1 2 3 4 5 UNITED STATES DISTRICT COURT 6 NORTHERN DISTRICT OF CALIFORNIA 7 8 CHINESE HOSPITAL ASSOCIATION, Case No. 18-cv-05403-JSC
9 Plaintiff, ORDER RE: DEFENDANT’S MOTION 10 v. FOR PARTIAL SUMMARY JUDGMENT ON CONSEQUENTIAL 11 JACOBS ENGINEERING GROUP, INC., DAMAGES 12 Defendant. Re: Dkt. No. 48
13 14 Plaintiff Chinese Hospital Association alleges that Defendant Jacobs Engineering Group, 15 Inc. breached its written agreement with Plaintiff for architectural services. Defendant’s motion 16 for partial summary judgment on Plaintiff’s right to recover consequential damages is now 17 pending before the Court.1 (Dkt. No. 48.2) Having considered the parties’ briefs and having had 18 the benefit of oral argument on November 14, 2019, the Court GRANTS IN PART and DENIES 19 IN PART Defendant’s motion for summary judgment. The express language of the parties’ 20 contract bars Plaintiff’s claim for lost profits, increased operational costs, and construction delay 21 damages. 22 FACTUAL BACKGROUND 23 In Spring 2007, Chinese Hospital, a nonprofit healthcare services corporation, contracted 24 with Carter & Burgess, Inc., an architecture firm, to design a new hospital. (Dkt. No. 29 at 23, 25 McFarlin Decl. at ¶ 3; Dkt. No. 29 at 57.) At some point thereafter, Carter & Burgess was 26 1 All parties have consented to the jurisdiction of a magistrate judge pursuant to 28 U.S.C. § 27 636(c). (Dkt. Nos. 10, 16.) 1 acquired by Jacobs Engineering Group, Inc. (“Jacobs”) and under a novation agreement between 2 Chinese Hospital, Carter & Burgess, and Jacobs, Jacobs took over Carter & Burgess’ rights and 3 responsibilities under the Design Contract. (Dkt. No. 29 at 23, McFarlin Decl. at ¶ 4.) In the Fall 4 of 2013, Plaintiff “became aware of serious defects in the construction documents” and terminated 5 the parties’ contract as of November 7, 2013. (Complaint at ¶ 11.) Plaintiff thereafter hired 6 another architectural firm to complete the project. (Id. at ¶ 13.) 7 PROCEDURAL BACKGROUND 8 Five years later, Plaintiff filed a certificate of merit in the Superior Court of the County of 9 San Francisco pursuant to California Code of Civil Procedure § 411.35(b)(1). (Dkt. No. 1-5.) The 10 next day, it filed this action in that same court pleading a single cause of action for breach of 11 contract against Defendant. (Dkt. No. 1-3.) Defendant thereafter removed the action based on 12 diversity jurisdiction and four days later filed a motion to dismiss for failure to state a claim. (Id.) 13 The Court granted the motion to dismiss to the extent Plaintiff’s breach of contract claim rests on 14 Defendant’s ordinary obligation to perform work consistent with the standard of care imposed on 15 an architect, but denied the motion to the extent Plaintiff’s claim is based on a different breach of 16 the contract. (Dkt. No. 20.) 17 Defendant thereafter moved for summary judgment on the affirmative defense of waiver, 18 but the Court denied the motion on the grounds that Defendant had not met its burden of proving 19 as a matter of law that Plaintiff waived its right to recover damages by terminating the parties’ 20 contract “for convenience.” (Dkt. No. 41.) Defendant requested the opportunity to separately 21 move for summary judgment on its claim that under the contract Plaintiff is limited to general 22 damages and cannot recover consequential damages. Plaintiff has since filed a statement of 23 damages sought and the parties have submitted briefing on the consequential damages issue. (Dkt. 24 Nos. 45, 48, 53, 54.) 