American Civil Construction, LLC v. Hirani Engineering & Land Surveying, Pc

CourtDistrict Court, District of Columbia
DecidedAugust 26, 2020
DocketCivil Action No. 2014-0745
StatusPublished

This text of American Civil Construction, LLC v. Hirani Engineering & Land Surveying, Pc (American Civil Construction, LLC v. Hirani Engineering & Land Surveying, Pc) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Civil Construction, LLC v. Hirani Engineering & Land Surveying, Pc, (D.D.C. 2020).

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

_________________________________________ ) UNITED STATES OF AMERICA, for the use ) and benefit of AMERICAN CIVIL ) CONSTRUCTION, LLC, ) ) Plaintiff, ) ) v. ) Case No. 14-cv-00745 (APM) ) HIRANI ENGINEERING & LAND ) SURVEYING, P.C., et al., ) ) Defendants. ) _________________________________________ )

SUPPLEMENTAL FINDINGS OF FACT AND CONCLUSIONS OF LAW

This matter is on remand from the D.C. Circuit for additional fact-finding on

Plaintiff American Civil Construction, LLC’s Miller Act claim against Defendant Colonial Surety

Company and Colonial’s statute-of-limitations defense to that claim. The Circuit directed this

court “to make findings of fact as to when the Prime Contract was terminated and whether ACC

performed labor or supplied material on April 29 and/or April 30.” United States ex rel. Am. Civil

Constr., LLC v. Hirani Eng’g & Land Surveying, PC, 962 F.3d 587, 594 (D.C. Cir. 2020)

(“Hirani II”). On remand, the court invited the parties to address these issues in supplemental

filings. See Pl.’s Supplemental Proposed Findings of Fact and Conclusions of Law, ECF No. 106

[hereinafter Pl.’s Suppl.]; Defs.’ Supplemental Proposed Findings of Fact and Conclusions of Law,

ECF No. 107 [hereinafter Defs.’ Suppl.]. Having considered the parties’ submissions, and the

entire trial record, the court makes the following supplemental findings of fact and conclusions of

law. When the Prime Contract was Terminated

1. In a letter dated Friday, April 26, 2013, Contracting Officer Jerome T. Rifkin of the

U.S. Army Corps of Engineers (“USACE”) terminated the Prime Contract between the USACE

and Hirani Engineering and Land Surveying, P.C. (“Termination Letter”). Pl.’s Ex. 150; Def.’s

Ex. 77. According to the letter, the “termination [was] effective immediately.” Id.

2. The Termination Letter appears twice in the trial record: Plaintiff’s Exhibit 150

and Defendants’ Exhibit 77. The first two pages of each exhibit are the same, consisting of the

text of the correspondence. The face of the Termination Letter indicates it was sent from the

USACE in Baltimore, Maryland, via “CERTIFIED MAIL-RETURN RECEIPT REQUESTED,”

to Jitendra Hirani, President of Hirani Engineering and Land Surveying, P.C., at Hirani’s office in

Jericho, New York. Defs.’ Ex. 77 at 1; Pl.’s Ex. 150 at 1. The record contains no return receipt

card indicating the date of delivery, signed by Mr. Hirani or any other company representative.

3. Defendants’ Exhibit 77 contains a third page titled “ACKNOWLEDGMENT OF

RECEIPT.” Defs.’ Ex. 77 at 3. This third page requests that an “Authorized Representative” of

Hirani “sign and return this notice in the enclosed envelope.” Id. Apparently, no authorized

representative of Hirani formally acknowledged receipt, as the date and signature blocks are blank.

Id.

4. Neither party presented any testimonial evidence as to the actual date on which the

USACE sent the Termination Letter, the actual means of transmittal (e.g., certified mail, email, or

fax), or the actual date on which Hirani received the Termination Letter.

