24CA0585 MG Dyess v MarkWest 05-22-2025
COLORADO COURT OF APPEALS
Court of Appeals No. 24CA0585 City and County of Denver District Court No. 18CV34745 Honorable Andrew J. Luxen, Judge
M.G. Dyess, Inc., a Mississippi corporation,
Plaintiff-Appellee,
v.
MarkWest Liberty Midstream & Resources, L.L.C., a Delaware limited liability corporation,
Defendant-Appellant.
JUDGMENT AFFIRMED
Division II Opinion by JUDGE FOX Gomez and Hawthorne*, JJ., concur
NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced May 22, 2025
Wheeler Trigg O’Donnell LLP, Meghan Frei Berglind, Denver, Colorado; Kilpatrick Townsend & Stockton LLP, Adam H. Charnes, Dallas, Texas; Kilpatrick Townsend & Stockton LLP, R. Lee Mann III, Atlanta, Georgia, for Plaintiff-Appellee
Snell & Wilmer L.L.P., James D. Kilroy, Ellie Lockwood, Denver, Colorado, for Defendant-Appellant
*Sitting by assignment of the Chief Justice under provisions of Colo. Const. art. VI, § 5(3), and § 24-51-1105, C.R.S. 2024. ¶1 In this construction contract dispute, defendant, MarkWest
Liberty Midstream & Resources, L.L.C. (MarkWest), appeals the
remand court’s order setting the amount of quantum meruit
damages awarded to plaintiff, M.G. Dyess, Inc. (Dyess), at
$31,702,197.14 and denying MarkWest’s motion for a new trial. We
affirm the district court’s judgment.
I. Background
¶2 MarkWest, a corporation that processes and transports
natural gas, entered into three contracts with Dyess, a pipeline
construction company, to install thousands of feet of pipeline. Each
contract concerned a particular length of pipeline, called a “spread,”
and each spread was assigned a lump sum payment amount and a
“mechanical completion date” after which liquidated damages would
accrue if the spread remained incomplete.
¶3 According to Dyess, MarkWest materially hindered its work,
increasing the costs and duration of the project. Dyess sued
MarkWest, asserting claims for breach of contract, negligent
misrepresentation, fraudulent nondisclosure, fraud, promissory
estoppel, and quantum meruit. MarkWest countered that it had
not hindered Dyess’s work and that Dyess had failed to achieve
1 mechanical completion by the contractual deadlines. MarkWest
counterclaimed for liquidated damages under the three operative
contracts. Both parties demanded a jury trial, and the multi-day
trial began February 3, 2020.
¶4 MarkWest maintained that Dyess’s promissory estoppel and
quantum meruit claims were not triable to the jury because they
were equitable claims. Dyess argued that these claims were legal
and that MarkWest had waived any objection to a jury trial.
¶5 Concluding that Dyess had brought “a mix of legal and
equitable claims,” the trial court submitted all the claims to the jury
under C.R.C.P. 39(c), which allows courts to “try any issue with an
advisory jury” in “all actions not triable by a jury.” The court also
noted that, if the jury awarded relief on an “arguably equitable
claim,” the court could allow further briefing.
¶6 The jury rejected Dyess’s claims, except its quantum meruit
claim, and awarded $26,039,641 in damages. It also awarded
MarkWest $4,500,000 in liquidated damages for its counterclaim.
MarkWest immediately moved to treat the jury’s quantum meruit
verdict as advisory, asking the court to decide the issue.
2 ¶7 MarkWest urged the court to conclude that MarkWest was not
liable to Dyess for the quantum meruit claim, and in the
alternative, that Dyess could only recover $934,436, the
approximate amount for the items listed in Jury Instruction 60 —
outlining the elements for a quantum meruit recovery. Dyess
countered that its expert had testified to overall losses equal to or
greater than the amount awarded, so the $26,039,641 verdict had
evidentiary support.
¶8 As relevant here, the trial court concluded that quantum
meruit is “an equitable theory of recovery . . . triable by the court
and not by a jury, subject to the right of the court to impanel an
advisory jury under C.R.C.P. 39(c).” It accepted the jury’s “advisory
verdict” — finding that MarkWest was liable under a quantum
meruit theory — but reduced the damages to $934,436.1
¶9 Dyess next asked for a judgment notwithstanding the verdict
(JNOV) on MarkWest’s counterclaim, asserting that it had achieved
mechanical completion before the final mechanical completion
dates, which it claimed MarkWest had extended. The trial court did
1 Dyess submitted six invoices — totaling $934,436 — that
MarkWest failed to pay.