25 DISCUSSION 26 Defendant moves for summary judgment on the issue of consequential damages. In 27 particular, Defendant contends that certain of the damages sought by Plaintiff are barred by the 1 A. Damages for Breach of Contract 2 “Contract damages seek to approximate the agreed-upon performance.” Applied Equip. 3 Corp. v. Litton Saudi Arabia Ltd., 7 Cal. 4th 503, 515 (1994); see also Cal. Civ. Code, § 3300 4 || (flor the breach of an obligation arising from contract, the measure of damages ... is the amount 5 which will compensate the party aggrieved for all the detriment proximately caused thereby, or 6 || which, in the ordinary course of things, would be likely to result therefrom.”). The injured party’s 7 || damages cannot, however, exceed that which it would have received if the contract had been fully 8 || performed on both sides. Cal. Civ. Code, § 3358. 9 “Contractual damages are of two types—general damages (sometimes called direct 10 || damages) and special damages (sometimes called consequential damages).” Lewis Jorge Constr. 11 Memt., Inc. v. Pomona Unified Sch. Dist., 34 Cal. 4th 960, 968 (2004). General damages are 12 || “those that flow directly and necessarily from a breach of contract, or that are a natural result of a 13 || breach.” Jd. Because general damages are “a natural and necessary consequence” of a breach, 14 || they “are often said to be within the contemplation of the parties, meaning that because their 15 occurrence is sufficiently predictable the parties at the time of contracting are ‘deemed’ to have 16 || contemplated them.” /d. In contrast, consequential damages “are those losses that do not arise 3 17 directly and inevitably from any similar breach of any similar agreement. Instead, they are
Z 18 secondary or derivative losses arising from circumstances that are particular to the contract or to 19 || the parties.” Id. 20 B. Plaintiff’s Damages 21 1. The Design Contract 22 As relevant to the current motion, the Design Contract includes the following damages 23 provision: 24 § 1.3.6 CLAIMS FOR CONSEQUENTIAL DAMAGES 25 Notwithstanding any other provision of this Agreement to the contrary, the parties hereto mutually agree that neither party shall be liable to the other for any damages in the nature of lost profits, lost opportunity or 26 ec = arising directly or indirectly from any breach of duty created by 27 28 || (Dkt. No. 48-2 at 18.)
1 2. Plaintiff’s Recoverable Damages 2 “Generally, provisions limiting liability in construction contracts are enforceable under 3 California law so long as the parties negotiated and expressly agreed to the limitations.” Civic 4 Ctr. Drive Apartments Ltd. P’ship v. Sw. Bell Video Servs., 295 F. Supp. 2d 1091, 1105–06 (N.D. 5 Cal. 2003) (citing Cal. Civ. Code § 2782.5). Defendant insists that in light of the above 6 contractual language, three of the categories of damages Plaintiff seeks are not recoverable: (1) 7 increased operational costs/lost revenue, (2) delayed project completion costs, and (3) construction 8 costs except rework costs. The Court addresses each in turn. 9 a) Increased Operational Costs/Lost Revenue 10 Defendant contends the following are non-recoverable consequential/lost profit damages: 11 “having to pay additional personnel to operate pharmacy facilities and to wash and sterilize carts,” 12 “paying more for garbage collection” because there is no “trash compactor at the loading dock,” 13 and “not being able to operate a skilled nursing facility.” (Dkt. No. 48 at 18:6-9.) Defendant’s 14 argument is twofold: (1) that operational costs and lost revenues are consequential damages and 15 therefore not recoverable under the waiver; and (2) even if lost profits are not consequential 16 damages, the express language of the parties’ agreement bars recovery for “lost profits” and “lost 17 opportunity.” 18 1.
