United States of America for the Use and Benefit of Warren Painting Co., Inc. v. J. C. Boespflug Construction Co. And Travelers Indemnity Co.

325 F.2d 54, 1963 U.S. App. LEXIS 3697
CourtCourt of Appeals for the Ninth Circuit
DecidedNovember 18, 1963
Docket18570
StatusPublished
Cited by6 cases

This text of 325 F.2d 54 (United States of America for the Use and Benefit of Warren Painting Co., Inc. v. J. C. Boespflug Construction Co. And Travelers Indemnity Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America for the Use and Benefit of Warren Painting Co., Inc. v. J. C. Boespflug Construction Co. And Travelers Indemnity Co., 325 F.2d 54, 1963 U.S. App. LEXIS 3697 (9th Cir. 1963).

Opinion

HAMLEY, Circuit Judge.

This is a suit, brought under the Miller Act, § 2, 49 Stat. 794 (1935), 40 U.S.C. § 270b (1958), to recover compensation for work performed in the construction of a government facility near Anchorage, Alaska. The action was brought on behalf of Warren Painting Company, Inc. (Warren), painting subcontractor on the project. The general contractor, J. C. Boespflug Construction Co. (Boespflug), and the surety on the general contractor’s payment bond, Travelers Indemnity Co., were named defendants.

Three claims were stated in the complaint, one of which involved asserted additional work necessitated by the unsatisfactory condition of the plaster surfaces. Recovery in the sum of $20,092.-74 was sought under this claim. Plaintiff appeals from that part of the judgment which disallowed this item. Defendants cross-appeal, contending that certain time cards and other documents offered by plaintiff in proof of damages, were erroneously received in evidence.

Boespflug was the prime contractor for the construction of a seven-story hospital at Elmendorf Air Force Base, on the outskirts of Anchorage. It awarded a subcontract for painting to Warren. Warren’s subcontract, entered into on April 29, 1953, called for completion of its work by July 1, 1955.

By October, 1954, the plastering subcontractor had completed the plastering of the ground floor of the hospital, and Warren began the painting of that area. So many structural and radial cracks in the plaster were discovered at this time that Warren wrote to Boespflug, under date of October 20,1954, stating that application of the first coat of paint did not constitute acceptance of the surface by Warren. 1 The presence of these cracks *56 was apparently due in part to an earthquake which had occurred early in October, 1954, and in part to the poor quality of the plastering job.

By December, 1954, most of the plastering had been completed. On December 10 of that year a second earthquake occurred, with consequent additional damage to the plastered surfaces. Testimony offered in behalf of Warren indicated that the patching by the plastering contractor was insufficient and, as a result, Warren was required to chop out and replace plaster around structural cracks. The trial court found that Warren performed certain repairs to the plastered surfaces “which were in a damaged and unsatisfactory condition, as more particularly set forth in Paragraph VIII of Plaintiff’s Amended Complaint.” 2

The Court further found:

“That the plastering had been previously installed by another subcontractor and was in such a condition as to prevent the Plaintiff from performing its subcontract work in accordance with the applicable painting specifications.”

As a result of the circumstances described above, a controversy developed between Warren and the plastering subcontractor. On January 18, 1955, Warren wrote to Boespflug complaining of the method being used by the plastering subcontractor in patching major cracks. In another letter to Boespflug, written on the same day, Warren suggested roller stippling as a part of the paint application, indicating, however, that this operation would add an additional cost. Roller stippling is the application of a very heavy coat of paint by the use of brushes, which coat is then “rolled” out with a roller stipple. 3

Boespflug replied, on February 25, 1955, that the roller stippling method had been accepted by the government inspector, at no additional cost to the government. 4 On March 1,1955, Warren wrote to Boespflug, advising that Warren did not intend to stipple the walls unless the plans and specifications were amended to provide for such application and additional compensation was provided by the government or other parties. In this letter, Warren also stated that if painting were to be done in accordance with present specifications, it would not proceed *57 with painting until notified by the government or Boespfiug that the plaster i~ acceptable and that Warren should proceed with the painting. 5

Having received no response to this letter by March 15, 1955, Warren on that date again wrote to Boespfiug, indicating that it was awaiting a directive to pro ceed, a notification from the government that the plaster work was acceptable, and a decision concerning the stippling of walls. In this letter Warren stated that unless such advice were received by March 29, 1955, it would not be possible to meet the painting completion date of July 1, 1955. At a conference with Boespfiug officials held on March 26, 1955, a representative of Warren orally reiterated the position stated in Warren's letters of March 1 and 15, 1955.

On March 26, 1955, following this conference, Boespfiug wrote to Warren, advising that it regarded Warren's statement that it would do no more painting until it received notice from the government or Boespfiug that the plaster was acceptable, and a directive to proceed with the painting, as a breach of contract. Warren was told in this letter that Boespfiug would not furnish such a directive and would not request the government to do so. Boespfiug called upon Warren to repudiate its statement referred to above by March 29, 1955, advising that unless this were done, Boespfiug would consider that Warren had breached its contract and would ask the latter's bonding company to take over completion of the painting subcontract. 6

Further conferences were had and, on March 28, 1955, Warren advised ]3oespfiug in writing that the extra cost involved in doing the stippling would be $8,321.07. There is no indication that Boespfiug agreed to this figure, or agreed `to pay any amount above that called for in the contract, to cover the cost of stippling or the cost of plaster repairing performed by Warren.

Three days later, on March 31, 1955, Warren advised Boespfiug that a solution of the controversy had been reached as a result of a conference with the plastering subcontractor. Under this arrangement Warren would request a change order permitting the stippling without charge to the government or change of contract price. The plastering subcontractor would contribute the sum of $2,500 in payment of the anticipated additional costs, and Warren would absorb the balance of any additional costs entailed by the stippling. But Boespfiug was also advised in this letter:

"This modification, if acceptable to the Government, is made with reservation of the position which we assumed with respect to acceptance of the existing surface. Thus, in accordance with the fourth paragraph of the letter of March 26th, we are not waiving any claims that we may have that arise by reason of future conditions of the plaster."

The plastering subcontractor thereafter agreed in writing to contribute the $2,500 called for by his understanding with Warren, 7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
325 F.2d 54, 1963 U.S. App. LEXIS 3697, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-warren-painting-co-ca9-1963.