3 not rule on the motion, and it was therefore deemed denied by
rule.2 See C.R.C.P. 59(j).
¶ 10 Dyess appealed (1) the order treating the verdict in its favor as
advisory and reducing the damages award; (2) the denial of its
motion for JNOV on MarkWest’s counterclaim; and (3) the denial of
its motion for pre- and post-judgment interest. MarkWest cross-
appealed the denial of its motion for pre- and post-judgment
interest.
¶ 11 A division of this court reversed the judgment insofar as the
trial court (1) “reduced the amount of damages awarded to Dyess on
its quantum meruit claim” and (2) “failed to award pre- and post-
judgment interest.” M.G. Dyess, Inc. v. MarkWest Liberty Midstream
& Res., L.L.C., 2022 COA 108, ¶ 38. It affirmed the judgment
insofar as the trial court accepted the jury’s liability verdict on the
quantum meruit claim and denied Dyess’s motion for JNOV. Id. at
¶¶ 23, 34. The case was then remanded for further proceedings.
Id. at ¶ 38.
2 Both parties filed C.R.C.P. 59(c)(4) motions to amend the judgment
to include pre- and post-judgment interest. These motions were also deemed denied. See C.R.C.P. 59(j).
4 ¶ 12 On remand, the court recognized that the court of appeals had
affirmed the finding of liability on quantum meruit damages in favor
of Dyess. Because the jury had awarded $26,039,641 in favor of
Dyess (on quantum meruit) and $4,500,000 in favor of MarkWest
(on its contract counterclaim), the remand court subtracted the
latter from the former to arrive at a judgment of $21,539,641 in
favor of Dyess. The court then added prejudgment interest of
$2,712,319.08 (eight percent, compounded annually) and
postjudgment interest of $7,450,237.06, for a total judgment of
$31,702,197.14.
¶ 13 As expected, MarkWest asked for a new trial and Dyess
opposed that request. MarkWest continued to argue that, unless
Dyess agreed to a reduced judgment of $934,436, the court should
grant a new trial because the jury’s damage award was manifestly
5 excessive and unsupported by the evidence.3 MarkWest’s theory at
trial, and on remand, was that any excess charges by Dyess were
subject to the contract’s change order process.
¶ 14 Dyess countered that the jury heard ample evidence that
MarkWest directed Dyess to perform out-of-scope work, work which
benefited MarkWest and for which Dyess was not paid. Moreover,
Dyess refuted MarkWest’s suggestion that Jury Instruction 60
limited (to $934,436) the recoverable out-of-scope work expenses.
¶ 15 Indicating that it had reviewed the record, the remand court
(with a new judge presiding after the trial judge retired) concluded
that the jury’s damages award was not “manifestly excessive” given
the evidence presented and denied MarkWest’s request for a new
trial. See Murphy v. Glenn, 964 P.2d 581, 586 (Colo. App. 1998)
(successor judge has discretion to rule on post-trial motion
3 Liability for quantum meruit was affirmed by the prior division of
this court, so it is not at issue here. See M.G. Dyess, Inc. v. MarkWest Liberty Midstream & Res., L.L.C., 2022 COA 108, ¶ 38. To the extent MarkWest argues for a new trial on anything other than the amount of damages, we will not entertain that argument. See Saint John’s Church in Wilderness v. Scott, 2012 COA 72, ¶ 8 (“The law of the case doctrine protects parties from relitigating settled issues, on the grounds that courts generally ‘refuse to reopen what has been decided.’” (quoting People ex rel. Gallagher v. Dist. Ct., 666 P.2d 550, 553 (Colo. 1983))).
6 challenging the sufficiency of the evidence). The court also
acknowledged that Dyess did not agree to a remittitur.
¶ 16 MarkWest now appeals the remand court’s orders. See
Simpson v. Yale Invs., Inc., 886 P.2d 689, 699 (Colo. 1994) (“When a
case is remanded to the trial court and subsequently appealed, the
reviewing court will consider only those issues arising after the
remand and whether the trial court complied with the order of
remand.”).
