MG Dyess v. MarkWest

Colorado Court of Appeals·Decided July 3, 2025·No. 24CA0463 24CA0995 & 24CA1400·Unpublished

Opinion

24CA0463, 24CA0995 & 24CA1400 MG Dyess v MarkWest 07-03-2025

COLORADO COURT OF APPEALS

Court of Appeals Nos. 24CA0463, 24CA0995 & 24CA1400 City and County of Denver District Court No. 23CV30585 Honorable Mark T. Bailey, Judge

M.G. Dyess, Inc., and M.G. Dyess LLC,

Plaintiffs-Appellees,

v.

MarkWest Liberty Midstream & Resources, L.L.C.,

Defendant-Appellant.

JUDGMENT AFFIRMED

Division II Opinion by JUDGE FOX Harris and Schutz, JJ., concur

NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced July 3, 2025

Wheeler Trigg O’Donnell LLP, Meghan Frei Berglind, Denver, Colorado; Kilpatrick Townsend & Stockton LLP, Adam H. Charnes, Dallas, Texas; Kilpatrick Townsend & Stockton LLP, R. Lee Mann III, Atlanta, Georgia, for Plaintiff-Appellee

Snell & Wilmer L.L.P., James D. Kilroy, Ellie Lockwood, Denver, Colorado, for Defendant-Appellant ¶1 Defendant, MarkWest Liberty Midstream & Resources, L.L.C.

(MarkWest), appeals the district court’s judgment entered in favor of

plaintiffs, M.G. Dyess, Inc. and its successor-in-interest M.G. Dyess

LLC (collectively, Dyess), on their breach of contract claim.

MarkWest contends that the district court erred by excluding

certain evidence and giving an adverse inference jury instruction at

trial. We affirm.

I. Background

¶2 In August 2017 Dyess contracted with MarkWest to build

three lengths, or “spreads,” of natural gas pipelines, spreads 1A,

1B, and 2, in West Virginia (the contracts). Relevant for this

appeal, each contract specified that in exchange for building each

spread, MarkWest would pay Dyess allocated portions of a lump

sum once Dyess reached “satisfactory completion of a payment

milestone,” including 30% of the lump sum once Dyess reached

“Mobilization,” 40% at “Work Welded Out,” and the remaining 30%

at “Mechanical Completion.”

¶3 However, MarkWest could withhold 10% of the lump sum

(retainage), which would then be due “within forty five (45) days

after Project Completion and Work Acceptance.” “Work Acceptance”

1 was defined as when Dyess “submitted a Notice of Project

Completion,” and MarkWest accepted it, in writing, agreeing that

the work was complete. If MarkWest believed the work was not

complete, it had to issue a “Completion Rework Notice” to Dyess

advising “in writing of any deficiencies or defects in the Work” for

Dyess to remedy and achieve Work Acceptance. MarkWest agreed

to pay $41,249,100.45 for Dyess’s work under all three of the

contracts; 10% of this in retainage amounted to $4,124,910.05.

¶4 Each contract specified that if Dyess failed “to achieve

Mechanical Completion by the Mechanical Completion Date,” it

would pay MarkWest liquidated damages, to a maximum of

$4,500,000 (the late completion payments). If Dyess did not make

the required late completion payments, MarkWest had “the right to

offset such Late Completion Payments against any payments still

due under this Contract including but not limited to the final

payment and Retainage.”

¶5 Conflict arose between the parties as the project progressed,

however. In 2018 Dyess sued MarkWest, and MarkWest asserted

counterclaims in M.G. Dyess, Inc. v. MarkWest Liberty Midstream &

Res., L.L.C., No. 18CV34745 (City & Cnty. of Denver Dist. Ct.)

2 (Dyess I). On February 14, 2020, a jury awarded Dyess

$26,039,641 in quantum meruit damages for an unjust enrichment

claim, awarded MarkWest $4,500,000 in late completion payments

pursuant to MarkWest’s breach of contract counterclaim, and

rejected the parties’ other claims. M.G. Dyess, Inc. v. MarkWest

Liberty Midstream & Res., L.L.C., 2022 COA 108, ¶ 6. The district

court in Dyess I determined that the quantum meruit claim was an

equitable claim, accepted the jury’s verdict as advisory only, and

reduced Dyess’s damages to $934,436. Id. at ¶ 8. The district

court entered judgment on July 8, 2020.

¶6 A division of this court later reversed the Dyess I district

court’s decision to treat the jury verdict as advisory, concluding

that the quantum meruit claim was legal and not equitable. Id. at

¶¶ 19-21. The division remanded the case to reinstate the award

subject to the parties’ posttrial motions and to award both parties

pre- and post-judgment interest. Id. at ¶¶ 24, 37-38.

