Towerridge, Inc., Sued as United States of America for the Benefit of Towerridge, Inc., and v. T.A.O., Inc., and Mid-Continent Casualty Co., And

111 F.3d 758, 41 Cont. Cas. Fed. 77,125, 46 Fed. R. Serv. 1411, 1997 U.S. App. LEXIS 7141, 1997 WL 178939
CourtCourt of Appeals for the Tenth Circuit
DecidedApril 15, 1997
Docket96-6015, 96-6107
StatusPublished
Cited by89 cases

This text of 111 F.3d 758 (Towerridge, Inc., Sued as United States of America for the Benefit of Towerridge, Inc., and v. T.A.O., Inc., and Mid-Continent Casualty Co., And) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Towerridge, Inc., Sued as United States of America for the Benefit of Towerridge, Inc., and v. T.A.O., Inc., and Mid-Continent Casualty Co., And, 111 F.3d 758, 41 Cont. Cas. Fed. 77,125, 46 Fed. R. Serv. 1411, 1997 U.S. App. LEXIS 7141, 1997 WL 178939 (10th Cir. 1997).

Opinion

BRORBY, Circuit Judge.

I. BACKGROUND

This action was brought by Towerridge, Inc., a subcontractor on a federal' construction project, against the prime contractor, T.A.O., Inc., and T.A.O.’s surety on the prime contract, Mid-Continent Casualty Company. Towerridge sued under the Miller Act, 40 U.S.C. §§ 270a-270d (1994), seeking recovery for sums allegedly due and owing under its subcontract. The jury awarded Tower-ridge $56,963.94 in damages and, in response to a special interrogatory, found T.A.O. acted in bad faith. The district court entered judgment accordingly, and later awarded Tower-ridge prejudgment interest and attorneys’ fees. T.A.O. appeals the award of damages, the award of prejudgment interest, and the award of attorneys’ fees. It also appeals the district court’s admission into evidence of references to a separate action between T.A.O. and the government. Towerridge cross-appeals the district court’s failure to note the jury’s finding of bad faith on its entry of judgment. We reverse the district court’s award of attorneys’ fees and affirm the district court on all other issues.

T.A.O. was the prime contractor on a construction project for the Oklahoma Air National Guard in Oklahoma City. Because the project was federally funded, T.A.O. was required under the Miller Act to post a payment bond to protect subcontractors and ma-terialmen. 1 Co-defendant Mid-Continent Casualty Co. was the surety on the bond.

*761 Under the prime contract, T.A.O. submitted monthly payment applications to the government. These payment applications stated the scheduled value of each of sixty-nine line-item tasks which made up T.A.O.’s obligations under the contract, the sum of which equaled the contract price. The applications also provided estimated percentages of completion of both the actual line item tasks and their scheduled values. Upon receipt of the applications, the government paid T.A.O. the percentage of scheduled values completed, minus a retainage due upon completion of the project.

Towerridge subcontracted with T.A.O. to perform most of the concrete and asphalt paving work for the project. The total subcontract price was $448,520.00. The subcontracted work was broken down into four line items: (1) concrete paving, dowels and sawing, (2) curb and gutter, (3) sealant, and (4) rock and asphalt. The subcontract assigned each line item a scheduled value representing its proportionate value of the whole; thus the sum of the scheduled values equaled the subcontract price. T.A.O. was to make monthly progress payments to Towerridge for work satisfactorily completed, minus a ten percent retainage. To that end, Tower-ridge submitted monthly payment applications to T.A.O. providing estimated completion percentages of the line-item tasks, and the appropriate percentage of each line item’s scheduled value to which Towerridge was therefore entitled. Thus, ideally, upon Towerridge’s completion of twenty percent of a line item, T.A.O. was to pay Towerridge twenty percent of that line item’s scheduled value; when Towerridge had completed ninety percent of a line item it was entitled to ninety percent of the scheduled value, and so forth. 2

Towerridge started work in June 1993. However, nearly from the beginning of Tow-erridge’s performance, T.A.O. and Tower-ridge disagreed over whether Towerridge was working sufficiently productively and efficiently to complete its work on schedule, Timely completion of all portions of the project was of particular importance to T.A.O. because its prime contract contained a liquidated damages clause rendering T.A.O. liable to the government for $296.85 for each day completion was delayed beyond the scheduled completion date.

