Lambert v. Superior Court

228 Cal. App. 3d 383, 279 Cal. Rptr. 32, 91 Daily Journal DAR 2896, 91 Cal. Daily Op. Serv. 1817, 1991 Cal. App. LEXIS 236
CourtCalifornia Court of Appeal
DecidedMarch 11, 1991
DocketA052158
StatusPublished
Cited by22 cases

This text of 228 Cal. App. 3d 383 (Lambert v. Superior Court) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lambert v. Superior Court, 228 Cal. App. 3d 383, 279 Cal. Rptr. 32, 91 Daily Journal DAR 2896, 91 Cal. Daily Op. Serv. 1817, 1991 Cal. App. LEXIS 236 (Cal. Ct. App. 1991).

Opinion

Opinion

CHIN, J.

This petition presents novel procedural and substantive questions about recording and removing mechanics’ liens. Real party in interest *385 William MacEwen, a licensed general contractor (contractor), recorded a lien for $117,328.05 against property owned by petitioners Claude and Micheline Lambert (owners). By contractor’s own admission, most of the lien is based upon “delay/interest damages” which the construction contract regards as “extra work.” Owners filed a motion to remove the lien, but the court denied the motion on procedural grounds. We conclude that the court erred.

In June of 1988, owners hired contractor to make major alterations to their home in San Rafael. The total contract price was $327,705, and the work was to be completed within one year. Two years and several change orders later, owners discharged contractor and hired another contractor to finish the work.

On October 19, 1990, contractor recorded a mechanic’s lien for $117,328.05 against owners’ property. The lien was for “general contracting and related building services; general construction materials and confiscated materials; charges for delay.” Contractor immediately filed a complaint for damages for breach of contract and to foreclose the mechanic’s lien. In December 1990, the court granted contractor’s unopposed request to stay proceedings on the complaint pending termination of the arbitration prescribed by the contract. Arbitration was set to begin in March 1991.

While the stay request was pending, owners filed a motion to remove the mechanic’s lien on the ground that they had paid contractor more than $361,000, well over the contract price. After hearing, the court denied the motion on the following grounds: “[Owners] have not availed themselves of the statutory remedy for disputing the lien. Civil Code § 3143. Nor does Connolly Development, Inc. v. Superior Court (1976) 17 Cal.3d 803, provide the authority for this motion as [owners] claim.” This petition followed.

Article XIV, section 3, of the California Constitution provides that “[m]echanics, persons furnishing materials, artisans, and laborers of every class, shall have a lien upon the property upon which they have bestowed labor or furnished material for the value of such labor done and material furnished; and the Legislature shall provide, by law, for the speedy and efficient enforcement of such liens.”

The Legislature implemented this constitutional provision by enacting Civil Code section 3109 et seq. In Connolly Development, Inc. v. Superior Court (1976) 17 Cal.3d 803 [132 Cal.Rptr. 477, 553 P.2d 637], the California Supreme Court found that the statutory scheme satisfied the requirements for procedural due process because a property owner has a “variety of measures by which he can protect himself against the impact of such a *386 lien . . . .” (Id., at p. 807.) The primary question we address is whether owners’ motion to remove the lien, not mentioned by Connolly, is one of those measures.

Civil Code section 3143, mentioned in the trial, court’s ruling, provides one method for removing a mechanic’s lien. It permits an owner who disputes a lien to release the property from the lien by posting a surety bond equal to one and one-half times the amount of the claim. But owners assert, with some support, that such a release bond may not be available to an individual owner, who will usually be required to post liquid collateral in the amount of the bond. (See Cal. Mechanics’ Liens and Other Remedies (Cont.Ed.Bar 1988) § 5.43, p. 263.)

Civil Code section 3143 is not the exclusive means for removing a mechanic’s lien. Connolly Development, Inc. v. Superior Court, supra, 17 Cal.3d at pages 813-814, found that “the recording of a mechanics’ lien, deprives the landowner of a significant property interest, and thus constitutes a ‘taking’ within the meaning of the federal and state due process clauses.” (Fn. omitted.) Due process would not be provided if a claimant’s unjustified lien or a lien of an unjustified amount could be removed only by pledging collateral in excess of the amount claimed.