Free access — add to your briefcase to read the full text and ask questions with AI
1 2 3 4 5 UNITED STATES DISTRICT COURT 6 NORTHERN DISTRICT OF CALIFORNIA 7 8 CHINESE HOSPITAL ASSOCIATION, Case No. 18-cv-05403-JSC
9 Plaintiff, ORDER RE: DEFENDANT’S MOTION 10 v. FOR PARTIAL SUMMARY JUDGMENT ON CONSEQUENTIAL 11 JACOBS ENGINEERING GROUP, INC., DAMAGES 12 Defendant. Re: Dkt. No. 48
13 14 Plaintiff Chinese Hospital Association alleges that Defendant Jacobs Engineering Group, 15 Inc. breached its written agreement with Plaintiff for architectural services. Defendant’s motion 16 for partial summary judgment on Plaintiff’s right to recover consequential damages is now 17 pending before the Court.1 (Dkt. No. 48.2) Having considered the parties’ briefs and having had 18 the benefit of oral argument on November 14, 2019, the Court GRANTS IN PART and DENIES 19 IN PART Defendant’s motion for summary judgment. The express language of the parties’ 20 contract bars Plaintiff’s claim for lost profits, increased operational costs, and construction delay 21 damages. 22 FACTUAL BACKGROUND 23 In Spring 2007, Chinese Hospital, a nonprofit healthcare services corporation, contracted 24 with Carter & Burgess, Inc., an architecture firm, to design a new hospital. (Dkt. No. 29 at 23, 25 McFarlin Decl. at ¶ 3; Dkt. No. 29 at 57.) At some point thereafter, Carter & Burgess was 26 1 All parties have consented to the jurisdiction of a magistrate judge pursuant to 28 U.S.C. § 27 636(c). (Dkt. Nos. 10, 16.) 1 acquired by Jacobs Engineering Group, Inc. (“Jacobs”) and under a novation agreement between 2 Chinese Hospital, Carter & Burgess, and Jacobs, Jacobs took over Carter & Burgess’ rights and 3 responsibilities under the Design Contract. (Dkt. No. 29 at 23, McFarlin Decl. at ¶ 4.) In the Fall 4 of 2013, Plaintiff “became aware of serious defects in the construction documents” and terminated 5 the parties’ contract as of November 7, 2013. (Complaint at ¶ 11.) Plaintiff thereafter hired 6 another architectural firm to complete the project. (Id. at ¶ 13.) 7 PROCEDURAL BACKGROUND 8 Five years later, Plaintiff filed a certificate of merit in the Superior Court of the County of 9 San Francisco pursuant to California Code of Civil Procedure § 411.35(b)(1). (Dkt. No. 1-5.) The 10 next day, it filed this action in that same court pleading a single cause of action for breach of 11 contract against Defendant. (Dkt. No. 1-3.) Defendant thereafter removed the action based on 12 diversity jurisdiction and four days later filed a motion to dismiss for failure to state a claim. (Id.) 13 The Court granted the motion to dismiss to the extent Plaintiff’s breach of contract claim rests on 14 Defendant’s ordinary obligation to perform work consistent with the standard of care imposed on 15 an architect, but denied the motion to the extent Plaintiff’s claim is based on a different breach of 16 the contract. (Dkt. No. 20.) 17 Defendant thereafter moved for summary judgment on the affirmative defense of waiver, 18 but the Court denied the motion on the grounds that Defendant had not met its burden of proving 19 as a matter of law that Plaintiff waived its right to recover damages by terminating the parties’ 20 contract “for convenience.” (Dkt. No. 41.) Defendant requested the opportunity to separately 21 move for summary judgment on its claim that under the contract Plaintiff is limited to general 22 damages and cannot recover consequential damages. Plaintiff has since filed a statement of 23 damages sought and the parties have submitted briefing on the consequential damages issue. (Dkt. 24 Nos. 45, 48, 53, 54.) 25 DISCUSSION 26 Defendant moves for summary judgment on the issue of consequential damages. In 27 particular, Defendant contends that certain of the damages sought by Plaintiff are barred by the 1 A. Damages for Breach of Contract 2 “Contract damages seek to approximate the agreed-upon performance.” Applied Equip. 3 Corp. v. Litton Saudi Arabia Ltd., 7 Cal. 4th 503, 515 (1994); see also Cal. Civ. Code, § 3300 4 || (flor the breach of an obligation arising from contract, the measure of damages ... is the amount 5 which will compensate the party aggrieved for all the detriment proximately caused thereby, or 6 || which, in the ordinary course of things, would be likely to result therefrom.”). The injured party’s 7 || damages cannot, however, exceed that which it would have received if the contract had been fully 8 || performed on both sides. Cal. Civ. Code, § 3358. 9 “Contractual damages are of two types—general damages (sometimes called direct 10 || damages) and special damages (sometimes called consequential damages).” Lewis Jorge Constr. 11 Memt., Inc. v. Pomona Unified Sch. Dist., 34 Cal. 4th 960, 968 (2004). General damages are 12 || “those that flow directly and necessarily from a breach of contract, or that are a natural result of a 13 || breach.” Jd. Because general damages are “a natural and necessary consequence” of a breach, 14 || they “are often said to be within the contemplation of the parties, meaning that because their 15 occurrence is sufficiently predictable the parties at the time of contracting are ‘deemed’ to have 16 || contemplated them.” /d. In contrast, consequential damages “are those losses that do not arise 3 17 directly and inevitably from any similar breach of any similar agreement. Instead, they are
Z 18 secondary or derivative losses arising from circumstances that are particular to the contract or to 19 || the parties.” Id. 20 B. Plaintiff’s Damages 21 1. The Design Contract 22 As relevant to the current motion, the Design Contract includes the following damages 23 provision: 24 § 1.3.6 CLAIMS FOR CONSEQUENTIAL DAMAGES 25 Notwithstanding any other provision of this Agreement to the contrary, the parties hereto mutually agree that neither party shall be liable to the other for any damages in the nature of lost profits, lost opportunity or 26 ec = arising directly or indirectly from any breach of duty created by 27 28 || (Dkt. No. 48-2 at 18.)
