O'Dea v. City of Winona

43 N.W. 97, 41 Minn. 424, 1889 Minn. LEXIS 376
CourtSupreme Court of Minnesota
DecidedSeptember 10, 1889
StatusPublished
Cited by14 cases

This text of 43 N.W. 97 (O'Dea v. City of Winona) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Dea v. City of Winona, 43 N.W. 97, 41 Minn. 424, 1889 Minn. LEXIS 376 (Mich. 1889).

Opinion

Collins, J.

The council of the defendant city, contemplating the grading and improvement of some two miles of one of its thoroughfares leading into the country, directed its engineer to prepare and .submit a plan or profile of the proposed work, with proper specifications, on which bids might be solicited. This was done May 28, 1888, and the council then advertised for bids. The plaintiff was the lowest bidder, whereupon the matter was referred to a committee, who subsequently advised and reported that the proposed work should be lessened and curtailed. On June 25th, a resolution was adopted by the council, awarding to plaintiff the contract for the improvement •of the street in question from one certain named point to another,— only a part of the distance covered by the plan and profile, the improvement of the balance having been abandoned, it seems. On July 7th, plaintiff and defendant entered into a contract for the work on that part of the street lying between the points named in the resolution, which was to be done in accordance with the plans and specifications above referred to, and to the satisfaction of the ■council and city engineer, at a certain price per cubic yard for each •of two distinct classes of work. The specifications also provided that [426]*426the work should be done subject to the approval of the city engineer and under his direction. The plaintiff claims to have complied with the terms of his contract, wh'ich defendant denies. The motion for a new trial, made after plaintiff recovered a verdict in the court below, having been denied, the defendant appeals.

.The defendant insists that the trial court erred in permitting the-plaintiff to introduce testimony tending to show that at a council meeting on J une 27th, when plaintiff’s bid was accepted, there were inquiries-made by members of the council, and answers by the city engineer in plaintiff’s presence, which indicated that there had not only been a-departure from the original plan of improvement as to its extent, but also as to its character; and that at some time subsequent to the presentation of the profile to the council and the commencement of the-work, the engineer directed and caused a new grade line to be laid down on the profile, — the principal result claimed from the alleged change-being a reduction or lowering of the fill exactly two feet; that is, the-top of the road-way would thereby be two feet lower, when completed,, than as first designed. It is undisputed that before, or perhaps at the time, plaintiff’s bid was accepted, the city council determined to-abandon all improvement of a part of the street. Just when or how this conclusion was reached is not apparent from the testimony, the-only record thereof or allusion thereto, so far as we have been able to discover, being in the resolution accepting the bid for a part of the-work, and in the minutes of the meeting before referred to. And from these minutes it might well be inferred that the changes intended by the plan to curtail the expense were much more radical than the single change in distance indicated by the resolution. The-contract between the parties made, so far as applicable to the work to be done, the plans and specifications submitted on May 28th a part of it. By the specifications, the work was to be performed under the-direction of the city engineer and subject to his approval, while in the contract it was provided that it should be done to the satisfaction of both council and engineer, as well as in accordance with the plans- and specifications. The chief controversy arising out of a consideration of this-alleged error is as to the grade line to which plaintiff contracted to bring the embankment or fill. The defendant insists-[427]*427that the work was not completed according to contract, because the grade was not brought to correspond with the line indicated upon the profile in red ink, while the plaintiff claims that another grade line was established on the profile,- as well as upon the ground, to which he worked; the practical difference being two feet, as before stated.

