Mai Steel Service Inc., a Kansas Corporation v. Blake Construction Company, and Molnick's Inc., a Corporation, Mai Steel Service Inc., a Kansas Corporation, and Blake Construction Company and Aetna Casualty & Surety Company, and Commercial Union Insurance Company v. Molnick's Inc., a Corporation

981 F.2d 414, 38 Cont. Cas. Fed. 76,358, 92 Daily Journal DAR 9116, 1992 U.S. App. LEXIS 14719
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 30, 1992
Docket88-6409
StatusPublished
Cited by1 cases

This text of 981 F.2d 414 (Mai Steel Service Inc., a Kansas Corporation v. Blake Construction Company, and Molnick's Inc., a Corporation, Mai Steel Service Inc., a Kansas Corporation, and Blake Construction Company and Aetna Casualty & Surety Company, and Commercial Union Insurance Company v. Molnick's Inc., a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mai Steel Service Inc., a Kansas Corporation v. Blake Construction Company, and Molnick's Inc., a Corporation, Mai Steel Service Inc., a Kansas Corporation, and Blake Construction Company and Aetna Casualty & Surety Company, and Commercial Union Insurance Company v. Molnick's Inc., a Corporation, 981 F.2d 414, 38 Cont. Cas. Fed. 76,358, 92 Daily Journal DAR 9116, 1992 U.S. App. LEXIS 14719 (9th Cir. 1992).

Opinion

981 F.2d 414

38 Cont.Cas.Fed. (CCH) P 76,358

MAI STEEL SERVICE INC., a Kansas Corporation, Plaintiff-Appellee,
v.
BLAKE CONSTRUCTION COMPANY, Defendant,
and
Molnick's Inc., a Corporation, Defendant-Appellant.
MAI STEEL SERVICE INC., a Kansas Corporation, Plaintiff-Appellee,
and
Blake Construction Company; and Aetna Casualty & Surety
Company, Defendant-Appellee,
and
Commercial Union Insurance Company, Defendant-Appellee,
v.
MOLNICK'S INC., a Corporation, Defendant-Appellant.

Nos. 88-6409, 88-6410.

United States Court of Appeals,
Ninth Circuit.

Argued and Submitted April 7, 1992.
Decided June 30, 1992.

Robert S. Kilborne, San Diego, CA, for defendant-appellant.

James L. Trachy, Anderson, McPharlin & Conners, Los Angeles, CA and Judah Lifschitz, Shapiro & Lifschitz, Washington, DC, for defendants-appellees.

Oscar Irwin, Hillyer & Irwin, San Diego, CA, for the plaintiff-appellee.

Appeal from the United States District Court for the Southern District of California.

Before: PREGERSON, D.W. NELSON and THOMPSON, Circuit Judges.

DAVID R. THOMPSON, Circuit Judge:

This appeal challenges a district court ruling that appellant Molnick's Inc., a steel installer on a federal construction project, cannot recover under either the prime contractor's Miller Act payment bond or the subcontractor's common law payment bond for its increased labor and material costs attributable to construction delays. We have jurisdiction under 28 U.S.C. § 1291 and we reverse. We also conclude that the prime contractor's surety is entitled to indemnification from the subcontractor's surety to the extent of its liability for Molnick's additional costs.

FACTUAL BACKGROUND

The Department of the Navy hired Blake Construction Company to build a naval hospital in San Diego, California. Pursuant to the Miller Act, 40 U.S.C. § 270a-270d, Blake obtained two Miller Act bonds from Aetna Casualty Insurance. One bond guaranteed Blake's performance under its contract with the United States government. The other bond guaranteed payment to all persons supplying labor or materials to the project.1

Blake subcontracted with Mai Steel Services to fabricate and install the hospital's steel framework. Mai furnished a performance bond for $6,940,000, guaranteeing the satisfactory completion of the framework. It also provided a payment bond for the same amount. Commercial Union Insurance was the surety on both bonds.