Connolly explained that other remedies are available to an owner both before and after the recording of a mechanic’s lien or a stop notice: “Before recording a mechanics’ lien or filing a stop notice, the claimant must serve a preliminary notice upon the owner, the contractor, and the construction lender. [Citations.] Upon receipt of such a notice from one not entitled to claim a lien, the owner or lender may immediately file suit to enjoin the claimant from asserting his lien. [Citation.] By the use of a temporary restraining order if necessary [citation], the plaintiff could secure a hearing before the lien was imposed, [fl] Even after the lien has been recorded, or the stop notice filed, the owner in many instances could seek a mandatory injunction ordering the claimant to release the lien. [Citations.] In any event, the owner need not wait until the claimant sues to enforce the lien; the imposition of that lien, and the owner’s denial of its validity, comprise a controversy sufficient to permit an immediate suit for declaratory relief. [Citation.] Such a declaratory relief action can claim priority on the calendar of the trial court. [Citation.] Thus by filing an action for injunctive or declaratory relief, the owner or lender can obtain a hearing either before imposition of the lien or within a reasonable period thereafter.” (Connolly Development, Inc. v. Superior Court, supra, 17 Cal.3d at pp. 822-823, fns. omitted.)

Contractor says that Connolly relegates owners to an action for injunctive or declaratory relief, and that a motion to remove mechanic’s lien *387 was improper. Contractor contends that “the Law and Motion procedure, subject to local rule limitations in time and page length of submissions, does not provide the constitutional safeguards that should also be accorded to the contractor. . . . Construction projects bring along with them complicated issues of fact which cannot always be raised in the Law and Motion format. . . . [fl] On the other hand, the injunctive procedure provides not only for the filing of detailed accounting and other documents, but also for the taking of oral evidence.”

Contractor reads too much from Connolly. The court upheld the constitutionality of a “ ‘taking’ ” of property by mechanic’s lien. In doing so it did not define or limit the procedures for removing liens. The court mentioned restraining orders, injunctions, and declaratory relief actions only to illustrate ways an owner could seek relief before a claimant sued to enforce a lien. It did not suggest that an owner could not challenge a lien by a motion to remove in a claimant’s action to enforce the lien.

If a claimant has not yet imposed a lien or, having imposed it, has not yet sued to foreclose it, an owner’s speediest remedy is through proceedings for injunctive or declaratory relief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Carpets v. Panku CA4/3
California Court of Appeal, 2025
Pacific Carpets v. 2525 Main Apartment CA4/3
California Court of Appeal, 2025
Tucker v. 1400 Fig CA2/2
California Court of Appeal, 2023
LSG Las Tunas v. A & R Corp. CA2/2
California Court of Appeal, 2021
Manela v. Stone
California Court of Appeal, 2021
RGC Gaslamp v. Ehmcke Sheet Metal Co.
California Court of Appeal, 2020
Carmel Development Co., Inc. v. Anderson
California Court of Appeal, 2020
McMILLAN v. UNIQUE PLACES, LLC
2015 NCBC 46 (North Carolina Business Court, 2015)
Pittsburg Unified School District v. S.J. Amoroso Construction Co.
232 Cal. App. 4th 808 (California Court of Appeal, 2014)
F.W. Spencer & Son v. Harris Construction CA5
California Court of Appeal, 2014
Cal Sierra Construction, Inc. v. Comerica Bank
206 Cal. App. 4th 841 (California Court of Appeal, 2012)
Forsgren Associates, Inc. v. Pacific Golf Community Development LLC
182 Cal. App. 4th 135 (California Court of Appeal, 2010)
T.O. IX, LLC v. Superior Court
165 Cal. App. 4th 140 (California Court of Appeal, 2008)
Newman v. Valleywood Associates, Inc.
874 A.2d 1286 (Supreme Court of Rhode Island, 2005)
Howard S. Wright Construction Co. v. Superior Court
130 Cal. Rptr. 2d 641 (California Court of Appeal, 2003)
Basic Modular Facilities, Inc. v. Ehsanipour
83 Cal. Rptr. 2d 462 (California Court of Appeal, 1999)
Mai Steel Service Inc. v. Blake Construction Co.
981 F.2d 414 (Ninth Circuit, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
228 Cal. App. 3d 383, 279 Cal. Rptr. 32, 91 Daily Journal DAR 2896, 91 Cal. Daily Op. Serv. 1817, 1991 Cal. App. LEXIS 236, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lambert-v-superior-court-calctapp-1991.