American Civil Construction, LLC v. Hirani Engineering & Land Surveying, Pc

CourtDistrict Court, District of Columbia
DecidedNovember 28, 2018
DocketCivil Action No. 2014-0745
StatusPublished

This text of American Civil Construction, LLC v. Hirani Engineering & Land Surveying, Pc (American Civil Construction, LLC v. Hirani Engineering & Land Surveying, Pc) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Civil Construction, LLC v. Hirani Engineering & Land Surveying, Pc, (D.D.C. 2018).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

_________________________________________ ) UNITED STATES OF AMERICA, for the use ) and benefit of AMERICAN CIVIL ) CONSTRUCTION, LLC, ) ) Plaintiff, ) ) v. ) Case No. 14-cv-00745 (APM) ) HIRANI ENGINEERING & LAND ) SURVEYING, P.C., et al., ) ) Defendants. ) _________________________________________ )

FINDINGS OF FACT AND CONCLUSIONS OF LAW

This dispute between Plaintiff American Civil Construction, LLC (“Plaintiff” or “ACC”)

and Defendants Hirani Engineering & Land Surveying, PC (“Hirani”) and Colonial Surety

Company (“Colonial”) arises out of ACC’s work as a subcontractor to Hirani on a federal

government construction project located on the National Mall in the District of Columbia.

ACC brought this action against Colonial under the Miller Act, 40 U.S.C. § 3133, and also

brought a state law claim against Hirani for breach of contract. As to both claims, Plaintiff seeks

$2,172,285.23 in money damages, plus prejudgment interest, attorney’s fees, and costs. Colonial,

in turn, brings a variety of counterclaims against ACC and asserts that it incurred losses in the

amount of $723,049.14 to finish the project that ACC failed to complete.

After denying Defendants’ motion for summary judgment, the court conducted a five-day

bench trial in March 2018. After the bench trial concluded, the parties submitted proposed findings of fact and conclusions of law, as well as briefs in rebuttal. The court held a final oral argument

on June 14, 2018.

As required by Federal Rule of Civil Procedure 52(a)(1), the court now makes its Findings

of Fact and Conclusions of Law. The court has reviewed the parties’ submissions, carefully

considered the evidence presented at trial, weighed the credibility of the witnesses, and applied the

applicable law. For the reasons set forth below, the court has determined that Plaintiff has met its

burden of proof with respect to its Miller Act claim against Colonial and its breach of contract

claim against Hirani. On the other hand, the court finds that Defendant Colonial has not sustained

its burden of proof on its counterclaims.

Accordingly, the court will enter final judgment in favor of ACC. It will formally do so,

however, only after ACC submits a final damages calculation that is consistent with these Findings

of Fact and Conclusions of Law.

BACKGROUND

To provide clarity and context for these findings of fact and conclusions of law, the court

provides a brief overview of the undisputed facts underlying this case and then summarizes the

case’s procedural history.

A. Factual Background

In June 2010, the United States Army Corps of Engineers (“USACE”) issued a solicitation

for bids to construct a levee wall across 17th Street, N.W. in the District of Columbia, south of

Constitution Avenue, N.W. (the “Project”). Flanked on the west side by the National World War

II Memorial and on the east side by the Washington Monument, the 380-foot-long levee wall was

designed to prevent the Potomac River from flooding across the National Mall into downtown

Washington, D.C. As designed, the 17th Street levee wall consists of two permanent stone-clad

2 levee stem wall sections, one on the east side and the other on the west side of 17th Street, which

sit on a curved grade beam foundation supported by twenty-four reinforced concrete caissons

running underground across the street. The grade beam foundation running across 17th Street

contains eight “post pockets.” In the event of a 100-year flood, these pockets are filled with an

eight-foot-tall temporary metal post and aluminum panel system that connect to the east and west

levee stem walls to block surging floodwaters. The images below illustrate the Project.

Images: completed stone-clad levee stem walls (Source Pl.’s Ex. 5)

Drawing of 17th Street levee (Source: Washington Post)

Following a bid process, on September 16, 2010, the USACE awarded Hirani the contract

(“the Prime Contract”) to construct the 17th Street levee wall for the amount of $3,833,097.00.