II. Applicable Law
A. Standards of Review
¶ 17 “We review a trial court’s order for a new trial for an abuse of
discretion. A trial court abuses its discretion when its ruling is
‘manifestly arbitrary, unreasonable, or unfair,’ or when it
misapplies the law.” Rains v. Barber, 2018 CO 61, ¶ 8 (citations
omitted).
¶ 18 In determining whether a party may recover for unjust
enrichment, we “defer to the trial court’s factual findings unless
they are clearly erroneous.” French v. Centura Health Corp., 2022
CO 20, ¶ 24. However, we review de novo contentions that an
express contract bars an unjust enrichment claim. See Interbank
7 Invs., LLC v. Eagle River Water & Sanitation Dist., 77 P.3d 814, 816
(Colo. App. 2003).
B. Grounds for a New Trial Under Rule 59(d)
¶ 19 Rule 59 governs motions for new trials. C.R.C.P. 59(a)(1).
Rule 59(d) lists six distinct grounds for a new trial:
(1) Any irregularity in the proceedings by which any party was prevented from having a fair trial; (2) Misconduct of the jury; (3) Accident or surprise, which ordinary prudence could not have guarded against; (4) Newly discovered evidence, material for the party making the application which that party could not, with reasonable diligence, have discovered and produced at the trial; (5) Excessive or inadequate damages; or (6) Error in law.
Rains, ¶ 11 (quoting C.R.C.P. 59(d)(1)-(6)). The following principles
guide our review of whether the remand court abused its
considerable discretion, see Averyt v. Wal-Mart Stores, Inc., 265
P.3d 456, 462 (Colo. 2011), in denying a new trial for the jury’s
allegedly excessive damage award:
• The amount of damages is within the jury’s sole province, and
an award will not be disturbed unless it has no record
support. Id.; Hildebrand v. New Vista Homes II, LLC, 252 P.3d
1159, 1170 (Colo. App. 2010).
8 • The verdict’s excessive nature must clearly and definitely
indicate that the jury (1) ignored the court’s instructions and
the undisputed evidence; or (2) was swayed by prejudice,
passion, or another improper consideration. Martinez v.
Affordable Hous. Network, Inc., 109 P.3d 983, 992 (Colo. App.
2004), rev’d on other grounds, 123 P.3d 1201 (Colo. 2005); see
also Averyt, 265 P.3d at 462-63 (an award may be adjusted
where there is an indication that the “jury acted out of
passion, prejudice, or corruption”).
C. Legal Principles of Quantum Meruit
¶ 20 A party asserting an unjust enrichment claim must prove
“that (1) at the plaintiff’s expense (2) the defendant received a
benefit (3) under circumstances that would make it unjust for the
defendant to retain the benefit without paying.” Bd. of Governors of
Colo. State Univ. v. Alderman, 2025 CO 9, ¶ 35. However, a party
typically cannot assert an unjust enrichment claim “if a valid
contract covers the same subject matter.” Id. at ¶ 36. Colorado
appellate courts recognize two exceptions to this rule: “(1) the
express contract fails or is rescinded or (2) the claim covers matters
that are outside of or arose after the contract.” Id. at ¶ 37; accord
9 M.G. Dyess, ¶ 17; Specialized Grading Enters., Inc. v. Goodland
Constr., Inc., 181 P.3d 352, 354-55 (Colo. App. 2007).
III. Analysis
¶ 21 While the remand court did not fully explain what evidence
supported the jury’s damages award, it indicated that its review of
the evidence supported that award, and it identified the legal
authority upon which it relied in declining to reduce the jury’s
award or grant a new trial on damages. Without the benefit of a
detailed analysis to review, we rely on the record, as outlined below,
for our analysis. See Interbank Invs., 77 P.3d at 816 (reviewing de
novo whether an express contract bars an unjust enrichment
claim).
A. Additional Background
¶ 22 Dyess and MarkWest’s operative contracts for the subject
pipelines were effective in August 2017. The contracts
contemplated that the first spread (spread 1A, .32 miles) and the
third spread (spread 2, 6.18 miles) would be completed by January
15, 2018, and the second spread (spread 1B, 7.52 miles) by October
1, 2017. The parties agree that the deadline for the first and third
spreads was extended once, but they dispute whether MarkWest
10 granted additional extensions.4 M.G. Dyess, ¶ 31 n.4. In any event,
each party blames the other for work delays and associated
expenses.
