Jacobsen Construction Co. v. Structo-Lite Engineering, Inc.

619 P.2d 306, 1980 Utah LEXIS 1055
CourtUtah Supreme Court
DecidedOctober 1, 1980
Docket16208
StatusPublished
Cited by34 cases

This text of 619 P.2d 306 (Jacobsen Construction Co. v. Structo-Lite Engineering, Inc.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jacobsen Construction Co. v. Structo-Lite Engineering, Inc., 619 P.2d 306, 1980 Utah LEXIS 1055 (Utah 1980).

Opinions

STEWART, Justice:

This appeal by defendant is from a judgment awarding plaintiffs damages resulting from defendant’s faulty construction of a fiberglass storage tank. Defendant’s claim is that the jury’s finding of assumption of risk entirely precludes a judgment for plaintiff under both of plaintiffs’ theories of recovery: negligence and breach of express warranty. The central issues raised are (1) whether assumption of risk is a complete bar to plaintiffs’ recovery under Utah’s comparative negligence statute, Utah Code Ann. (1953), as amended, § 78-27-37, and (2) whether assumption of risk constitutes a defense to an action for breach of express warranty.

Plaintiffs Jacobsen Construction Company and Jelco, Inc. (“Jacobsen-Jelco”), acting as joint venturers, contracted with plaintiff Central Utah Water Conservancy District (“Conservancy District”) to build a water treatment plant. Jacobsen-Jelco entered into a subcontract with defendant Structo-Lite Engineering, Inc. (“Structo-Lite”) whereby Structo-Lite would provide six fiberglass chemical storage tanks constructed in accordance with the plans and specifications of the project engineers, third-party defendant Templeton, Linke and Associates.

Mr. Bevan, president of Structo-Lite, represented to Jacobsen’s agent that Struc-to-Lite would fabricate fiberglass tanks which would meet the plans and specifications of the project engineers. Mr. Bevan personally signed the purchase order which provided that Structo-Lite would supply the tanks in conformity with all engineering plans and specifications and that they would be warranted by Structo-Lite as to quality of workmanship and materials.

After defendant delivered the tanks to the job site, the project superintendent for Jacobsen-Jelco observed that some of the temporary supports used to maintain roundness had failed in transit, causing the tanks to appear elliptical at the open end and resulting in damage to the flanges located at the tops of the tanks. Mr. Bevan, upon being informed of these findings, indicated [308]*308that he would make the necessary repairs and install the remaining connections.

Prior to completion of the job, all six tanks were filled with water to test for leaks. Four of the six tanks were found to have minor leaks. The tank which subsequently failed was not one of the four. Structo-Lite, upon being informed of the leaks, made the necessary repairs.

Upon completion of the project and prior to operation, a seven-day test of the facilities was conducted. The plant, upon passing the test, was declared ready for operation.

Liquid alum was poured into one of the tanks in May of 1974. The following July a tank which subsequently exploded was filled with alum. The day after the chemical was placed in the tank, the plant operator noticed a minute leak. Before he could lessen the pressure, the tank exploded, spreading the liquid chemical throughout the entire building. Substantial damage to the heating and electrical system in the plant resulted.

Plaintiffs filed a complaint alleging negligence in the construction of the tanks and breach of contract and express warranty for failure to construct the tanks according to the specifications agreed upon. Structo-Lite filed a third-party complaint against Templeton, Linke and Associates for inadequate design and specifications.

After all testimony was submitted, the trial court directed a verdict against Struc-to-Lite on the ground that the evidence showed as a matter of law that the tanks had been negligently manufactured. Defendant then requested that special interrogatories be submitted to the jury. In answer to the interrogatories, the jury found Jacobsen-Jelco and Conservancy District had been contributorily negligent and had assumed the risk of the incurred damages. In apportioning the proximate contribution of each party toward the loss, the jury found Structo-Lite 70% liable and Ja-cobsen-Jelco and Conservancy District 20% and 10% responsible, respectively. The jury found Templeton, Linke and Associates, third-party defendants, not negligent.

Plaintiffs cross-appeal, contending that they were entitled to a finding, as a matter of law, that they were not contribu-torily negligent and that they had not assumed the risk of defendant’s negligence. The evidence shows that Jacobsen-Jelco was aware that the tanks were “out-of-round,” a visual inspection evidencing a three to four inch differential in tank diameter from the high to the low spot on the tank. Jacobsen-Jelco was also aware of an elliptical shape and damaged flanges located at the top end of the tanks resulting from failure of the bracing supports during transit to the water plant. Conservancy District noticed during construction of the tanks that they did not all have smooth surfaces and detected spots where the woven roving was not covered by the fiberglass matting. Further, after installation at the plant site, flat spots and irregularities on the tanks were noticed.