The parties dispute to whom blame for any delays or defects in Towerridge’s performance should be attributed. Both note delays and disruptions caused by the government hampered completion of the overall project; however, they disagree on the extent the government’s actions impaired Tow-erridge’s ability to perform. Towerridge asserts it was at all times ready and able to meet its obligations -under the subcontract, and that any delays in its performance were caused by T.A.O. and the government’s failure to satisfy necessary preconditions to Towerridge’s performance, such as clearing, grading and surveying. Additionally, Tower-ridge claims T.A.O. failed to properly schedule, supervise, and coordinate the project, and that any defects in its work were the result of T.A.O.’s inadequate project management rather than the fault of Towerridge. T.A.O., on the other hand, contends Tower-ridge repeatedly left the work site and failed to use sufficient workers to timely complete its work, even after T.A.O. repeatedly warned of the necessity for Towerridge to increase its workforce and speed its performance. T.A.O. also contends Towerridge’s work was substandard, containing numerous defects requiring repair or reconstruction, further delaying completion. Eventually, T.A.O. hired supplemental subcontractors to complete and correct the work Towerridge was to have performed.

Moreover, with the exception of Tower-ridge’s first monthly payment application in July 1993, T.A.O. and Towerridge did not agree on the percentage of work completed by Towerridge. For example, the eomple- *762 üon percentages set forth in Towerridge’s second pay application resulted in a claim to T.A.O. for $110,817.00. However, T.A.O. only paid Towerridge $92,248.20. By the time T.A.O. terminated Towerridge, their opinions on the amount of work completed had grown further disparate. Towerridge’s fifth, and final, pay application showed 87% completion of the concrete paving, 67% completion of the curb and gutter work, 82% completion of the sealant, and 53% completion of the asphalt paving. However, T.A.O. claimed Towerridge had actually completed only 73%, 59%, 73%, and 35% of each line item, respectively, and paid Towerridge accordingly.

Towerridge brought suit for the sums it claimed were due and owing for work allegedly performed. At trial, it asserted entitlement to $56,963.94. It reached this figure by subtracting the amount paid by T.A.O. ($245,875.82) from the amount, not including retainage, billed T.A.O. for work completed ($322,335.90), totaling $76,460.08. It then added $35,815.90 in withheld retainage, $3,133.00 for work performed under a change order modifying the original subcontract, and $677.00 for labor provided subsequent to its final pay application. Finally, it credited T.A.O. for $47,287.04 T.A.O. paid directly to one of Towerridge’s suppliers and $11,835.00 T.A.O. paid directly to a sub-contractor of Towerridge, arriving at the final total of $56,-963.94.

II. ANALYSIS

A. Damages Award

T.A.O. first asserts the district court erred in refusing to grant T.A.O.’s motion for judgment as a matter of law, in which T.A.O. claimed Towerridge was not entitled to recover under the Miller Act because it had failed to provide any evidence of sums owed for work performed under the subcontract. We review the district court’s denial of T.A.O.’s motion de novo, Haines v. Fisher, 82 F.3d 1503

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MVT Services v. Great West Casualty Company
118 F.4th 1274 (Tenth Circuit, 2024)
Dalton M, LLC v. North Cascade Trustee Services, Inc.
Court of Appeals of Washington, 2022
City of Albuquerque v. Barr
D. New Mexico, 2021
FDIC v. Chicago Title Insurance Compa
12 F.4th 676 (Seventh Circuit, 2021)
Maxfield v. Cox
D. Utah, 2021
Doe v. United States
S.D. Florida, 2019
United States v. Hirani Eng'g & Land Surveying, P.C.
345 F. Supp. 3d 11 (D.C. Circuit, 2018)
Bogustawa Frey v. Hotel Coleman
Seventh Circuit, 2018
Xyngular, Corp. v. Schenkel
890 F.3d 868 (Tenth Circuit, 2018)
White v. Wycoff
862 F.3d 1065 (Tenth Circuit, 2017)
SFF-TIR, LLC v. Stephenson
250 F. Supp. 3d 856 (N.D. Oklahoma, 2017)
Xyngular Corp. v. Schenkel
200 F. Supp. 3d 1273 (D. Utah, 2016)
United States v. Reyna
98 F. Supp. 3d 895 (W.D. Texas, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
111 F.3d 758, 41 Cont. Cas. Fed. 77,125, 46 Fed. R. Serv. 1411, 1997 U.S. App. LEXIS 7141, 1997 WL 178939, Counsel Stack Legal Research, https://law.counselstack.com/opinion/towerridge-inc-sued-as-united-states-of-america-for-the-benefit-of-ca10-1997.