¶ 23 According to Dyess, its inability to construct the pipelines in
tandem, as its bid documents indicated, and on schedule resulted
from MarkWest’s delayed property access, inspector limits, weather
stoppages, and repeated safety shutdowns. So it had to expend
substantially more in labor and materials to meet its obligations to
MarkWest.
¶ 24 MarkWest argues here, as it argued to the remand court, that
(1) the express contracts precluded Dyess from recovering for
unjust enrichment, and (2) the jury could only award quantum
meruit damages for the work identified in Jury Instruction 60 (or
$934,436). Dyess disagrees that its quantum meruit damages are
limited in either way.
4 There was conflicting testimony about whether MarkWest
extended the completion dates for one or more of the spreads. Ultimately, the prior division of this court indicated that the jury could have reasonably inferred that any extension was conditional on successful completion of the parties’ (ultimately unsuccessful) attempts to negotiate the matter. M.G. Dyess, ¶¶ 28-34. Consistent with this finding, the division did not disturb the jury’s $4,500,000 award in MarkWest’s favor. Id.
11 ¶ 25 Before turning to the delays and expenses Dyess detailed to
the jury, and MarkWest’s rebuttal to those, we provide an overview
of the key contract provisions.
B. Contract Provisions Invoked
¶ 26 Section 1.1 of each contract required that Dyess perform “all
workmanship, labor, materials, and equipment set forth in Exhibit
‘A’ [the Scope of Work], and as subsequently added by [MarkWest]
in accordance with the terms of th[e] Contract.” Section 4 detailed
that
Changes to the Scope of Work (for work in addition to that covered under the Lump Sum Fixed Price . . . and which is consistent with the original terms and intent of this Contract) shall be made only by a written change order specifying the requested changes or additions, including changes to the Lump Sum Fixed Price.
¶ 27 MarkWest reiterates that the scope of work was broad and
covered installing the specified lengths of pipe for each spread. It
also points to the following provisions as limiting Dyess’s recovery:
• Sections 2.17 and 3.1, requiring that any extra work be
authorized through approved change orders; and
12 • Section 4.7, identifying the approving authorities for
change orders.
¶ 28 As relevant to Dyess’s position, Section 3.18 provides that
changes that increase or decrease the scope of work will be handled
via a negotiated adjustment, and Dyess tried to negotiate for time
extensions and additional payments.5 When a settlement proved
elusive, Dyess sued to recover the labor and materials it provided,
and MarkWest countered by demanding contractual delay damages.
C. Access Issues
¶ 29 During the bid process, MarkWest representatives disclosed
that they had not secured all necessary legal land access but
indicated the access would soon be resolved and certainly before
Dyess planned to begin the pipeline work. The access required to
complete spread 1B was belatedly secured near the end of
September 2017.
5 During trial, MarkWest claimed that, in extending the pipeline
completion deadlines, it effectively compensated Dyess for any expenses incurred before the end of December 2017. The jury agreed that (even with the extension) Dyess did not timely complete the pipeline segments (as the delay payments verdict reflects), but it seemingly rejected MarkWest’s claim that Dyess contractually waived any claim to overages.
13 D. Inspector Delays
¶ 30 After the contracts were signed, Dyess learned that most of its
ground disturbance activities needed to be inspected by a
MarkWest-provided inspector. Dyess’s original work plan called for
nine or ten work crews working simultaneously to expedite pipeline
progress. With only two inspectors, Dyess could only mobilize two
crews. And coordinating the two inspectors’ presence on site
proved difficult. MarkWest disputes any surprise, but Dyess was
not the only contractor requesting more inspectors.
¶ 31 Although Brian McRaney, Dyess’s project manager, asked for
additional inspectors so Dyess could deploy more work crews, he
did not receive more inspectors until mid-December, well after
spread 1B was due (October 1, 2017) and shortly before the other
two spreads were to be delivered (January 15, 2018).6 As it turned
out, the additional three inspectors (five in total) did not provide the
6 Michael Hoy, MarkWest’s construction manager, acknowledged
that because Dyess did not have access to the land for spread 1B until September 25 or 26, 2017, it was unrealistic for MarkWest to expect Dyess to construct 7.52 miles of pipeline in a few days, or by the October 1, 2017, due date in the contract.
14 relief Dyess needed because a December 2017 MarkWest incident
on a different spread further delayed Dyess’s work.
