Citizens Nat. Bank of Meridian v. LL Glascock, Inc.
This text of 243 So. 2d 67 (Citizens Nat. Bank of Meridian v. LL Glascock, Inc.) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
CITIZENS NATIONAL BANK OF MERIDIAN, Defendant/Appellant,
v.
L.L. GLASCOCK, INC., Complainant/Appellee.
Supreme Court of Mississippi.
Wilbourn, Williams & Glover, Meridian, for defendant-appellant.
Floyd, Cameron, Deen & Prichard, Ralph E. Young, Jr., Meridian, for complainant-appellee.
PATTERSON, Justice:
This is an appeal by the Citizens National Bank of Meridian from a decree of the *68 Chancery Court of Lauderdale County which awarded L.L. Glascock, Inc., the sum of $8,902.21. The judgment was entered against the bank on a quantum meruit basis for the performance of extra work in connection with a building contract between the parties. Since interest, overhead, and profit were not included in the judgment, L.L. Glascock, Inc., has filed a cross appeal contending that the lower court erred in not permitting recovery on these items.
In 1964 the appellant, hereinafter owner, and appellee, hereinafter contractor, entered into a written contract for the demolition and removal of the owner's existing bank building in the city of Meridian and for the construction of a new bank building upon the same site. Subsequent to the removal of the old building the contractor, in testing the site for placing of concrete piling for the foundation of the new building, encountered the existing foundations of the old building. These foundations were about five feet below the surface of the basement level of the old building. Although the presence of these old foundations was anticipated, their precise location and size were unknown to the parties until disclosed by testing operations. Their location obstructed the placing of the new piling, necessitating that they either be bored through or removed.
Thereafter, the contractor contacted the structural engineer, an employee of the architect, and asked if some of the old foundations could be used as foundation for the new structure. Upon being advised that this was not feasible, the contractor removed the foundations which entailed much labor and expense, but which was nevertheless less expensive than boring through the existing foundations. A conflict of evidence arose between the engineer and the contractor as to whether the removal was directed by the engineer. The engineer testified that he advised the contractor that it would be necessary for him to remove only that portion of the existing foundation as would give room for the new piling. The testimony of the contractor's witnesses was that he directed that the old foundations be completely removed.
During the time the removal of the foundations was under way the contractor advised the owner's architect that he considered this labor to be supplementary to the contract for which payment in excess of the contract price would be expected. Accordingly when the work was completed in May 1965, the architect was presented a bill for this work.
The architect testified that he never directed the removal of the old foundations and that he was unaware the contractor expected additional pay for the labor performed until shortly before the bill was presented. Subsequently, they discussed the matter on several occasions. It is apparent that the architect initially thought the contractor was entitled to be paid over the contract price for the work performed. He informed the contractor that he would aid him in obtaining this payment. However, upon reexamining the contract, he concluded that the work was not extra and was within the contract price. He, therefore, declined to certify to the owner that the contractor was due reimbursement for extra work.
After a lengthy hearing in which all of the contract documents were introduced, the chancellor found the owner liable on a quantum meruit basis for the removal of the old foundations which he found to be extra work not anticipated by the contract. He further found "that the owner personally through its board of directors never officially passed on this subject and certainly never signed anything or gave any oral statement to the effect that they agreed that this was an extra. There is evidence that the architect agreed that this was an extra, but changed his mind, and there is no doubt in the Court's mind but that from the beginning of the work the contractor felt that this was an extra." *69 He also found that the owner had not waived any provisions of the contract.
The relevant portions of the contract are:
2-F CONCRETE PILING
(a) Scope: Furnish labor and materials to complete bored, cast in place concrete pilings as indicated, specified herein or both.
* * * * * *
(4) Equipment: Use drilling equipment generally used in standard pile boring practice, as approved.
(5) If obstructions such as maconry (sic) old foundations, etc., are encountered, bore thru as directed.
(6) Payment:
a. Except as herein provided, no separate payment will be made for specified work; include all costs in connection therewith in Stipulated Sum for entire work under contract. (Emphasis added.)
* * * * * *
Attached to the contract and made a part thereof is a pamphlet prepared by the American Institute of Architects entitled "General Conditions." Article 15 thereof is as follows:
CHANGES IN THE WORK
The Owner, without invalidating the Contract, may order extra work or make changes by altering, adding to or deducting from the work, the Contract Sum being adjusted accordingly. All such work shall be executed under the conditions of the original Contract except that any claim for extension of time caused thereby shall be adjusted at the time of ordering such change.
In giving instructions, the Architect shall have authority to make minor changes in the work, not involving extra cost, and not inconsistent with the purposes of the building, but otherwise, except in an emergency endangering life or property, no extra work or change shall be made unless in pursuance of a written order from the Owner, signed or countersigned by the Architect, or a written order from the Architect stating that the Owner has authorized the extra work or charge, and no claim for an addition to the Contract Sum shall be valid unless so ordered.
* * * * * *
Should conditions encountered below the surface of the ground be at variance with the conditions indicated by the Drawings and Specifications the Contract Sum shall be equitably adjusted upon claim by either party made within a reasonable time after the first observance of the conditions. (Emphasis added.)
Article 16 of the bulletin relating to claims for extra cost states:
If the Contractor claims that any instructions by drawings or otherwise involve extra cost under the Contract, he shall give the Architect written notice thereof within a reasonable time after the receipt of such instructions, and in any event before proceeding to execute the work, except in emergency endangering life or property, and the procedure shall then be as provided for changes in the work. No such claim shall be valid unless so made. (Emphasis added.)
The architect's status and authority are related in Article 38 which is set forth in part below:
ARCHITECT'S STATUS; ARCHITECT'S SUPERVISION
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
243 So. 2d 67, 1971 Miss. LEXIS 1506, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-nat-bank-of-meridian-v-ll-glascock-inc-miss-1971.