Tupelo Redevelopment Agency v. The Gray Corporation, Inc.

CourtMississippi Supreme Court
DecidedJanuary 12, 2006
Docket2006-CA-00218-SCT
StatusPublished

This text of Tupelo Redevelopment Agency v. The Gray Corporation, Inc. (Tupelo Redevelopment Agency v. The Gray Corporation, Inc.) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tupelo Redevelopment Agency v. The Gray Corporation, Inc., (Mich. 2006).

Opinion

` IN THE SUPREME COURT OF MISSISSIPPI

NO. 2006-CA-00218-SCT

THE TUPELO REDEVELOPMENT AGENCY

v.

THE GRAY CORPORATION, INC.

AND

RONALD J. RAGLAND, SR. d/b/a RAGLAND ENGINEERING AND RAGLAND CONSTRUCTION

RONALD J. RAGLAND, SR. d/b/a RAGLAND ENGINEERING AND RAGLAND CONSTRUCTION

DATE OF JUDGMENT: 01/12/2006 TRIAL JUDGE: HON. THOMAS J. GARDNER, III COURT FROM WHICH APPEALED: LEE COUNTY CIRCUIT COURT ATTORNEYS FOR APPELLANT: KEVIN B. SMITH GUY W. MITCHELL WILLIAM DANIEL PRESTAGE WILLIAM G. ARMISTEAD, SR. ATTORNEYS FOR APPELLEES: B. SEAN AKINS THOMAS W. PREWITT KENNETH MARTIN HEARD, III NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: ON DIRECT APPEAL: AFFIRMED; ON CROSS-APPEALS: AFFIRMED - 10/18/2007 MOTION FOR REHEARING FILED: MANDATE ISSUED:

BEFORE DIAZ, P.J., CARLSON AND RANDOLPH, JJ.

CARLSON, JUSTICE, FOR THE COURT:

¶1. After a jury trial, the Circuit Court of Lee County entered a judgment in favor of the

Gray Corporation, Inc., and against the Tupelo Redevelopment Agency for $258,118; and

likewise entered a judgment in favor of Ronald J. Ragland, Sr., d/b/a Ragland Engineering

and Ragland Construction and against the Gray Corporation for $1,216,605.20. The Tupelo

Redevelopment Agency appeals from the judgment entered against it, and the Gray

Corporation, Inc., and Ronald J. Ragland, Sr., d/b/a Ragland Engineering and Ragland

Construction, cross-appeal. After consideration of the record before us and the applicable

law, we affirm on all issues raised both in the direct appeal and the cross-appeals.

FACTS AND PROCEEDINGS IN THE TRIAL COURT

¶2. On October 20, 2000, the Tupelo Redevelopment Agency (TRA) entered into a

contract with the Gray Corporation, Inc. (Gray) for the construction of the Tupelo

Fairgrounds Redevelopment Project (the Project). Gray was bonded by the Hartford Fire and

Insurance Company (Hartford). The original price contemplated by the contract was

$1,725,347.08 and consisted of three components: Component A, water and sewer

improvements; Component B, site work; and Component C, electrical, CATV, telephone and

duct system. Allen & Hoshall provided the electrical plan and specifications to TRA for

2 Component C of the Project. Jesco, Inc. (Jesco)1 was hired to serve as Construction

Manager, and Tupelo Water & Light (TWL) was hired to inspect and approve the

Component C work. For the Component C work, Gray 2 entered into a oral subcontract with

Ronald Ragland, Sr., d/b/a Ragland Engineering and Ragland Construction (Ragland),3

whereby Ragland agreed to perform some of the layout work contemplated by Gray’s

contract with TRA, and to construct portions of the Project.

¶3. After beginning work on Component C, Ragland noticed there were problems with

the plans given to it by Gray. After Allen & Hoshall spent nearly three months trying to

correct the electrical plans and specifications with no solution, TRA, Jesco and Allen &

Hoshall enlisted Ragland’s help to properly identify quantities of work and the scope of the

Project requirements. Because these revisions required extra work on the part of Gray and

Ragland, TRA, through its representative Jesco, promised Gray and Ragland a future change

order. On February 15, 2001, Ragland presented Brister with a narrative explaining the need

for a change order to the Project. On March 2, 2001, Gray obtained change order number

1 Jesco’s employee Steve Brister was the primary construction manager. As Jesco’s primary construction manager, Steve Brister’s scope of employment was to “manage the project, to be the owner’s liaison, eyes and ears on the project on a day-to-day basis.” 2 In accordance with Miss. Code. Ann. § 31-5-51 (Rev. 2005), Gray, as principal, and Hartford, as surety, executed a payment bond under which Gray and Hartford jointly and severally agreed to promptly pay all persons supplying labor and materials in the prosecution of the work required by the Project. 3 Mr. Ragland is a professional engineer, a registered land surveyor and a licensed contractor.

