Tucker v. 1400 Fig CA2/2
Opinion
Filed 11/8/23 Tucker v. 1400 Fig CA2/2 NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
SECOND APPELLATE DISTRICT
DIVISION TWO
DEAN E. TUCKER, B324667
Plaintiff and Appellant, (Los Angeles County Super. Ct. No. 19STCV24308)
v.
1400 FIG, LLC, et al.,
Defendants and Respondents.
APPEAL from a judgment of the Superior Court of Los Angeles County, Richard L. Fruin, Jr., Judge. Affirmed.
Dean E. Tucker, in pro. per., for Plaintiff and Appellant.
The Rodarti Group and Josef M. Rodarti for Defendants and Respondents.
Dean Tucker (appellant) appeals from an order releasing the property of 1400 Fig, LLC (the LLC) and Soleiman Gabbay (collectively respondents) from appellant’s mechanic’s lien and also dismissing respondents from the complaint. We conclude appellant’s mechanic’s lien was unenforceable due to his failure to comply with preliminary notice and licensing requirements. Thus we affirm the order releasing the mechanic’s lien and dismissing respondents from the action.
BACKGROUND
The LLC owns the real property at 1400 South Figueroa Street, Los Angeles, California (property). Gabbay holds a majority of the LLC’s membership interests.
In November 2015, the LLC entered into a construction contract with Fassberg Contracting Corporation (Fassberg) to construct apartments on the property. Fassberg subcontracted the electrical work to the appellant on January 7, 2016.
When he started the work appellant had a valid contractor’s license. However, between October 20, 2016, and December 1, 2016, appellant’s license was suspended due to the lapse of his contractor’s bond. Once a new bond was secured, appellant’s contractor’s license was reinstated.
After completing his work, appellant—unpaid for his services—sent a preliminary notice to the LLC on November 11, 2018, asserting a claim for $860,000. Later appellant recorded two mechanic’s liens. The first, recorded on June 3, 2019, expired due to appellant’s failure to timely file a foreclosure claim. The second, recorded on June 24, 2021, claimed appellant was owed $975,627.48.
Fassberg filed a complaint on July 11, 2019, seeking damages from appellant. Two years later appellant filed a separate action against respondents to foreclose on his second mechanic’s lien. Various other causes of action for damages against Fassberg, its agent, the individual owners of Fassberg, and the bank funding the construction project were asserted. The cases were consolidated with Fassberg’s case designated as the lead.
Respondents filed a motion to release their property from appellant’s mechanic’s liens. Following the August 30, 2022 hearing, the trial court took the matter under submission and then issued its order on September 6, 2022. The trial court determined appellant’s mechanic’s lien to be invalid because he lacked a contractor’s license during part of the project and had not complied with the notice requirements for recording a mechanic’s lien. As a result, respondents’ property was released from appellant’s liens and respondents were dismissed from appellant’s complaint. Appellant’s subsequent motion for motion for reconsideration was denied.
Appellant filed a timely notice of appeal. The order was appealable because it dismissed respondents from appellant’s complaint.1
1 The order of dismissal was an appealable order because it left no issue to be determined as to respondents. (Heshejin v. Rostami (2020) 54 Cal.App.5th 984, 991 [“‘it has long been the settled rule that in a case involving multiple parties, a judgment is final and appealable when it leaves no issues to be determined as to one party’”].)
CONTENTIONS ON APPEAL
Appellant challenges the order of dismissal on three grounds. First, he argues the court lacked sufficient evidence to conclude appellant failed to meet the preliminary notice requirements before recording his mechanic’s lien. Second, appellant contends the court abused its discretion by determining he did not substantially comply with the contractor licensing requirements. Finally, appellant asserts it was an abuse of discretion to dismiss respondents after their property was released from his mechanic’s lien.
DISCUSSION
I. Applicable law and standard of review By the California Constitution and by statute, “contractors, laborers, and suppliers” have the right to record a “mechanic’s lien” against any property “upon which they have bestowed labor or furnished material for the value of such labor done and material furnished.” (Cal. Const., art. XIV, § 3; see Civ. Code, §§ 8000-9566; RGC Gaslamp, LLC v. Ehmcke Sheet Metal Co., Inc. (2020) 56 Cal.App.5th 413, 422 (RGC Gaslamp).)
A subcontractor seeking to record a mechanic’s lien must give preliminary notice to the property’s owner, the direct contractor, and the construction lender prior to recording the lien. (Civ. Code, §§ 8200, subds. (a)(1) & (c), 8400, subd. (a), 8410.) Once the lien is recorded, the lien encumbers title to the property and has priority over subsequently recorded instruments. (RGC Gaslamp, supra, 56 Cal.App.5th at p. 422.)
There are “a variety of measures [or mechanisms]” by which an owner could obtain provisional relief from a mechanic’s lien or “speedy” judicial review of such a lien, either before or
immediately after its recording. (Connolly Development, Inc. v. Superior Court (1976) 17 Cal.3d 803, 807.) These include the owner’s statutory right to seek release of the mechanic’s lien upon posting a bond in the amount of 125 percent of the lien and the owner’s right to file an action for declaratory or injunctive relief challenging the mechanic’s lien. (Id. at pp. 822-823.) Another postlien mechanism identified later was for the owner to file a motion in the contractor’s pending action to foreclose on a mechanic’s lien. (Lambert v. Superior Court (1991) 228 Cal.App.3d 383, 386-387 (Lambert).)
When a property owner files a motion to eliminate or reduce a mechanic’s lien, the contractor bears the burden of establishing the “probable validity” of the propriety and amount of its lien by a preponderance of the evidence. (Lambert, supra, 228 Cal.App.3d at p. 387.) This standard requires the contractor to prove a “‘prima facie case’” by establishing the “‘probable outcome of the litigation’” in its favor. (Howard S. Wright Construction Co. v. Superior Court (2003) 106 Cal.App.4th 314, 319-320.)
We review a trial court’s determination of the probable validity of a mechanic’s lien for an abuse of discretion, reviewing subsidiary factual findings for substantial evidence and subsidiary legal rulings—such as the meaning of statutes—de novo. (Howard S. Wright Construction Co. v. Superior Court, supra, 106 Cal.App.4th at p. 320.) II. Substantial evidence supports the court’s finding appellant did not comply with the preliminary notice requirement “A claimant may enforce a lien only if the claimant has given preliminary notice to the extent required by Chapter 2
(commencing with Section 8200) and made proof of notice.” (Civ. Code, § 8410.) When served by mail, the preliminary notice must be sent by registered or certified mail, express mail, or overnight delivery by an express service carrier. (Civ. Code, § 8110.) If notice is given through the United States Postal Service, the proof of service must include documentation or a return receipt from the United States Postal Service. (Civ. Code, § 8118, subd. (b).)
Free access — add to your briefcase to read the full text and ask questions with AI
Tucker v. 1400 Fig CA2/2 (Tucker v. 1400 Fig CA2/2) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.