E. Weather Delays, Fatality, and “No Slip” Policy
¶ 32 The fall of 2017 was a wet season in the area where the
pipeline was being installed. In addition to the challenges the rain
and snow posed to the pipeline workers, there was a fatality on
spread 4 (Dyess was not working on that segment) caused by heavy
equipment sliding into a worker and crushing him against another
piece of equipment. That fatality lead MarkWest to implement its
“no slip” (or heavy equipment) policy. Dyess agreed to abide by
MarkWest’s no slip policy, which did not allow pipeline contractors
to work when weather conditions limited workers’ ability to safely
manage heavy equipment or otherwise endangered pipeline
crewmembers.
¶ 33 Dyess lost workdays because of this policy and soon realized it
would not meet the January 2018 spread deadlines. MarkWest
extended the due dates into March 2018, but Dyess continued to
work into July 2018 even though it was unsuccessful in negotiating
another extension.
15 F. Claimed Harm
¶ 34 The remand court was largely tasked with determining
whether the jury’s $26,039,641 quantum meruit award enjoyed
record support. Without the benefit of the remand court’s analysis,
we must look at the evidence in the record to determine whether the
record supports the award.
¶ 35 Dyess presented expert testimony from Jens Baker detailing
the additional expense Dyess incurred as the project continued.
Baker explained the components of the figures he provided for the
jury to consider as follows7:
7 The jury also heard that Dyess incurred $67,004,011 in added
expenses. But MarkWest had paid $40,964,370 of Dyess’s billings, so the difference — without any expected profit — was $26,039,641. This testimony likely explains how the jury arrived at its damages award. According to Baker, the jury should have awarded $28,303,383 (without the 23.3% contractual markup) or $34,205,285 (with the markup). To the extent Baker looked to the contract to add a markup to cover home-office and other such costs, that markup came from the contract itself. As the jury did not award breach of contract damages to Dyess, it would have been inappropriate to award Dyess any amount for markups. Baker’s calculations also relied, in part, on the fee schedules Dyess supplied to MarkWest (but MarkWest provided no alternative fee structure for the jury to consider). Baker also testified that he updated change order 8 using the negotiated rates in the contacts, agreeing that those rates included a markup.
16 Costs (*indicates 23.3% markup applied) Amount Extended Performance Costs Due to $9,782,152 MarkWest Interferences* Move-Arounds Caused by Right-of-Way $169,326 Restrictions Schedule Revisions and Crew Changes $6,607,568 Directed by MarkWest* MarkWest Failure to Supply Operations $1,946,584 Personnel (after 12/7/17 and before 12/16/17) Shutdowns (directed by MarkWest due to $6,456,985 winter weather and no slip policy)* Additional costs (coordination, potholing, $3,340,768 winter weather conditions*) (markup only applied to winter conditions) Total Costs Before Markup Applied $28,303,383 Total Costs with Markup of $5,901,902 $34,205,285
¶ 36 The jury’s damage award loosely aligns with Baker’s testimony
about how (and in what amount) MarkWest’s actions damaged
Dyess after the contracts were signed.
¶ 37 As mentioned, and as McRaney testified, section 3.18 of each
contract contemplated that the parties would negotiate an
adjustment for changes to the scope of work. Dyess asked for an
adjustment, but MarkWest repeatedly refuted, ignored, or delayed
Dyess’s efforts to negotiate for the additional labor and materials
Dyess provided.
17 ¶ 38 A party may recover for unjust enrichment if “substantial
changes occur that are not covered by the contract and are not
within the contemplation of the parties, and when the effect of such
changes is to require extra work or to cause substantial loss to one
party.” Specialized Grading Enters., Inc., 181 P.3d at 354-55; see
also V.C. Edwards Contracting Co. v. Port of Tacoma, 514 P.2d 1381,
1386 (Wash. 1973) (applying the same principle and noting that
“[t]he critical factor . . . is whether the [party] should have
discovered or anticipated the changed condition”).
¶ 39 In Specialized Grading Enterprises, a subcontractor brought
an unjust enrichment claim for extra work, and “[t]he contractor
argued that the [extra work] . . . was expressly provided for in the
general contract” and that the contract’s change order procedure
provided “an adequate contractual remedy.” 181 P.3d at 355. A
division of this court reversed the district court’s entry of a directed
verdict in the contractor’s favor on the unjust enrichment claim,
reasoning that (1) the parties did not follow the change order
procedure; (2) the work the subcontractor performed was the
contractor’s responsibility; (3) “[t]he subcontractor could not have
reasonably anticipated that the contractor” would not perform; and
18 (4) “the contractor was aware of the problem and the
subcontractor’s efforts.” Id. at 356.
