U.S. for Use of Barber-Colman Co. v. U.S. Fidelity & Guar. Co.

19 F.3d 1431, 1994 U.S. App. LEXIS 12927, 1994 WL 108502
CourtCourt of Appeals for the Third Circuit
DecidedMarch 31, 1994
Docket93-1665
StatusUnpublished
Cited by5 cases

This text of 19 F.3d 1431 (U.S. for Use of Barber-Colman Co. v. U.S. Fidelity & Guar. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.S. for Use of Barber-Colman Co. v. U.S. Fidelity & Guar. Co., 19 F.3d 1431, 1994 U.S. App. LEXIS 12927, 1994 WL 108502 (3d Cir. 1994).

Opinion

19 F.3d 1431

NOTICE: Fourth Circuit I.O.P. 36.6 states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Fourth Circuit.
UNITED STATES of America, for the use of Barber-Colman
Company, Plaintiff-Appellee,
v.
UNITED STATES FIDELITY & GUARANTY COMPANY, Defendant-Appellee,
v.
Frederick J. FRANK, Third Party Defendant-Appellant,
and
Macco Contracting, Incorporated; Susan T. Frank, Third
Party Defendants.

No. 93-1665.

United States Court of Appeals, Fourth Circuit.

Submitted March 8, 1994.
Decided March 31, 1994.

Appeal from the United States District Court for the District of South Carolina, at Columbia. Robert R. Merhige, Jr., Senior District Judge, sitting by designation. (CA-91-1780)

Frederick J. Frank, appellant Pro Se.

Robert Francis McMahan, Jr., Columbia, SC, Jackson L. Barwick, Jr., Baker, Barwick, Ravenel & Bender, Columbia, SC, for appellees.

D.S.C.

AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.

Before MURNAGHAN, HAMILTON, and WILLIAMS, Circuit Judges.

OPINION

PER CURIAM:

This is an appeal from a trial and judgment pursuant to the Miller Act. 40 U.S.C. Secs. 270a-270d (1988). The Miller Act is designed to provide a remedy for unpaid "persons supplying labor and material in the prosecution of the work provided for" on federal projects. The Act supplants state mechanic's lien law in that it provides a remedy for sub-contractors who would ordinarily be able to file a mechanic's lien on property for which they had provided labor and materials. F.D. Rich Co. v. United States ex. rel Industrial Lumber Co., 417 U.S. 116, 122 (1974).

Frederick Frank, through his corporation Macco Contracting (Macco), entered into a contract with the United States Government for the construction of a Marine Corps Reserve Center in South Carolina. Macco, pursuant to the terms of the Miller Act, posted a payment bond issued by United States Fidelity & Guaranty Company (USF & G). The bond contained a broad indemnity agreement by which Macco and Frank agreed to indemnify USF & G for losses by reason of the bond, including attorney's fees. Macco subcontracted a portion of the work to Thomas Plumbing and Heating Company (Thomas). Thomas, in turn subcontracted the heating, ventilation, and air conditioning work to Barber-Colman Company (Barber-Colman). Barber-Colman subcontracted with Fogle Electric (Fogle) to do the electric work on site.

Barber-Colman began work on the project, specifically through the translation of the Army Corps of Engineers' schematics into control drawings. Michael Hendrick, Barber-Colman's application engineer, created those drawings and performed other work on the project for over eighty-five hours. Hendrick had one meeting on site with Thomas, on October 5, 1990. At that meeting changes were proposed and accepted. Hendrick incorporated those changes on October 18 and compiled a new submittal package on October 19. Based on those changes, Hendrick ordered new equipment for the project in the last week of October. The material arrived and Hendrick inventoried and warehoused it over the course of the next three weeks, ending the second week in November. There is no evidence in the record or transcript that any of this material was tendered to Macco or delivered to the site. Fogle did a small amount of work on the site at some point during November. Although Carlisle Fogle could not testify as to the exact date that Fogle was last on site, based on the billing to Barber-Colman at the end of November, Fogle testified that he "believe[d] it was around [the November] time frame." (Tr. at 23.)

In October, before the project was completed, Thomas went out of business. Because there was no direct contractual relationship between Macco and Barber-Colman, both parties were concerned about how their rights would be protected after Thomas's default. Barber-Colman refused to perform unless Macco paid the performance payment that was due under the contract between Barber-Colman and Thomas. Macco refused to pay Barber-Colman without more substantial performance. After some negotiations between Barber-Colman and Macco during which the possibility of a new subcontract was discussed, Barber-Colman sent a letter dated October 25 stating that it would not perform further until a new purchase order could be written. Macco continued to attempt to get Barber-Colman to perform up until October 31. Macco eventually sub-contracted with Johnson Controls to fill the void left by Thomas and Barber-Colman.

On January 25, 1991,1 Barber-Colman sent Macco notice under the Miller Act. After Macco had rejected Barber-Colman's claim, Barber-Colman filed this action against USF & G, Macco's surety. USF & G impleaded Macco as a third-party defendant on the terms of the bond, claiming indemnification and its own attorney's fees. Following a one-day trial, the district court announced its judgment and opinion from the bench and found for Barber-Colman against USF & G and for USF & G against Macco.

Frank raises eight issues on appeal. As a third-party defendant, Frank is entitled to assert on appeal errors in the main case between USF & G and Barber-Colman. United States v. Lumbermens Mut. Casualty Co., 917 F.2d 654, 658 n. 5 (1st Cir.1990); Kicklighter v. Nails by Jannee, Inc., 616 F.2d 734, 738 n. 1 (5th Cir.1980). The first, whether Barber-Colman gave notice within ninety days of the last work provided on the project, is dispositive. Notice of a claim under the Miller Act is a strict condition precedent to a sub-contractor's right of recovery. United States ex rel. John D. Ahern Co. v. J. F. White Contracting Co., 649 F.2d 29, 31 (1st Cir.1981); United States ex rel. Noland Co. v. Andrews, 406 F.2d 790, 791 (4th Cir.1969).

Frank contends on appeal that the district court erred in concluding that Barber-Colman's notice of its claim was timely under the Miller Act. The Miller Act requires

[t]hat any person having direct contractual relationship with a subcontractor but no contractual relationship ... with the contractor furnishing said payment bond shall have a right of action ... upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished ... the last of the material for which such claim is made.

40 U.S.C. Sec. 270b(a) (1988). Here, Barber-Colman had a direct contractual relationship with Thomas, Macco's sub-contractor. There was no contractual relationship between Barber-Colman and Macco.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
19 F.3d 1431, 1994 U.S. App. LEXIS 12927, 1994 WL 108502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-for-use-of-barber-colman-co-v-us-fidelity-guar-co-ca3-1994.