Cajun Industries, LLC v. Calgon Carbon Corporation and O’Neal Constructors, LLC

CourtDistrict Court, S.D. Mississippi
DecidedFebruary 11, 2026
Docket1:24-cv-00107
StatusUnknown

This text of Cajun Industries, LLC v. Calgon Carbon Corporation and O’Neal Constructors, LLC (Cajun Industries, LLC v. Calgon Carbon Corporation and O’Neal Constructors, LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cajun Industries, LLC v. Calgon Carbon Corporation and O’Neal Constructors, LLC, (S.D. Miss. 2026).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF MISSISSIPPI SOUTHERN DIVISION

CAJUN INDUSTRIES, LLC PLAINTIFF

v. CAUSE NO. 1:24CV107-LG-RPM

CALGON CARBON CORPORATION and O’NEAL CONSTRUCTORS, LLC DEFENDANTS

MEMORANDUM OPINION AND ORDER GRANTING CALGON CARBON CORPORATION’S MOTION TO DISMISS COUNTS 2, 4, AND 5 OF THE AMENDED COMPLAINT

Cajun Industries, LLC, filed this lawsuit against O’Neal Constructors, LLC, and Calgon Carbon Corporation, seeking payment for work it performed on the Calgon Carbon G-Line Expansion Project in Bay St. Louis, Mississippi. Calgon, the project owner, has filed a [51] Motion to Dismiss Counts 2, 4, and 5 of Cajun’s [15] Amended Complaint pursuant to Fed. R. Civ. P. 12(b)(6). The parties have fully briefed the Motion. After reviewing the submissions of the parties, the record in this matter, and the applicable law, the Court finds that the Motion should be granted. BACKGROUND Calgon retained O’Neal to serve as the general contractor on a construction project to expand its facility. O’Neal entered into one subcontract with Cajun for site development work and another for concrete work. Cajun filed this lawsuit against O’Neal and Calgon in the Circuit Court of Hancock County, Mississippi, and O’Neal removed the case to this Court on the basis of diversity jurisdiction. In its Amended Complaint, Cajun claims that Calgon became aware during the project that O’Neal was not paying its subcontractors for work they performed. Cajun alleges:

The situation became so poor that Calgon began taking over the project directly and directly paying subcontractors, fulfilling the contract obligations that O’Neal had entered into. Indeed, Calgon created the expectation amongst those working on the project that Calgon would fulfill O’Neal’s obligations if O’Neal failed to do so.

Am. Compl. [15] at 5. Cajun claims it “diligently performed its work and supplied its materials,” but O’Neal and Calgon failed to pay Cajun what it is owed. Id. It has filed a breach of contract claim against O’Neal, a claim for payment pursuant to Miss. Code Ann. § 85-7-405 against both O’Neal and Calgon, a claim for lien enforcement against Calgon, a quantum meruit claim against Calgon, and an unjust enrichment claim against Calgon. Cajun claims the defendants owe “an amount not less than $2,873,619.46, together with attorney fees, statutory penalties, costs, pre-judgment interest, post-judgment interest, and prompt payment penalties.” Id. at 7. DISCUSSION I. STANDARD OF REVIEW AND CHOICE OF LAW Federal Rule of Civil Procedure 8 requires that a pleading contain “a short and plain statement of the claim showing that the pleader is entitled to relief[.]” Fed. R. Civ. P. 8(a)(2). Under Rule 12(b)(6), a party may move to dismiss for “failure to state a claim upon which relief can be granted[.]” Fed. R. Civ. P. 12(b)(6). Thus, “claims may be dismissed under Rule 12(b)(6) ‘on the basis of a dispositive issue of law.’” Jackson v. U.S. Dep’t of Hous. & Urb. Dev., 38 F.4th 463, 466 (5th Cir. 2022) (quoting Neitzke v. Williams, 490 U.S. 319, 326 (1989)). “Dismissal under Rule 12(b)(6) also is warranted if the complaint does not contain sufficient factual

matter, accepted as true, to state a claim to relief that is plausible on its face.” Id. (citation modified). “A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Lampkin v. UBS Fin. Servs., Inc., 925 F.3d 727, 733 (5th Cir. 2019) (quoting Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009)). When deciding a Rule 12(b)(6) Motion, a court “accept[s] all well-pleaded facts as true and review[s] them in the light most favorable to the plaintiff.”