1. Evidence Supporting a Quantum Meruit Recovery
¶ 40 As noted, the contracts were executed in August 2017, but the
inadequacy of the number and availability of the inspectors
MarkWest provided was evident only after the contracts’ effective
date. Relatedly, Michael Hoy (MarkWest’s construction manager)
testified that he was immediately under pressure to keep costs
down for his portion of the overall project and that the operations
budget (which funded the inspectors) was reduced to serve that
directive. Not only were there insufficient inspectors, but the few
inspectors were not available when and where Dyess needed them.
Indeed, Hoy admitted he was aware of the coordination and
communication challenges.
¶ 41 As mentioned, MarkWest implemented the no slip policy after
the workplace fatality in December, well after the contracts’ effective
date. Once the policy was in effect, MarkWest largely dictated when
Dyess could work. Dyess employees testified they could not have
reasonably anticipated losing so many workdays. Moreover,
according to McRaney, Dyess’s proposal contemplated
19 approximately five days of adverse weather, but actual rainouts
were closer to thirty-seven days.
¶ 42 Neither the contracts nor the parties contemplated the extent
of work stoppages or all the difficulties they would later encounter.
See id. at 354-56. Dyess always expected to finish most of its work
before winter. However, the delays required Dyess to work into and
past the winter season, when conditions made the work more
challenging and more expensive. See, e.g., George Sollitt Constr. Co.
v. United States, 64 Fed. Cl. 229, 239 (2005) (recognizing that
construction “during winter months may be more expensive than
the same work performed during temperate weather”). Indeed, Hoy
warned that further delays would result in increased construction
costs for winter work.8
¶ 43 It is true that MarkWest presented evidence to argue that not
all of the delays were directly attributable to it. For example,
MarkWest presented evidence of as many as twenty-one incidents
as of December 12, 2017 — ranging from suspected drug ingestion
8 MarkWest issued its first bid on May 11, 2017, but it had to re-bid
later that summer because no company bid to complete the challenging spread 1.
20 by untrained Dyess crew members to a piece of heavy equipment
tipping into a ditch — requiring work stoppages, arguing it should
not be faulted for them. It is also unclear whether Baker’s analysis
accounted for (1) the $189,168 MarkWest paid for the clearing
subcontractor who was on standby pending resolution of the land
access issues; (2) the portion of the work MarkWest removed from
Dyess — the hot tap work — and assigned to a different contractor
(with no corresponding reduction in Dyess’s compensation); (3) the
$500,000 MarkWest paid to Dyess for the safety training it required
in January 2018 (after the fatality); (4) inefficiencies generated by
Dyess personnel changes;9 and (5) MarkWest’s expenditures
associated with locating and fixing a Dyess-installed leaky pipe.
Working into the winter contributed (in part) to some of the
incidents, but, as noted, some of the trial evidence may have
9 For example, (1) Steve Greenway, Dyess’s superintendent, felt the
strain of the project and asked to be re-assigned to a different project, so, effective December 4, 2017, Jody Broom replaced him; (2) Dyess fired a supervisor for leaving his post; and (3) three laborers disappeared to avoid drug testing. Worker shortages in the area forced Dyess to hire some inexperienced crew. That inexperience showed in the various incidents.
21 suggested that fault for each work stoppage could not be laid solely
at MarkWest’s feet.
¶ 44 To the extent there was conflicting testimony about what the
parties viewed as included in the contracts’ scope and the cause of
delays, however, we must defer to the jury’s assessment of witness
credibility and conflicting testimony. See Vaccaro v. Am. Fam. Ins.
Grp., 2012 COA 9M, ¶ 34; see also Vititoe v. Rocky Mountain
Pavement Maint., Inc., 2015 COA 82, ¶ 34 (appellate court will
review the entire record to determine if there “is competent evidence
from which the jury logically could have reached its verdict”).
Indeed, we may not disturb the jury’s determination of the amount
of damages unless it has no record support, which is not the case
here. See Averyt, 265 P.3d at 462; Hildebrand, 252 P.3d at 1170.
Nor does the jury’s verdict clearly and definitely show that it ignored
the court’s instructions or undisputed evidence, or that it was
motivated by improper considerations. See Martinez, 109 P.3d at
992; see also Averyt, 265 P.3d at 462-63.