After the water testing revealed leaks in several of the tanks, plaintiffs, knowing that alum solution was heavier than water, proceeded to fill the tanks with alum solution without any further testing for tensile strength. Moreover, testing by the American Testing Laboratories at the direction of Jacobsen-Jelco revealed some deficiencies in the fabrication of the tanks. Plaintiffs’ knowledge of these defects must be viewed in light of the warranty given by defendants that the tanks would conform to the specifications of the general contract, including a tensile strength of 100,000 psi and a flexal strength of 150,000 psi with a “very smooth, hard surface and good finishing properties.”

We review the facts and the inferences to be drawn therefrom in favor of the verdict and conclude that the verdict as to contributory negligence is supported by the evidence. Furthermore, there is a reasonable basis in the evidence to find that plaintiffs unreasonably proceeded in light of their knowledge and appreciation of the risk created by defendant, and we thus uphold the jury’s finding of plaintiffs’ assumption of risk.

[309]*309We next address the contention raised by defendant that plaintiffs’ assumption of risk should completely bar recovery. The term “assumption of risk” has been historically defined and applied in different ways. Under the circumstances in this case, the term “assumption of risk” meant the voluntary, yet unreasonable, encounter of a known, appreciated risk. The complete bar to recovery which such conduct once constituted in a negligence action has been abolished by the Utah comparative negligence statute to avoid the harshness visited upon plaintiffs as a result of the all-or-nothing nature of the former rule of law. Section 78-27-37 provides:

Contributory negligence shall not bar recovery in an action by any person or his legal representative to recover damages for negligence or gross negligence resulting in death or in injury to person or property, if such negligence was not as great as the negligence or gross negligence of the person against whom recovery is sought, but any damages allowed shall be diminished in the proportion to the amount of negligence attributable to the person recovering. As used in this act, “contributory negligence” includes “assumption of the risk.”

The legislative intent to include assumption of risk within contributory negligence terminology and eliminate the use of the term is consistent with a recent trend established by other courts, legislatures, and legal commentators alike.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nixon v. Clay
2019 UT 32 (Utah Supreme Court, 2019)
Rutherford v. Talisker Canyons Fin., Co.
2019 UT 27 (Utah Supreme Court, 2019)
Machado v. Yacht Haven U.S.V.I., LLC
61 V.I. 373 (Supreme Court of The Virgin Islands, 2014)
Niemela v. Imperial Manufacturing, Inc.
2011 UT App 333 (Court of Appeals of Utah, 2011)
JCW Electronics, Inc. v. Garza
257 S.W.3d 701 (Texas Supreme Court, 2008)
Rothstein v. Snowbird Corp.
2007 UT 96 (Utah Supreme Court, 2007)
Fordham v. Oldroyd
2007 UT 74 (Utah Supreme Court, 2007)
Phelps v. Firebird Raceway, Inc.
83 P.3d 1090 (Court of Appeals of Arizona, 2004)
Interwest Construction v. Palmer
923 P.2d 1350 (Utah Supreme Court, 1996)
Lawson Ex Rel. Lawson v. Salt Lake Trappers, Inc.
901 P.2d 1013 (Utah Supreme Court, 1995)
Interwest Construction v. Palmer
886 P.2d 92 (Court of Appeals of Utah, 1995)
Perez v. McConkey
872 S.W.2d 897 (Tennessee Supreme Court, 1994)
Clover v. Snowbird Ski Resort
808 P.2d 1037 (Utah Supreme Court, 1991)
Donahue v. Durfee
780 P.2d 1275 (Court of Appeals of Utah, 1989)
Mikkelsen v. Haslam
764 P.2d 1384 (Court of Appeals of Utah, 1988)
Deats v. Commercial Security Bank
746 P.2d 1191 (Court of Appeals of Utah, 1987)
Stephens v. Henderson
741 P.2d 952 (Utah Supreme Court, 1987)
Arbegast v. Board of Education
65 N.Y. 161 (New York Court of Appeals, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
619 P.2d 306, 1980 Utah LEXIS 1055, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jacobsen-construction-co-v-structo-lite-engineering-inc-utah-1980.