5. In a letter dated April 30, 2013, Jitrendra Hirani responded to the Termination

Letter. Pl.’s Ex. 151. As pertinent here, Mr. Hirani wrote: “On April 29, 2013, about 20 minutes

2 before the issuance of the default termination, the USACE called Hirani to communicate, via

telephone, that an interim unsatisfactory performance evaluation, among other things, was

generated by the USACE’s computer mailing system in late March 2013 (allowing for 30 days to

respond or cure) that was never received by Hirani Engineering.” Id. (emphasis added). There

was no testimony about a call between the USACE and Mr. Hirani on April 29, 2013; nor did

Mr. Hirani explain what he meant by receipt of a call from the USACE “about 20 minutes before

the issuance of the default termination.”

6. Nearly a year later, Hirani alleged in a complaint filed in the Court of Federal

Claims on April 25, 2014, that it had received the Termination Letter on Monday, April 29, 2013.

Pl.’s Ex. 168 at 9; see also Trial Tr., Mar. 5, 2018, PM Sess., at 32–33. There was no trial testimony

as to how Hirani determined it had received the Termination Letter on that date when drafting the

complaint. Absent such testimony, the complaint is weak proof of the actual date of receipt.

7. In consideration of the foregoing evidence, the court finds that Hirani received the

Termination Letter no earlier than Tuesday, April 30, 2013, the date that Mr. Hirani issued the

company’s response letter. Defendants have not carried their burden of establishing an earlier date

of receipt. See Hirani II, 962 F.3d at 593 (stating that, as proponents of the statute of limitations

defense, Defendants “will bear the burden of showing that Hirani received the termination letter

before Monday, April 29”). Accordingly, the “effective date of the termination” of the Prime

Contract, per the Federal Acquisition Regulations, is no earlier than Tuesday, April 30, 2013.

See Hirani II, 962 F.3d at 593 (citing 48 C.F.R. § 2.101) (providing that “[i]f the contractor

receives the termination notice after the date fixed for termination, then the effective date of

termination means the date the contractor receives the notice”).

3 8. Defendants do not assert that Hirani actually received the Termination Letter on

Sunday, April 28, 2013, or earlier. See generally Defs.’ Suppl. at 2–3 & n.3 (asserting that the

record evidence supports receipt of the Termination Letter on Monday, April 29, 2013). 1 Instead,

they urge the court to find that the “record evidence reveals that ACC, at trial, conceded that the

Corps’ termination of Hirani was effective prior to April 29, 2013.” Id. at 1. ACC made no such

concession. Defendants cite to statements made by ACC at the summary judgment stage that the

USACE “terminated” the Prime Contract on April 26, 2013, see id. at 2 (citing ECF No. 46 at 9;

ECF No. 46-2 at 7, ¶ 27; ECF No. 46-3 at 8, ¶ 31), but each of those statements simply recites the

fact of the date of Termination Letter. The same is true of Defendants’ citation to ACC’s Pre-Trial

Statement, see Defs.’ Suppl. at 3 (citing ECF No. 65 at 10), and ACC’s opening statement at trial,

see id. (citing Trial Tr., Mar. 5, 2018, AM Sess., at 8). None of those statements constitute a legal

concession about the effective date of the Prime Contract’s termination for statute of limitations

purposes. See 32 C.J.S. Evidence § 542 (“A judicial admission, to be binding, must be one of

fact and not a conclusion of law . . . or statements of legal theories or conceptions.”); McNamara

v. Picken, 950 F. Supp. 2d 125, 129 (D.D.C. 2013) (observing that “[i]t is well established that

judicial admissions on questions of law have no legal effect”) (citation omitted).

Whether ACC Performed Labor or Supplied Materials on April 29 and/or April 30

9. ACC’s Project crew performed no work on April 29, 2013. ACC’s daily report for

that date states in relevant part: “No work today; Rained Out Today; No possibility of work today;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
American Civil Construction, LLC v. Hirani Engineering & Land Surveying, Pc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-civil-construction-llc-v-hirani-engineering-land-surveying-pc-dcd-2020.