¶ 45 As a result, we cannot say that the remand court erred by
concluding that the record supported Dyess’s unjust enrichment
claim. See Alderman, ¶ 37.
22 2. Change Orders and Quantum Meruit
¶ 46 We next engage with MarkWest’s argument that Dyess had to
follow the change order process to recover labor or material costs.
The record reflects that MarkWest selectively ignored Dyess’s
change order requests. Significantly, MarkWest observed Dyess
performing the now-challenged work without objecting or
requesting change order submittals before the work proceeded. See
Jarosz v. Caesar Realty, Inc., 220 N.W.2d 191, 193 (Mich. Ct. App.
1974) (allowing recovery for unjust enrichment, notwithstanding a
change order provision, “because defendants were aware of and
authorized changes . . . [and] had either waived th[e] [change order]
requirement . . . or [the] requirement did not extend to extra work”).
¶ 47 So MarkWest knew of its right to request and receive change
orders, but it selectively ignored the change order process — or
simply refused to pay Dyess — for the work it now claims required
change orders. On these facts, we cannot say that the jury erred by
effectively concluding that MarkWest waived its right to rely on the
change order process (after all, the jury agreed Dyess was entitled
to quantum meruit damages). See Tarco, Inc. v. Conifer Metro. Dist.,
23 2013 COA 60, ¶ 33; Avicanna Inc. v. Mewhinney, 2019 COA 129,
¶ 25.
¶ 48 But whether a party waived a contractual provision and
whether such waiver entitles the other party to pursue an unjust
enrichment claim are different questions. The rationale underlying
“waiver as an excuse for nonperformance . . . is based in large part
on the policies against . . . unjust enrichment.” 13 Richard A. Lord,
Williston on Contracts § 39:15, Westlaw (4th ed. database updated
May 2025). Therefore, waiver of a contractual right generally
precludes the waiving party from “seek[ing] judicial enforcement of
the contract with regard to the waived performance.” Id.; see also
Assocs. of San Lazaro v. San Lazaro Park Props., 864 P.2d 111, 111,
115-16 (Colo. 1993) (holding that a breach of warranty action
should have been dismissed where the party claiming breach
waived the right to rely on the contract’s warranty).
¶ 49 Thus, because courts will not enforce waived provisions, we
conclude that waiver is sufficiently analogous to the provision
having failed that it satisfies the exception under which a party to
an express contract may seek restitution for unjust enrichment
when the contract (in whole or in part) fails or is rescinded. See
24 Alderman, ¶ 37. When a party waives a contractual provision that
could otherwise block an unjust enrichment claim, the waiving
party can no longer rely on that provision, even if the contract as a
whole has not failed.
¶ 50 We also conclude that waiving a contractual provision is
distinguishable from the circumstances in Alderman. There,
Alderman and other students sued Colorado State University (CSU)
to recover tuition and fees after the university transitioned to
remote services during the COVID-19 pandemic. Id. at ¶¶ 7-11.
Although the students “contracted for an in-person education,” a
“statutory provision . . . granted CSU the authority to suspend
university operations in the event of ‘the prevalence of fatal
diseases, or other unforeseen calamity.’” Id. at ¶¶ 10, 41 (quoting
§ 23-30-111, C.R.S. 2024). Because the statute was “incorporated
into the parties’ contract, meaning that the contract explicitly
allowed the university to temporarily suspend operations,” the court
concluded that Alderman could not bring an unjust enrichment
claim. Id. at ¶¶ 38, 41, 44.
¶ 51 The Alderman court held that the statutory provision — which
became part of the contract — did not render the contract (or any
25 portion of it) unenforceable. Id. at ¶¶ 4, 41. It reasoned that
Alderman’s inability to state a claim for breach of contract due to
the statutory provision differed from the contract being
unenforceable. Id. A contract fails, the court held, “when it
becomes legally unenforceable,” not when “it does not provide all
the services and protections to which a party claims they are
entitled.” Id. at ¶ 40. Thus, although the contract was silent as to
CSU’s obligation to issue refunds when it transitioned to remote
services, the court held that unjust enrichment is not “a gap-filler
provision to provide a remedy when a contract is silent about a
desired term.” Id. at ¶¶ 16-17, 43.