Sanders-Burns v. City of Plano, 594 F.3d 366, 372 (5th Cir. 2010). Generally, courts can only consider the facts set forth in the complaint and its attachments. Villarreal v. Wells Fargo Bank, N.A., 814 F.3d 763, 766–67 (5th Cir. 2016). Federal courts sitting in diversity apply the forum state’s substantive law. In re Katrina Canal Breaches Litig., 495 F.3d 191, 206 (5th Cir. 2007) (citing Erie R.R. Co. v. Tompkins, 304 U.S. 64, 78 (1938)). When analyzing substantive issues, the

federal court first looks to the decisions of the state’s highest court, if available. Cerda v. 2004-EQR1 L.L.C., 612 F.3d 781, 794 (5th Cir. 2010). Otherwise, the federal court generally looks to decisions of the state’s immediate appellate court. Id. When state courts have not provided guidance, the federal court “must attempt to predict state law, not to create or modify it.” Am. Waste & Pollution Control Co. v. Browning-Ferris, Inc., 949 F.2d 1384, 1386 (5th Cir. 1991) (citation modified). II. COUNT 2 OF THE AMENDED COMPLAINT In Count 2, Cajun states that it is pursuing a “Section 85-7-405 Payment Action.” Am. Compl. [15] at 6. This statute provides:

A payment action for the recovery of the amount of the lien claimant’s claim against the party he contracted with shall be commenced in county, circuit or chancery court within one hundred eighty (180) days from the date of filing for record of the lien claimant’s claim of lien.

Miss. Code Ann. § 85-7-405(1)(c)(i) (emphasis added). Calgon argues that this statute does not allow a contractor to file a payment action against a project owner when there is no contract between the contractor and owner. Cajun responds that “Calgon is correct that the statute requires that such an action be brought against ‘the party [the claimant] contracted with,’ Miss. Code Ann. § 85-7-405(1)(c)(i), but Calgon does not point to any provision of the statute that prevents a claimant from also bringing a payment action against the owner.” Pl.’s Resp. Mem. [55] at 11. However, just because the statute does not prohibit a payment action against an owner does not necessarily mean that it permits one. Under Mississippi law, “where a statute enumerates and specifies the subject or things upon which it is to operate, it is to be construed as excluding from its effect all those not expressly mentioned or under a general clause, those not of like kind or classification as those enumerated.” Jones Cnty. Sch. Dist. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sanders-Burns v. City of Plano
594 F.3d 366 (Fifth Circuit, 2010)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Neitzke v. Williams
490 U.S. 319 (Supreme Court, 1989)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Cerda v. 2004-EQR1 L.L.C.
612 F.3d 781 (Fifth Circuit, 2010)
Omnibank of Mantee v. United Southern Bank
607 So. 2d 76 (Mississippi Supreme Court, 1992)
Citizens Nat. Bank of Meridian v. LL Glascock, Inc.
243 So. 2d 67 (Mississippi Supreme Court, 1971)
In Re Katrina Canal Breaches Litigation
495 F.3d 191 (Fifth Circuit, 2007)
Tupelo Redevelopment Agency v. Gray Corp.
972 So. 2d 495 (Mississippi Supreme Court, 2007)
Redd and Hill v. L & a Contracting Co.
151 So. 2d 205 (Mississippi Supreme Court, 1963)
Johnston v. Palmer
963 So. 2d 586 (Court of Appeals of Mississippi, 2007)
Zaida Villarreal v. Wells Fargo Bank, N.A.
814 F.3d 763 (Fifth Circuit, 2016)
Ground Control, LLC. v. Capsco Industries, Inc.
214 So. 3d 232 (Mississippi Supreme Court, 2017)
Kevin Lampkin v. UBS Painewebber, Inc., et
925 F.3d 727 (Fifth Circuit, 2019)
Jones County School District v. Mississippi Department of Revenue
111 So. 3d 588 (Mississippi Supreme Court, 2013)
Jackson v. HUD
38 F.4th 463 (Fifth Circuit, 2022)
Walker v. Brown
28 Ill. 378 (Illinois Supreme Court, 1862)
Salinas v. City of Houston
138 F.4th 822 (Fifth Circuit, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
Cajun Industries, LLC v. Calgon Carbon Corporation and O’Neal Constructors, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cajun-industries-llc-v-calgon-carbon-corporation-and-oneal-constructors-mssd-2026.