3 1, as required by the contract terms with TRA, for modifications to the electrical plan and

specifications to Component C. Additionally, Gray requested and received two more change

orders, number 2 and number 3. The three change orders brought about net additions of

$283,209.20 to the original contract terms. Gray and Ragland proceeded with the

contemplated work on the Project without receiving any additional change orders for any

extra work or time delays associated with Component C.4

¶4. After Ragland completed the work and requested payment from Gray, which was

never received, Ragland made a ore tenus motion to intervene in a suit which already had

been filed in the Circuit Court of Lee County, styled “W.G. Construction, Inc. v. The Gray

Corporation, Inc. and The Hartford Fire and Insurance Company,” civil cause number CV02-

133(G)L on the docket of that court.5 The motion to intervene was granted on August 12,

2002.

¶5. Thereafter, Ragland filed an intervention complaint against Gray and Hartford. In the

complaint, Ragland alleged:

Ragland’s work at the project was made difficult, more costly, and time consuming by Gray and/or third parties for which Gray is responsible. In

4 However, Gray and Ragland contend that since the changes were ongoing and delays were mounting, TRA promised to issue a “final change order” to address all outstanding issues. Such final change order was never issued by TRA due to the disputes which arose at the end of the Project and Gray’s request for equitable adjustment. 5 On October 29, 2003, the circuit court entered an Agreed Order Dismissing with Prejudice the Claims of W.G. Construction, Inc. and the Derivative Third-Party Claims Asserted by the Gray Corporation, Inc. Against the Tupelo Redevelopment Agency Which are Premised on the Claims of W.G. Construction, Inc.

4 addition to the work that it initially contracted to perform, Ragland was required by Gray to perform and did perform additional and different work than the work originally contemplated by the parties. Further, Ragland was unable to perform its work in the manner originally contemplated and as scheduled. It was denied access to portions of the work; Ragland’s construction efforts were interfered with; and, Ragland encountered different conditions at the project than had been reasonably anticipated. Likewise, Gray improperly performed administrative tasks and aspects of the project were changed. As a consequence of all of the above, Ragland became entitled to additional compensation and although Ragland was entitled to additional contract time, Gray continued to insist that Ragland perform at an unreasonable rate.

Ragland periodically billed Gray for its work; however, although Gray made some payments, Gray refused and still refuses to pay Ragland $534,454.11 being the total amount due it and which has been due for many months.

Based on Ragland’s allegations, Ragland’s prayer for relief is as follows:

WHEREFORE, PREMISES CONSIDERED, Ronald J. Ragland, Sr. demands judgment against The Gray Corporation, Inc. and The Hartford Fire and Insurance Company in the amount of at least Five Hundred Thirty-Four Thousand, Four Hundred Fifty Four Dollars and 11/cents ($534,454.11), plus pre-judgment interest, the penalty and interest required by § 31-5-27 Miss. Code Ann. (Supp. 2001), interest, costs and attorneys fees anticipated under § 31-5-57 Miss. Code Ann. (Supp. 2001).

Both Gray and Hartford filed Answers and Affirmative Defenses on September 23, 2002,

denying any liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Dew v. Langford
666 So. 2d 739 (Mississippi Supreme Court, 1995)
In Re Estate of Taylor
539 So. 2d 1029 (Mississippi Supreme Court, 1989)
Mauck v. Columbus Hotel Co.
741 So. 2d 259 (Mississippi Supreme Court, 1999)
Shive v. State
507 So. 2d 898 (Mississippi Supreme Court, 1987)
In Re Estate of Gillies
830 So. 2d 640 (Mississippi Supreme Court, 2002)
Key Constructors, Inc. v. H & M GAS CO.
537 So. 2d 1318 (Mississippi Supreme Court, 1989)
Citizens Nat. Bank of Meridian v. LL Glascock, Inc.
243 So. 2d 67 (Mississippi Supreme Court, 1971)
U.S. F/U/B/A Williams Electric Co. v. Metric Constructors, Inc.
480 S.E.2d 447 (Supreme Court of South Carolina, 1997)
Grey v. Grey
638 So. 2d 488 (Mississippi Supreme Court, 1994)
Bailey v. Estate of Kemp
955 So. 2d 777 (Mississippi Supreme Court, 2007)
Hartford Cas. Ins. Co. v. Halliburton Co.
826 So. 2d 1206 (Mississippi Supreme Court, 2001)
Wall v. Swilley
562 So. 2d 1252 (Mississippi Supreme Court, 1990)
In Re Estate of Richardson
903 So. 2d 51 (Mississippi Supreme Court, 2005)
Turner v. Turner
612 So. 2d 1141 (Mississippi Supreme Court, 1993)
Mississippi Transp. Com'n v. SCI, INC.
717 So. 2d 332 (Mississippi Supreme Court, 1998)
White v. Stewman
932 So. 2d 27 (Mississippi Supreme Court, 2006)
McKee v. McKee
418 So. 2d 764 (Mississippi Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Tupelo Redevelopment Agency v. The Gray Corporation, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/tupelo-redevelopment-agency-v-the-gray-corporation-miss-2006.