¶ 52 In Alderman, the statute effectively created an explicit
contractual exception to the requirement that CSU provide in-
person services. So Alderman could not sue for breach of contract
or unjust enrichment because an express provision of the contract
allowed the allegedly prohibited conduct. By contrast, waiver is not
an explicit provision or exception that becomes part of a contract;
instead, it effectively eliminates the waived provision. In short,
Alderman’s claims were barred because there was an express
26 provision, while a waiving party cannot enforce or rely on an
express provision that it has disavowed.
¶ 53 Just as a contract’s failure or rescission creates an avenue for
unjust enrichment recovery because there are no enforceable
contractual provisions, waiver results in the waived contractual
provision becoming legally unenforceable. See id. at ¶ 40; 13
Williston on Contracts § 39:15. Waiver is also different from the
parties omitting a term from their agreement, see Alderman, ¶ 43,
because the parties contemplated the term, but it failed. Allowing
claims for unjust enrichment when a contractual provision fails or
is rescinded is not the same as allowing unjust enrichment claims
to serve as a gap-filler for overlooked terms. See id. Otherwise, the
exceptions discussed in Alderman, ¶ 37, would be meaningless.
¶ 54 The parties’ contract originally provided a contractual way for
Dyess to be compensated for its additional work: it could (1) submit
change orders or (2) negotiate an adjustment pursuant to section
3.18. Admittedly, MarkWest honored the first few change orders.
But witnesses testified that Dyess tried to submit other change
orders and MarkWest largely ignored or otherwise rejected Dyess’s
later change order submittals. MarkWest’s waiver meant that there
27 was no longer an enforceable contractual provision covering out-of-
scope work, and any such work fell outside of the contract. See id.
So to the extent the disputed work and materials were subject to a
change order requirement, the jury could have reasonably
concluded that MarkWest’s waiver of these sections allowed Dyess
to recover under unjust enrichment.
¶ 55 Relatedly, MarkWest also posits that any quantum meruit
recovery was necessarily limited by Jury Instruction 60 and Dyess’s
counsel’s purported concession that the damages sought under that
instruction were under a million dollars.10 Dyess rejects any such
limitation.
¶ 56 The plain language of Jury Instruction 60 shows that it did
not limit Dyess’s potential quantum meruit recovery to costs
associated with the limited specific examples of extracontractual
work it provided. Jury Instruction 60 explicitly stated that
“[d]epending on your findings, items not covered by the contracts
10 MarkWest also consistently claimed that Dyess could not advance
multiple theories of recovery, but Colorado law allows a party to advance multiple theories of recovery while allowing for only one monetary recovery. See Hemmann Mgmt. Servs. v. Mediacell, Inc., 176 P.3d 856, 860 (Colo. App. 2007).
28 and not within the contemplation of the parties include items such
as: slip work, drains, timber mats, rock ditch, extra spool piece at
the kickoff, and test leads misfire work.” (Emphasis added.) The
“such as” language plainly shows Jury Instruction 60 did not
explicitly limit Dyess’s quantum meruit damages to costs related to
the enumerated specific examples.11
¶ 57 From the jury’s verdict and award, it is evident that the jury
found that MarkWest received substantial value from work and
materials Dyess provided. The verdict also shows that the jury
rejected MarkWest’s theory — reiterated several times during
trial — that, by accepting the first extension to the completion
schedule and a lower payment, Dyess waived any claim that it was
owed more. And the jury’s verdict shows it rejected MarkWest’s
repeated suggestion that Dyess accepted the $3,000,000 MarkWest
offered after Dyess demanded $7,500,000.
11 Moreover, because MarkWest represented to the remand court
that it did not seek a new trial “based on an erroneous instruction,” specifically referencing Jury Instruction 60, it cannot complain of the instruction now. See Gebert v. Sears, Roebuck & Co., 2023 COA 107, ¶ 25 (“[A]rguments never presented to, considered by, or ruled upon by a district court may not be raised for the first time on appeal.”).
29 ¶ 58 Collectively, because evidence in the record supports the jury’s
quantum meruit damage award, we may not second-guess the
jury’s decision. See Averyt, 265 P.3d at 462; Hildebrand, 252 P.3d
at 1170. We therefore affirm the remand court’s judgment denying
MarkWest a new trial and affirm its netted quantum meruit
damages award of $21,539,641.
IV. Disposition
¶ 59 The judgment is affirmed.
JUDGE GOMEZ and JUDGE HAWTHORNE concur.