approval, we [Voigt Construction] agree to furnish labor and material specified above for the sum of $2,000.00: payment to be made as follows: progress billing.

(Emphasis added).

Regner and appellant testified that the $2,000 figure in the contract referred to a downpayment of one-third of the estimated cost of appellant’s work. Jones could not pay $2,000, so appellant instead accepted $500.00 as a downpayment, but did not change the figure in the contract.

Appellant billed respondents for his labor, materials and subcontractors' charges, in one final bill for $16,623.65. Jones paid appellant $6,500.00. Appellant claimed that his labor and materials came to $10,-740.97, and that the subcontractors’ charges were $5,205.42 and, therefore, he was still owed $10,123.65, and commenced this action.

The trial court found that the parties had a contract for $2,000.00. The court interpreted the term “progress billing” as requiring appellant to bill respondents for every $2,000 of work provided to respondents. The court concluded that since appellant had only billed respondents once, for a total of $16,623.65, he was not entitled to any amount over the initial $2,000, regardless of the reasonable value of his services.

ISSUES

1. Did the trial court err in finding that the parties had a contract for $2,000?

2. Is the evidence sufficient to support the trial court’s determination that appellant gave respondents a firm bid of $6,000?

3.Does the failure to provide progress billings relieve respondents of any liability to appellant beyond $2,000?

ANALYSIS

Appellant contends that he should be able to recover the figure billed, or at least the reasonable value of his services. In order for a mechanic’s lien to be enforceable, two requirements must be met: “[t]he services provided must be lienable improvements as described in Minn.Stat. § 514.01 (1984) and the lien must be enforceable against the interest in the property held by the defendant.” Korsunsky Krank Erickson Architects v. Walsh, 370 N.W.2d 29, 31 (Minn.1985). The underlying basis permitting the imposition of a lien on respondent’s property is their consent to the improvement of the property. Id. Respondents’ consent is inferred from the contract to perform the improvement. Laird v. Moonan, 32 Minn. 358, 360, 20 N.W. 354, 354 (1884).

Once it is clear that the lien is enforceable, the trial court must then determine the amount of the lien. Minn.Stat. § 514.-03, subd. 2 (1984) provides in pertinent part:

With respect to any contract or improvement * * * the lien shall be as follows:
(a) If the contribution is made under a contract with the owner and for an agreed price, the lien as against him shall be for the sum agreed upon.
(b) In all other cases, it shall be for the reasonable value of the work done, and of the skill, material, and machinery furnished. * * *

Id. (emphasis supplied).

The trial court found:

1. that respondents entered into an agreement with Voigt to complete some remodeling;
2. that Voigt received a $500 downpayment;
3. that the contract required appellant to submit bills to respondents whenever $2,000 or work and/or materials had been provided;
*833 4. that appellant failed to so bill respondents, despite their frequent requests that he do so;
5. that respondents did not have access to information regarding receipts for materials, labor records, and the names of the subcontractors;
6. that respondents paid appellant $6,500.

1. Contract for $2,000

The existence of a contract is primarily a question of fact to be determined by the trial court on the basis of the evidence presented and the surrounding circumstances. The trial court’s findings will not be reversed unless they are manifestly and palpably contrary to the evidence. Brekken v. Holien, 289 Minn. 95, 98, 182 N.W.2d 717, 720 (1970). Although the written contract itself would support the trial court’s finding of a contract for $2,000.00, at trial, the parties testified that the written contract did not encompass their total agreement. The parties testified that appellant estimated that his work would cost around $6,000, not including the subcontractors’ charges. The $2,000 figure merely represented a downpayment of one-third of the estimated cost. Therefore, the trial court’s finding that the parties had a remodeling contract for $2,000 is clearly erroneous.

2. Contract for $6,000

Respondents claim that even if the trial court’s finding of a contract for $2,000 is erroneous, appellant should not recover any sum over his estimated figure of $6,000. In its memorandum the trial court stated that respondents had not only informed appellant that they had a remodeling budget of $10,000, but had also been assured by appellant that they were within this budget. The court further stated that since Jones had apprised appellant of this budget, appellant knew that the $6,000 estimate was “more than an estimate.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paving Plus, Inc. v. Professional Investment, Inc.
382 N.W.2d 912 (Court of Appeals of Minnesota, 1986)
Malmin v. Grabner
163 N.W.2d 39 (Supreme Court of Minnesota, 1968)
State v. Helmenstein
163 N.W.2d 85 (North Dakota Supreme Court, 1968)
Korsunsky Krank Erickson Architects, Inc. v. Walsh
370 N.W.2d 29 (Supreme Court of Minnesota, 1985)
Brekken v. Holien
182 N.W.2d 717 (Supreme Court of Minnesota, 1970)
Ylijarvi v. Brockphaler
7 N.W.2d 314 (Supreme Court of Minnesota, 1942)
Laird v. Moonan
20 N.W. 354 (Supreme Court of Minnesota, 1884)

Cite This Page — Counsel Stack

Bluebook (online)
404 N.W.2d 830, 1987 Minn. App. LEXIS 4273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/voight-v-jones-minnctapp-1987.