We are safe in asserting that no matter which of these lines should be regarded as the correct one, the grade itself would have to be fixed and indicated upon the ground by a person qualified, to some extent, in civil engineering. With nothing but the plans, profile, and specifications, the ordinary contractor or non-expert could not safely proceed with the work. Therefore, and in accordance with the universal custom, the work was laid out on the ground by means of grade marks placed upon telegraph poles, which were alongside the roadway as then travelled, instead of upon stakes, as is customary. This was done for the information and guidance of the plaintiff by an assistant of the engineer, but under his direction and supervision. And the grade thus established was in conformity with the new line alleged by plaintiff to have been laid down upon the profile. To these marks, and to the grade so fixed under the personal supervision of the city engineer, and with his express approval, the plaintiff, in good faith, brought and completed the fill, as he claims, and as the jurors evidently believed. The testimony in question tended to show that at some time prior to the commencement of the work the council had made or sanctioned the change in the grade; that the members knew of it; and that the engineer’s acts in reference thereto were not disapproved. It also had a tendency to show, among other things, that the plaintiff was acting honestly when performing the work in the manner directed by the defendant’s authorized and official representative. The contract does not seem to have been unprofitable. The work was to be paid for by the cubic yard, not by the job; and if, under circumstances like those existing here, a contractor, acting in good faith, receives his grade lines and directions from the engineer designated to establish the lines and give the necessary instruction, whose duty it is to look after the work and supervise its performance; who does this by attending upon its construction almost daily; who approves and finally certifies that it has been performed in accord[428]*428anee with the terms of the contract, — he must be permitted to recover. The fault, if there be one, is not chargeable to the contractor, but to and upon the party with whom he has dealt, and upon whose agents and officers he was authorized and compelled to rely.

It is further urged that the court erred in charging the jury that the plaintiff might recover without showing that the work had been performed to the satisfaction of the city council. In support of this position, we are cited to a number of cases wherein were involved contracts for the making of some article of adornment or convenience, or to gratify the taste or personal preferences of one of the parties, to his satisfaction, or subject to his approval; such, for instance, as Gibson v. Cranage, 39 Mich. 49, where plaintiff contracted to make a portrait; Brown v. Foster, 113 Mass. 136, in which plaintiff had agreed to make a suit of clothes for defendant; and Zaleski v. Clark, 44 Conn. 218, a case wherein it appeared that plaintiff’s contract was to make a bust of defendant’s deceased husband. In each of these cases, and in others of like character, it has been held that the party for whom the work is done may determine for himself, — may arbitrarily accept or reject as he chooses. And it is claimed that there is another class of cases, somewhat difficult to distinguish, perhaps, from those above mentioned, — the distinction being suggested in Wood Reaper Machine Co. v. Smith, 50 Mich. 565, (15 N W. Rep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCree & Company v. State
91 N.W.2d 713 (Supreme Court of Minnesota, 1958)
Steller v. Thomas
45 N.W.2d 537 (Supreme Court of Minnesota, 1950)
Mathis v. Holland Furnace Co.
166 P.2d 518 (Utah Supreme Court, 1946)
Park Construction Co. v. Independent School District No. 32
11 N.W.2d 649 (Supreme Court of Minnesota, 1943)
State Use Crawfordsville Special School District v. Huxtable
12 S.W.2d 1 (Supreme Court of Arkansas, 1928)
United States Trust Co. v. Incorporated Town of Guthrie Center
181 Iowa 992 (Supreme Court of Iowa, 1917)
Holt v. Sims
102 N.W. 386 (Supreme Court of Minnesota, 1905)
Murray v. Nickerson
95 N.W. 898 (Supreme Court of Minnesota, 1903)
Town of Birch Cooley v. First National Bank
90 N.W. 789 (Supreme Court of Minnesota, 1902)
Child Lumber & Manufacturing Co. v. Page
68 P. 373 (Washington Supreme Court, 1902)
Anderson v. Pringle
82 N.W. 682 (Supreme Court of Minnesota, 1900)
Walters v. Minneapolis, St. Paul & Sault Ste. Marie Railway Co.
79 N.W. 516 (Supreme Court of Minnesota, 1899)
Taylor v. Marcum
62 N.W. 330 (Supreme Court of Minnesota, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
43 N.W. 97, 41 Minn. 424, 1889 Minn. LEXIS 376, Counsel Stack Legal Research, https://law.counselstack.com/opinion/odea-v-city-of-winona-minn-1889.