The USACE subsequently awarded “Option 1” to Hirani on December 16, 2010, requiring Hirani

3 to install stone veneer cladding and coping on the permanent levee walls for $641,369.00. As

required by Hirani’s contract with the USACE, Colonial issued performance and payment bonds

on behalf of Hirani.

On April 4, 2011, ACC and Hirani entered into a fixed-price subcontract (“the

Subcontract”) for $2,845,600.00, under which ACC agreed to perform most, but not all, of Hirani’s

obligations under the Prime Contract. ACC began performing under the Subcontract a week later,

and Hirani subsequently subcontracted Option 1 to ACC in the amount of $613,650.00.

The ensuing years on the Project were beset by a series of delays, modifications to the

scope of the Project, and work-related disputes. By letter dated April 26, 2013, two-and-a-half

years after it awarded the Prime Contract to Hirani, the USACE gave notice of its intent to

terminate Hirani. In the days following Hirani’s termination, ACC left the Project site. The

USACE subsequently made a demand against the Performance Bond issued by Colonial, and

Colonial stepped in to complete the Project. With the assistance of Loewke Brill, a consulting

firm, Colonial contracted with Akima Construction Services, LLC, Lorton Stone, LLC, and

Structural Stone, LLC, to complete the Project, including Option 1, and did so around November

2014.

B. Procedural Background

ACC filed suit in this court against Hirani and Colonial on April 29, 2014. See Compl.,

ECF No. 1. Colonial responded by filing four counterclaims against ACC: (1) two for breach of

contract, one as assignee of Hirani and one as surety; (2) one for breach of the covenant of good

faith and fair dealing; and (3) one for interference with contractual relations. See Def. Colonial’s

Answer & Countercls., ECF No. 8. With leave of court, Plaintiff filed a Second Amended

Complaint on February 16, 2016, asserting two claims: (1) breach of contract against Hirani, and

4 (2) a payment demand under the Miller Act against Colonial, premised on the payment bond

Colonial issued in connection with the Prime Contract. Plaintiff’s Second Amended Complaint

sought quantum meruit damages in the amount of $2,070,185.23. See Second Amended Compl.,

ECF No. 26.

Following discovery, Defendants jointly filed a Motion for Summary Judgment and a

Motion to Strike Plaintiff’s Jury Demand. See Defs.’ Mot. for Summ. J., ECF No. 44; Defs.’ Mot.

to Strike Jury Demand, ECF No. 45. The court denied Defendants’ Motion for Summary Judgment

and granted Defendants’ Motion to Strike the Jury Demand on June 27, 2017. See Mem. Op.,

ECF No. 54; Order, ECF No. 55. Following a delay in the proceedings, the parties appeared for a

Pretrial Conference on February 23, 2018. See Pretrial Conf. Hrg. Tr. (February 23, 2018),

ECF No. 75. The court thereafter conducted a bench trial over the course of five days from March

5, 2018, to March 9, 2018. See Trial Tr. Day 1 A.M. Session (March 5, 2018), ECF No. 76

[hereinafter Day 1 A.M. Tr.]; Trial Tr. Day 1 P.M. Session [hereinafter Day 1 P.M. Tr.]; Trial Tr.

Day 2 A.M. Session (March 6, 2018), ECF No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ex Parte Southwestern Surety Insurance
247 U.S. 19 (Supreme Court, 1918)
United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
Fleischmann Distilling Corp. v. Maier Brewing Co.
386 U.S. 714 (Supreme Court, 1967)
United States v. Winstar Corp.
518 U.S. 839 (Supreme Court, 1996)
Lakhdar Boumediene v. Barack Obama
610 F.3d 718 (D.C. Circuit, 2010)
Morrison Knudsen Corp. v. Fireman's Fund Insurance
175 F.3d 1221 (Tenth Circuit, 1999)
GE Supply v. C & G Enterprises, Inc.
212 F.3d 14 (First Circuit, 2000)
Nepera Chemical, Inc. v. Sea-Land Service, Inc.
794 F.2d 688 (D.C. Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
American Civil Construction, LLC v. Hirani Engineering & Land Surveying, Pc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-civil-construction-llc-v-hirani-engineering-land-surveying-pc-dcd-2018.