¶7 Because the division had affirmed the jury’s quantum meruit

liability finding, the Dyess I remand court simply offset MarkWest’s

$4,500,000 breach of contract judgment from Dyess’s $26,039,641

quantum meruit judgment, arriving at a net award of $21,539,641

3 (plus pre- and post-judgment interest) in favor of Dyess. The new

judgment was entered on December 27, 2023. MarkWest

challenged the remand court’s decision in a separate appeal, and

another division of this court affirmed the judgment as entered by

the remand court. M.G. Dyess v. MarkWest Liberty Midstream &

Res., LLC, slip op. at ¶¶ 12, 58 (Colo. App. No. 24CA0585, May 22,

2025) (not published pursuant to C.A.R. 35(e)).

¶8 While the Dyess I case was progressing, however, Dyess and

MarkWest began disputing whether MarkWest had to pay Dyess the

retainage, which led to a second case and this appeal. On January

20, 2020, shortly before trial commenced in Dyess I, Dyess sent

project completion notices for all three spreads and requested

payment. Dyess requested $4,081,182.83 in retainage (accounting

for a $43,727.22 partial payment MarkWest had made to Dyess).

¶9 On February 19, 2020, MarkWest responded by sending a

“Nonacceptance of Projection Completion and Completion Rework

Notice” (the nonacceptance notice). According to MarkWest, Dyess

had “not performed all Services required under the Contracts nor

ha[d] it fulfilled its outstanding obligations under the Contracts to

MarkWest’s satisfaction.” MarkWest specifically contended that

4 Dyess failed to “complete restoration of Number 2 Ridge Road” (the

Ridge Road restoration work), despite requests to do so, and failed

to compensate MarkWest for the cost of hiring another contractor to

complete this work. MarkWest also alleged that Dyess still owed

$4,500,000 in late completion payments and had submitted

insufficiently detailed project completion notices. As a result,

MarkWest refused to pay Dyess the retainage.

¶ 10 Dyess sued MarkWest on February 23, 2023, asserting a

breach of contract claim based on MarkWest’s failure to pay the

retainage. M.G. Dyess, Inc. v. MarkWest Liberty Midstream & Res.,

L.L.C., No. 23CV30585 (City & Cnty. of Denver Dist. Ct.) (Dyess II).

MarkWest asserted several affirmative defenses and a counterclaim

for breach of contract. As relevant here, MarkWest alleged that

Dyess’s request for retainage was barred by the contracts, which

allowed MarkWest to offset late completion payments against the

retainage. On November 16, 2023, after a four-day trial, the jury

awarded Dyess $4,451,182.84 in damages (several hundred

thousand dollars more than Dyess’s demand).

¶ 11 On December 7, 2023, MarkWest moved pursuant to C.R.C.P.

59 for a new trial or, alternatively, remittitur. The district court

5 declined the request for a new trial but agreed to reduce the jury’s

award to $4,081,182.83, the amount of Dyess’s demand. The

court’s February 7, 2024, judgment awarded Dyess $4,081,182.83

Free access — add to your briefcase to read the full text and ask questions with AI

MG Dyess v. MarkWest, (Colo. Ct. App. 2025).

MG Dyess v. MarkWest (MG Dyess v. MarkWest) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lexton-Ancira Real Estate Fund v. Heller
826 P.2d 819 (Supreme Court of Colorado, 1992)
Rodriguez v. Schutt
896 P.2d 881 (Colorado Court of Appeals, 1995)
Bly v. Story
241 P.3d 529 (Supreme Court of Colorado, 2010)
Aloi v. Union Pacific Railroad Corp.
129 P.3d 999 (Supreme Court of Colorado, 2006)
Itin v. Ungar
17 P.3d 129 (Supreme Court of Colorado, 2000)
Quist v. Specialties Supply Co., Inc.
12 P.3d 863 (Colorado Court of Appeals, 2000)
Pfantz v. Kmart Corp.
85 P.3d 564 (Colorado Court of Appeals, 2004)
Mortgage Investments Corp. v. Battle Mountain Corp.
70 P.3d 1176 (Supreme Court of Colorado, 2003)
Genova v. LONGS PEAK EMERGENCY PHYSICIANS, P.C.
72 P.3d 454 (Colorado Court of Appeals, 2003)
Jacqueline Gebert v. Sears, Roebuck & Co.
2023 COA 107 (Colorado Court of Appeals, 2023)