Blake also subcontracted with Molnick's to install the hospital's steel decking. Under the terms of this subcontract, Molnick's was required to finish the decking no more than six months after the framework was in place.

Mai entered into a sub-subcontract with Molnick's. This sub-subcontract obligated Molnick's to assume all responsibility for installing the hospital's framework. Molnick's was given five months to finish the task. Molnick's conditioned its performance on Mai's ability to supply it with steel and other materials according to a predetermined schedule.

Mai never lived up to its part of the sub-subcontract. Its steel shipments were routinely late and often included defective materials. As a result, Molnick's incurred sizeable cost overruns and failed to complete the framework on time. Mai's inability to deliver the materials as promised also prevented Molnick's from installing the steel decking on schedule.

Molnick's sued Mai in the district court for breach of the framework contract and for tortious interference with the decking contract.2 In these actions, Molnick's sought to recover the unpaid balance of the framework contract,3 plus additional labor and material costs it incurred in completing both the framework and decking contracts.

A jury found in favor of Molnick's on its breach of contract claim against Mai, and awarded Molnick's damages for the unpaid balance of the framework contract,4 plus $1,154,008 in additional labor and material costs Molnick's incurred in completing that contract. The jury also found that Mai had tortiously interfered with Molnick's performance of the decking contract with Blake, and awarded Molnick's an additional $758,818 for the increased labor and material costs Molnick's was forced to expend in completing the decking contract. Mai failed to satisfy either judgment and has since filed a petition in bankruptcy.

At a post-trial hearing, the district court concluded that neither Aetna nor Commercial Union was liable for the increased labor and material costs Molnick's was awarded against Mai. Molnick's appeals this ruling.

DISCUSSION

A. Aetna's Liability to Molnick's

The Miller Act requires a general contractor on a federal construction project to furnish "[a] payment bond ... for the protection of all persons supplying labor and material in the prosecution of the work provided for in [the] contract." 40 U.S.C. § 270a(a)(2). The Act "represents a congressional effort to protect persons supplying labor and material for the construction of federal public buildings in lieu of the protection they might receive under state statutes with respect to the construction of nonfederal buildings." United States ex rel. Sherman v. Carter, 353 U.S. 210, 216, 77 S.Ct. 793, 797, 1 L.Ed.2d 776 (1957). Because the Act is "highly remedial in nature," it must be liberally construed to effectuate Congress's intent. Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102, 107, 64 S.Ct. 890, 893, 88 L.Ed. 1163 (1944).

Under the Act, "[e]very person who has furnished labor or material" used in a project may recover against a Miller Act surety. 40 U.S.C. § 270b(a). This includes any "subcontractor[ ] who deal[s] directly with the prime contractor," as well as any sub-subcontractor who has supplied labor or materials to a subcontractor. MacEvoy, 322 U.S. at 107-08, 64 S.Ct. at 893-94. Thus, Molnick's is entitled to recover against Aetna, the general contractor's surety, in its capacity as both a subcontractor and a sub-subcontractor, provided the costs it seeks to recover fall within the scope of the Miller Act.

In determining whether Molnick's may recover its increased costs under the Act, we must resolve two issues of first impression in this circuit: (1) can a subcontractor or supplier recover against a Miller Act surety for the subcontractor's increased labor and material costs caused by construction delays,5 and if so, (2) is such recovery limited to situations in which the general contractor caused the delays?

1. Expenses Attributable to Delay

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chapman v. Ei Constructors, Inc., No. Cv 0040938 (Feb. 21, 1995)
1995 Conn. Super. Ct. 1702 (Connecticut Superior Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
981 F.2d 414, 38 Cont. Cas. Fed. 76,358, 92 Daily Journal DAR 9116, 1992 U.S. App. LEXIS 14719, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mai-steel-service-inc-a-kansas-corporation-v-blake-construction-company-ca9-1992.