John A. Artukovich Sons, Inc. v. American Fidelity Fire Insurance

72 Cal. App. 3d 940, 140 Cal. Rptr. 434, 1977 Cal. App. LEXIS 1782
CourtCalifornia Court of Appeal
DecidedAugust 26, 1977
DocketCiv. 49592
StatusPublished
Cited by5 cases

This text of 72 Cal. App. 3d 940 (John A. Artukovich Sons, Inc. v. American Fidelity Fire Insurance) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John A. Artukovich Sons, Inc. v. American Fidelity Fire Insurance, 72 Cal. App. 3d 940, 140 Cal. Rptr. 434, 1977 Cal. App. LEXIS 1782 (Cal. Ct. App. 1977).

Opinion

Opinion

POTTER, J.

Defendant American Fidelity Fire Insurance Company appeals from a judgment in favor of plaintiff John A. Artukovich Sons, Inc. The judgment awarded plaintiff principal in the sum of $35,517.71, interest in the amount of $3,039.81, plus costs of suit (including attorneys’ fees) in the sum of $6,769.05 as the amount due pursuant to the terms of a public works payment bond covering Stuckey Engineers, the contractor on a construction project for the City of Oceanside. The project was the installation of a sewer system known as “North Valley Sewer Improvement District-Schedule 1.”

At the trial, plaintiff submitted evidence concerning nine separate items comprising charges for equipment rental, repairs and modifications to equipment and hauling charges. Defendant did not dispute six of these nine totaling $15,117.71, but took issue with three items, the amount of which defendant claimed was in excess of that covered by the bond.

*943 The three items in dispute were plaintiff’s claims for (1) $11,250 comprising three months’ (July 22, 1974, to Oct. 21, 1974) minimum rental at $3,750 per month for a Buckeye trencher; (2) $4,675 comprising rental for six months and nine days (Apr. 9, 1974, to Oct. 15, 1974) at a monthly rate of $750 per month for a trench shield; and (3) $1,800 comprising one month’s (July 25, 1974 through Aug. 24, 1974) minimum rental for a Lima truck crane. Defendant contested these three items on the basis that although the equipment had been delivered to the job and was employed in the work for a portion of the period covered by the rental claims, work on the project ceased July 29, 1974, and thereafter the equipment sat idle until plaintiff recovered it. It was defendant’s position that rental charges for the equipment were not covered by the bond except when it was actually being used on the project and that the cessation of work on July 29, 1974, cut off its liability for further rental charges.

Inasmuch as no findings of fact were requested or made, it is not possible to state definitely what the nature of the cessation of work on the project was. It is undisputed that the contractor stopped work on the project on July 29, 1974. Defendant claims that a “dispute arose between Stuckey and the City of Oceanside over the availability of a certain portion of the right-of-way for Stuckey’s installation of underground pipe.” However, no citation to the record is given which supports such assertion. Plaintiff’s president testified that he was informed “around the end of July” that Stuckey Engineers were “having difficulties with the City of Oceanside with respect to estimates and right of way and other problems,” and were on that basis “going to shut the job down and put the matter in the hands of their attorneys and tiy to resolve them through negotiation.” However, Stuckey Engineers did not at that time say anything about picking up the equipment and “for the next two, three, four weeks” reported “that the negotiations were continuing, and that possibly they might be able to resolve their differences and start up construction again.” Other testimony with respect to the status of the project after July 29, 1974, was the uncontradicted testimony of the city engineer as follows:

“Q. By Mr. Rebaroff [counsel for plaintiff]: After the contractor left the project on July 29th, a series of negotiations commenced between the contractor and the City, did they not, sir? A. That is correct. Q. That was in an attempt to get the contractor to return to the project? A. Physically, *944 yes. Q. And as a matter of fact, the City did not notify the contractor that its work had been terminated, its contract had been terminated until September 16; isn’t that right, sir? A. Yes, sir, that is correct.”

Plaintiffs president admitted that he was aware “sometime in mid-September that, you know, the jig was up for Stuckey, and that they were done with the job, and they were in default.” The truck crane was returned on or about September 4, on the basis that the initial one-month minimum rental period had expired, that plaintiff had immediate need for the equipment and would replace it if the work resumed. The trencher was not returned until approximately the expiration of the three-month minimum rental period when Stuckey Engineers agreed that they would have no further use for it.

Additional evidence in behalf of plaintiff was to the effect (1) that the cost to plaintiff of modifications to the trencher to meet Stuckey’s requirements was $7,051.25 which exceeded by $2,051.25 the $5,000 maximum charge for which it agreed to make such modifications; (2) that the trencher was not currently being manufactured as a production item and could only be obtained on special order with a delay of a year to a year and a half; and (3) that without a commitment for a minimum of three months’ rental, plaintiff “would not even have rented it. We wouldn’t have bothered to rent it or prepare the machine for a month or whatever. It is not worth the trouble.”

The reasonableness of this arrangement was confirmed by Mr. Ralph Campbell, a partner of Stuckey Engineers, who agreed that it was not possible to obtain such a piece of equipment on less than a three-month minimum rental basis.

The court rendered an oral- statement of its intended decision. Plaintiffs claim on account of the minimum rental for the trencher was upheld in full. In upholding this claim, the court noted that the trencher was actually delivered to the job site and used “for a good period of time before the termination of activities by Stuckey on July 29, 1974,” and that there was a specific written agreement between plaintiff and Stuckey for a guaranteed three-months’ minimum rental. The court referred to • Mr. Campbell’s deposition testimony that it was “common practice within the industry and within this business to have a minimum period of time for equipment such as this to be guaranteed for rental.” The *945 court reasoned that if the minimum period were not agreed to by Stuckey Engineers, then plaintiff would not have rented the equipment and it would not have been available for the project, and concluded that a three-month minimum period was “a reasonable minimum period” in view of the cost of modification and the size and scope of the project.

With respect to the one-month minimum rental charge for the truck crane, the court again noted the existence of an express written agreement for a one-month minimum rental and found that such minimum rental period agreed to in good faith was not “an unreasonable period.”

With respect to the charges for the rental of the trench shield, for which plaintiff claimed rental through October 15, 1974, the court limited recovery to the monthly rental period ending September 8, 1974. Inasmuch as the first rental period to expire after the July 29 termination of work was only 11 days thereafter, it was reasonable not to withdraw the equipment in view of the reported negotiations between Stuckey Engineers and the city.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
72 Cal. App. 3d 940, 140 Cal. Rptr. 434, 1977 Cal. App. LEXIS 1782, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-a-artukovich-sons-inc-v-american-fidelity-fire-insurance-calctapp-1977.