Roy A. Elam Masonry, Inc. v. Fru-Con Construction Corp.

922 S.W.2d 783, 1996 Mo. App. LEXIS 481, 1996 WL 133243
CourtMissouri Court of Appeals
DecidedMarch 26, 1996
Docket68114
StatusPublished
Cited by3 cases

This text of 922 S.W.2d 783 (Roy A. Elam Masonry, Inc. v. Fru-Con Construction Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roy A. Elam Masonry, Inc. v. Fru-Con Construction Corp., 922 S.W.2d 783, 1996 Mo. App. LEXIS 481, 1996 WL 133243 (Mo. Ct. App. 1996).

Opinion

GARY M. GAERTNER, Judge.

Defendani/appellant, Fru-Con Construction Corporation (“Fru-Con”), appeals the judgment of the Circuit Court of the City of St. Louis entering judgment on a jury verdict of $600,000 in favor of plaintifi/respondent, Roy A. Elam Masonry, Inc. (“Elam”), on Elam’s breach of contract action, and amending the judgment to include an additional $205,902.62 in prejudgment interest. We reverse the judgment of the trial court and remand for dismissal of Elam’s action without prejudice.

Fru-Con raises eight points on appeal. As we find the first point dispositive, we address only those parts of the record relevant to the first point.

On November 14, 1988, Fru-Con entered into a contract with Southwestern Redevelopment Corp. II (“SRC”) to construct the Southwestern Bell St. Louis Data Center Project for $103,901,483 (“the General Contract”). Fru-Con was to commence work on November 14, 1988, and achieve “substantial completion” of the Data Center 820 calendar days later, on February 11,1991.

In early 1989, Fru-Con and Elam entered into a subcontract wherein Elam, as subcontractor, agreed to perform masonry work on the Data Center, and Fru-Con, as general contractor, agreed to pay Elam $4,977,000 for this work (“the Subcontract”). Elam was to begin work on September 1, 1989, and finish by July 1, 1990, nine months later. Time was of the essence. The terms of the General Contract were incorporated into the Subcontract; however, the Subcontract also provided: “IN THE EVENT OF CONFLICT BETWEEN THE CONTRACT DOCUMENTS AND THIS SUBCONTRACT, THE PROVISIONS OF THIS SUBCONTRACT SHALL GOVERN.”

Article 3.C of the Subcontract stated in part:

Should Subcontractor be delayed by any act or omission of Contractor, Engineer or *786 Owner, or by any other cause beyond Subcontractor’s control and if the cause of delay is not due to any act or omission of Subcontractor, Subcontractor shall be entitled to request a reasonable extension of time for completion of the Subcontract work.... No payment of any kind, for compensation, or for damages, or otherwise, shall be made to Subcontractor because of any such delay even though Subcontractor’s extension of time request be granted, unless Owner is obligated to pay Contractor compensation or damages because of such delay, and then, as and when Owner pays such compensation or damages to Contractor, Subcontractor shall receive that share of such compensation or damages which can be agreed to or proven to have been directly attributable to such delay.

As stated above, the Subcontract’s start date was September 1,1989. However, Fru-Con encountered various problems prior to that date which greatly delayed the Data Center’s construction. 1 As a consequence, Fru-Con repeatedly extended the Subcontract’s start date by means of written schedule updates and oral representations to Elam, pushing the start date further and further back on the calendar. These schedule extensions resulted in Elam not beginning its work under the Subcontract until November 1, 1990—a delay of fourteen months.

On March 19, 1991, Elam sent Fru-Con what it termed a “formal request for an equitable adjustment to our contract.... based on the delay in the project that has caused [Elam] to incur unanticipated costs.” Elam listed $686,088 in damages and requested a change order in that amount, “to compensate Elam Masonry for the damages it has incurred thru [sic] 10/29/89. This change order amount will begin to draw interest, ... April 2, 1991.” Elam threatened legal action if the matter was not resolved by that date.

In response, Fru-Con informed Elam it had forwarded Elam’s claim to SRC “for their review and comment.” Fru-Con further stated, “As to your demand for immediate disposition, we can only direct you to a thorough reading of the terms and conditions of your contract with us.” ■

Elam replied on April 11,1991:

It remains the position of Elam Masonry that the fourteen month delay in allowing us to proceed was absolutely unreasonable and beyond the contemplation of the parties, having been caused totally from conditions beyond our control. Accordingly, Elam Masonry expects to be compensated by Fru-Con for our damages whether or not Fru-Con is successful in receiving compensation from the owner....

On August 27, 1991, Elam sent Fru-Con “additional backup information” in support of its claim for damages arising out of the fourteen-month delay, which Elam now set at $699,153. Elam also asserted:

Reference has been made to the subcontract clause which ostensibly bars the subcontractor from collecting delay damages unless the owner compensates the contractor. Although we understand that the information requested herein will pe [sic] presented to the owner as part of Fru-Con’s delay claim, we must stress that Elam is entitled to compensation from Fru-Con whether or not Fru-Con is successful in obtaining any or all of its claim from the owner. The 14 month delay to Elam resulted from the affirmative misrepresentations by Fru-Con as to the projected start date, were beyond Elam’s control, were unreasonable in duration, and were beyond the contemplation of the parties. There is a significant body of case law indicating that under these conditions, a no damage for delay clause is legally unenforceable. ...

Attached to this letter was a “Delay Damages Change Order Summary,” showing total damages of $699,153; and a “Financial History,” showing Elam’s income for the years 1984 through 1990.

*787 On October 9, 1991, Fru-Con submitted to SRC a “request for an equitable adjustment to our contract for the delays and disruptions relating to issues previously noticed and discussed affecting the building of the data center structure.” Elam’s claim for $699,153 was included in Fru-Con’s request for delay damages, as part of Fru-Con’s “Additional Subcontract Costs.” Fru-Con also included a copy of Elam’s August 27, 1991, letter to Fru-Con, and copies of the Delay Damages Change Order Summary and Financial History accompanying that letter.

On July 23, 1992, Elam filed suit against Fru-Con for breach of contract, requesting damages for underabsorbed overhead, lost profits, labor escalation costs, loss of net worth, and loss of value as a viable ongoing construction company. 2 Elam alleged the. following in its petition:

7. Elam was willing and able to commence and complete performance in accordance with the contractually agreed dates, but in spite of repeated oral and written assurances from Fru-Con to Elam as to its Subcontract start date, Elam was not allowed to begin work on the Project until November 1, 1990, fourteen months after the scheduled start and 5 months after its scheduled completion.

⅜ ⅜ ⅜ ⅝ ⅜ ⅝
10. The 14 month delay to Elam in the start of the job and the affirmative misrepresentations by Fru-Con as to the original start date and subsequent start dates, were beyond Elam’s control, were unreasonable in duration and were beyond the reasonable contemplation of Elam at the time the contract was signed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ITS Financial, LLC v. Advent Financial Services, LLC
823 F. Supp. 2d 772 (S.D. Ohio, 2011)
Purcell Tire & Rubber Co. v. Executive Beechcraft, Inc.
59 S.W.3d 505 (Supreme Court of Missouri, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
922 S.W.2d 783, 1996 Mo. App. LEXIS 481, 1996 WL 133243, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roy-a-elam-masonry-inc-v-fru-con-construction-corp-moctapp-1996.