Donatelli v. D.R. Strong Consulting Engineers, Inc.

312 P.3d 620, 179 Wash. 2d 84
CourtWashington Supreme Court
DecidedNovember 14, 2013
DocketNo. 86590-6
StatusPublished
Cited by30 cases

This text of 312 P.3d 620 (Donatelli v. D.R. Strong Consulting Engineers, Inc.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donatelli v. D.R. Strong Consulting Engineers, Inc., 312 P.3d 620, 179 Wash. 2d 84 (Wash. 2013).

Opinions

Fairhurst, J.

¶1 Steve and Karen Donatelli hired D.R. Strong Consulting Engineers Inc. to help the Donatellis develop their real property. Before development of the property could be completed, however, the Donatellis suffered substantial financial losses and lost the property in foreclosure. The Donatellis sued D.R. Strong for breach of contract; violation of the Consumer Protection Act (CPA), chapter 19.86 RCW; negligence; and negligent misrepresentation. D.R. Strong moved for partial summary judgment on the CPA and negligence claims. D.R. Strong argued that the negligence claims must be dismissed under the economic loss rule because the relationship between the parties was governed by contract and the damages claimed by the Donatellis were purely economic. The trial court and Court of Appeals held that as a matter of law, the Donatellis’ negligence claims were not barred. We affirm.

I. FACTUAL AND PROCEDURAL HISTORY

¶2 The Donatellis consulted with and hired D.R. Strong to help the Donatellis develop their King County real property into two short plats. According to Steve Donatelli, D.R. Strong’s representatives orally agreed to help the Donatellis with the county permitting process and to manage the project “through to [the] final recording of the short plats.” Clerk’s Papers (CP) at 65. In their complaint, the Donatellis alleged that D.R. Strong agreed to:

a. Perform the necessary surveys and analyses;
b. Create the required plans for, inter alia, soil erosion, storm water drainage;
c. Prepare the necessary reports and County permit applications; and
[88]*88d. Take all other actions necessary to get the short plats recorded with King County so that Donatelli could build houses on each lot.

CP at 2. According to the Donatellis, D.R. Strong represented that it would be able to finish the project within “approximately one and [one-half] years, if not less time.” CP at 4.

¶3 D.R. Strong’s first involvement in the project was apparently helping the Donatellis apply for preliminary approval for the project with King County pursuant to King County Code 19A.08.150. King County granted preliminary approval on October 4, 2002. In its letter granting preliminary approval, the county noted that the “preliminary approval is valid for a period of 60 months.” CP at 28.

¶4 On October 11, 2002, D.R. Strong sent the Donatellis a written contract for engineering services entitled “Revised Proposal for Engineering Services.” CP at 21. In the contract, D.R. Strong agreed to perform six phases of engineering services in exchange for an estimated fee totaling $33,150. The contract did not reflect whether D.R. Strong agreed to provide managerial services or to oversee the day-to-day operation of the project. The contract limited D.R. Strong’s professional liability to $2,500 or its professional fee, whichever was greater. Steve Donatelli apparently signed the contract on October 31, 2002, although he now claims that he did not know what he was signing.

¶5 According to the Donatellis, between October 2002 and October 2007, D.R. Strong assumed a managerial role over the project and worked closely with other contractors, builders, and vendors involved with the project. See CP at 67 (D.R. Strong “ran the daily operations of the Project.”), 68 (D.R. Strong “[was] running the show.”). Although in the written contract D.R. Strong estimated its fee would be $33,150, D.R. Strong allegedly charged the Donatellis “approximately $120,000 in costs and fees” over the course of the project. CP at 2.

[89]*89¶6 In October 2007, the preliminary approval expired and the project was still not complete. The expiration of the preliminary approval came as a complete surprise to the Donatellis. According to Steve Donatelli, employees of D.R. Strong “apologized many times, said that they screwed up, and that they would make everything right.” CP at 67. D.R. Strong began the process of obtaining a new preliminary approval for the project. Before D.R. Strong could obtain a new preliminary approval, however, the Donatellis suffered substantial financial losses and eventually lost the property in foreclosure.

