Johnsen v. Wineman

157 N.W. 679, 34 N.D. 116, 1916 N.D. LEXIS 2
CourtNorth Dakota Supreme Court
DecidedMarch 24, 1916
StatusPublished
Cited by4 cases

This text of 157 N.W. 679 (Johnsen v. Wineman) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnsen v. Wineman, 157 N.W. 679, 34 N.D. 116, 1916 N.D. LEXIS 2 (N.D. 1916).

Opinions

Fisk, Ch. J.

Action to foreclose a mechanic’s lien. The complaint is in the usual form, claiming a balance due on the contract of $354.Y3 and $238.3Y for alleged extras furnished at defendant’s request, and praying for a foreclosure of the lien. The answer, among other things, alleges damages for delay in completing the contract at the rate of $5 per day from November 15, 1912, to April 1, 1913, or a total of $6Y5, such damages having been stipulated for in the contract. It further alleges that pursuant to agreement all matters of difference between the [119]*119parties were submitted to arbitration, and an award was made finding a balance due plaintiff of only $1.14, wbicb has been paid. The answer also contains a counterclaim for damages in the said sum of $675 for the delay in completing the contract as aforesaid, to which counterclaim plaintiff filed a reply denying the same.

At the conclusion of the trial the district court, among other things, found the following facts:

That on or about April 1, 1918, plaintiff and defendant being in controversy regarding the satisfactory condition of the work and completion of said contract, certain amounts claimed for extra work done upon said building by plaintiff, damages occasioned defendant by plaintiff’s failure to complete the work in a satisfactory manner, and within the time required by the contract, and the amount claimed to be due plaintiff by defendant, and other differences and disputes arising between them, entered an agreement to submit the entire controversy and all differences between them to three arbitrators, — one to be selected by the plaintiff, one by defendant, and the third by the two first chosen, who should act upon all matters of difference between plaintiff and defendant arising out of said AVork, and strike a balance between them, and in pursuance of said agreement to submit to arbitration three arbitrators were chosen in the manner aforesaid, who fully and fairly considered all matters of difference and dispute between plaintiff and defendant, having listened to claims and complaints of each party, and having carefully inspected the work and all matters involved or growing out of said Avork and contract, and having completed their work, ■and on March 29, 1913, being in readiness to make an award which was then in writing but not disclosed to the parties, the plaintiff and defendant in their presence again agreed in writing to which their names were respectively subscribed by them (on the bottom of the same paper ■on which such award Avas written) to abide by and accept Avhatever award should be made by said arbitrators, both plaintiff and defendant agreeing and understanding that said award then in writing, to which they attached their agreement, should determine the entire matter of •controversy betAveen them, and said arbitrators did thereupon and on March 29, 1913, malee an award, and notified plaintiff and defendant thereof, and published said award, by the terms of which it Avas found [120]*120that there was a balance due to the plaintiff from the defendant of the sum of $1.14, and the court finds that the amount so found to be due plaintiff by the arbitrators has' been paid to plaintiff by defendant. .That it was agreed by the parties that said arbitrators should decide and determine all questions and differences between them, and not the matter of extra work alone.

VII.

That the plaintiff performed extra work, for which he is entitled to-reasonable compensation outside of the regular contract price; the nature and amount of said extra work and its reasonable value as found by the court is as follows, and, together with the contract price, shows the total credits due to the plaintiff in the account as stated by the court:

Contract price ................................... $4,029.0(>

Boxing sewer pipe................................ 3.64

Frame and door — switch—electric lights.............. 3.60

Treads and raisers, front stairs...................... 30.50

One screen door.................................. 2.50-

Angle iron for windows............................ 20.80-

Hanging window, toilet room........................ 2.00

Moving skylight, allowed at........................ 10.Off

Varnishing stairs ................................. 12.00

Total credits to Jobeasen..........................'. $4,114.04

That the foregoing items of extra work include all additional or extra work and compensation, to which the plaintiff is entitled to a credit upon the contract; that the plaintiff claims to be entitled to other items of extra work, and the same are made a part of the statement of lien filed and claimed by him, but the court finds that none of said other items are proper credits to be allowed to the plaintiff.

[121]*121IX.

The court finds as credits due the defendant, including the amount of payments on the contract for all of the foregoing, the following:

Payments made to date ........................... $3,134.45

Damage to floor .................................. 100.00

Rental lost ...................................... 150.00

Ceiling.......................................... 15.00

Prism light over area not used...................... 82.00

Total credits to Wineman.......................... $4,081.45

And the court finds that, in addition to the said total sum of credits above, defendant is entitled to a balance for deficiency as above stated in iron stairway, bulletin board, and window areas which exceeds the balance of $2.61 in plaintiff’s favor.

X.

That because-of the submission to arbitration and the agreement to' abide thereby, the award of the arbitrators and the acceptance and performance thereof by defendant, defendant is not indebted in any sum whatsoever to the plaintiff.

The court further finds that on the merits, and having examined the items of difference and claims of the respective parties, and stated an account between them, that the defendant is not indebted to the plaintiff in any sum whatsoever.

Pursuant to these findings the court made conclusions of law favorable to defendant and entered judgment accordingly. From such judgment plaintiff has appealed, specifying that he desires a trial de novo of the entire case in this court.

We are convinced, both on the merits and because of the award of the arbitrators, that the judgment is right and must be affirmed. We choose to place our decision, however, upon the latter ground only, and will proceed to give as briefly as possible our reasons for adjudging that [122]*122the award returned by the arbitrators constitutes a barrier to plaintiff’s recovery. We take it to be well settled that the award, if valid, supersedes plaintiff’s recovery on the contract or for extras. Wiberly v. Matthews, 91 N. Y. 648; New York Lumber & Wood Working Co. v. Schnieder, 119 N. Y. 475, 24 N. E. 4.

Is the award valid and enforceable? The answer depends upon whether in this state there may be a common-law arbitration, or, in other words, whether the statutory provisions are exclusive, it being conceded that the proceedings failed to conform with the statutory prerequisites.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nelson Paving Co., Inc. v. Hjelle
207 N.W.2d 225 (North Dakota Supreme Court, 1973)
Nordenstrom v. Swedberg
143 N.W.2d 848 (North Dakota Supreme Court, 1966)
Copney v. . Parks
193 S.E. 21 (Supreme Court of North Carolina, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
157 N.W. 679, 34 N.D. 116, 1916 N.D. LEXIS 2, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnsen-v-wineman-nd-1916.