¶7 The Donatellis sued D.R. Strong, claiming damages in excess of $1.5 million and alleging breach of contract, CPA violations, negligence, and negligent misrepresentation. D.R. Strong moved for partial summary judgment on the CPA, negligence, and negligent misrepresentation claims. D.R. Strong argued that the economic loss rule barred the Donatellis’ negligence claims. The trial court denied summary judgment on the two negligence claims but granted summary judgment on the CPA claims. The trial court found that “professional negligence claims can be stated even in the context of a contractual relationship.” CP at 95.

¶8 The Court of Appeals affirmed, holding that the independent duty doctrine did not bar the Donatellis from bringing negligence claims against D.R. Strong because professional engineers owe duties to their client independent of any contractual relationship. Donatelli v. D.R. Strong Consulting Eng’rs, Inc., 163 Wn. App. 436, 443, 261 P.3d 664 (2011). We granted D.R. Strong’s petition for review. Donatelli v. D.R. Strong Consulting Eng’rs, Inc., 173 Wn.2d 1025, 272 P.3d 851 (2012).

II. ISSUES

¶9 A. Did the trial court properly deny summary judgment as to the Donatellis’ negligence claim when there were genuine issues of material fact regarding the scope of D.R. Strong’s contractual obligations to the Donatellis?

[90]*90flO B. Did the trial court properly deny summary judgment as to the Donatellis’ negligent misrepresentation claim when the Donatellis alleged D.R. Strong misrepresented the time and expense necessary to complete the project and such representations induced the Donatellis to contract with D.R. Strong?

III. STANDARD OF REVIEW

f 11 Typically, we review an order on summary judgment de novo, engaging in the same inquiry as the trial court. Mohr v. Grantham, 172 Wn.2d 844, 859, 262 P.3d 490 (2011). Summary judgment is appropriate when “there is no genuine issue as to any material fact and . . . the moving party is entitled to a judgment as a matter of law.” CR 56(c). In this case, the trial court did not consider whether there were genuine issues of material fact underlying D.R. Strong’s motion for summary judgment because the motion presented a purely legal question — does the economic loss rule bar the Donatellis from bringing claims of negligence and negligent misrepresentation against D.R. Strong? We review alleged errors of law de novo. Jongeward v. BNSF Ry., 174 Wn.2d 586, 592, 278 P.3d 157 (2012) (citing State v. Breazeale, 144 Wn.2d 829, 837, 31 P.3d 1155 (2001)). To the extent we consider factual issues in this case, we consider all facts and reasonable inferences in the light most favorable to the Donatellis, the nonmoving party. Dowler v. Clover Park Sch. Dist. No. 400, 172 Wn.2d 471, 484, 258 P.3d 676 (2011).

IV. ANALYSIS

¶12 The question D.R. Strong presented before the trial court and the Court of Appeals was whether the economic loss rule barred the Donatellis’ negligence and negligent misrepresentation claims against D.R. Strong.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skanska Usa Building Inc., V. 1200 Howell Street, Llc
Court of Appeals of Washington, 2025
Busey v. Wells Fargo Bank NA
W.D. Washington, 2020
Kerry Zieger v. City Of Seattle
Court of Appeals of Washington, 2020
Jeanette Johnstone v. The City Of Seattle
Court of Appeals of Washington, 2019
Veridian Credit Union v. Eddie Bauer, LLC
295 F. Supp. 3d 1140 (W.D. Washington, 2017)
Vanishing Prices, Llc v. Bella's Voice
Court of Appeals of Washington, 2016
Pointe at Westport Harbor Homeowners' Ass'n v. Engineers Northwest, Inc., PS
376 P.3d 1158 (Court of Appeals of Washington, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
312 P.3d 620, 179 Wash. 2d 84, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donatelli-v-dr-strong-consulting-engineers-inc-wash-2013.