1 2. Plaintiff’s Recoverable Damages 2 “Generally, provisions limiting liability in construction contracts are enforceable under 3 California law so long as the parties negotiated and expressly agreed to the limitations.” Civic 4 Ctr. Drive Apartments Ltd. P’ship v. Sw. Bell Video Servs., 295 F. Supp. 2d 1091, 1105–06 (N.D. 5 Cal. 2003) (citing Cal. Civ. Code § 2782.5). Defendant insists that in light of the above 6 contractual language, three of the categories of damages Plaintiff seeks are not recoverable: (1) 7 increased operational costs/lost revenue, (2) delayed project completion costs, and (3) construction 8 costs except rework costs. The Court addresses each in turn. 9 a) Increased Operational Costs/Lost Revenue 10 Defendant contends the following are non-recoverable consequential/lost profit damages: 11 “having to pay additional personnel to operate pharmacy facilities and to wash and sterilize carts,” 12 “paying more for garbage collection” because there is no “trash compactor at the loading dock,” 13 and “not being able to operate a skilled nursing facility.” (Dkt. No. 48 at 18:6-9.) Defendant’s 14 argument is twofold: (1) that operational costs and lost revenues are consequential damages and 15 therefore not recoverable under the waiver; and (2) even if lost profits are not consequential 16 damages, the express language of the parties’ agreement bars recovery for “lost profits” and “lost 17 opportunity.” 18 1. Lost profits are not recoverable 19 Plaintiff’s request for lost profit damages associated with Plaintiff not being able to operate 20 a skilled nursing facility is barred by the Design Contract’s unambiguous language: “neither party 21 shall be liable to the other for damages in the nature of lost profits . . . .” Plaintiff’s argument that 22 the “Consequential Damages” header to this clause limits the waiver to “lost profit” consequential 23 damages but does not waive “lost profit” direct damages would render the reference to “lost 24 profit” and “lost opportunity” meaningless as all the contract would have needed to say is no 25 consequential damages. But it did not. Instead, it specifically identified damages “in the nature of 26 lost profits” as not recoverable. See Zalkind v. Ceradyne, Inc., 194 Cal. App. 4th 1010, 1027 27 (2011) (“the meaning of a contract must be derived from reading the whole of the contract, with 1 rendering some meaningless.”); see also AIU Ins. Co. v. Superior Court, 51 Cal. 3d 807, 827-28 2 (1990) (declining to interpret a contract provision in a manner that causes another limitation “to be 3 rendered meaningless”). Plaintiff cites no case that suggests the Court can ignore this 4 unambiguous language based on nothing more than the title of the paragraph. Further, even if the 5 plain language of the Design Contract was ignored, Plaintiff’s reliance on Lewis Jorge to support 6 its assertion that its claimed lost profits are direct damages is unpersuasive. The profits sought 7 here are not “profits unearned on the very contract that was breached.” Lewis Jorge, 34 Cal. 4th at 8 971. Accordingly, the Court concludes that Defendant has met its burden of proving that 9 Plaintiff’s claim for lost profits is barred as a matter of law under Section 1.3.6 of the Design 10 Contract. 11 2. Increased operational costs are not recoverable 12 Plaintiff also insists that the additional pharmacy-related costs are recoverable because 13 under Section 1.2.3.6 of the Design Contract Defendant was required to design the Hospital’s 14 pharmacy in a configuration that could be licensed. It argues that because Defendant did not do 15 so, it has to operate two pharmacies at increased cost. Plaintiff similarly insists that under Section 16 1.2.3.6 and Exhibit E of the Design Contract, Defendant was required to review laws, codes, and 17 regulations and that “Jacobs failed to provide a layout for the Hospital’s central sterile services 18 department in a way that was code-compliant.” (Dkt. No. 53 at 15:16-19.) According to Plaintiff, 19 because Defendant did not do so, it has incurred additional operational costs as Hospital personnel 20 are now forced to wash carts by hand. Finally, Plaintiff contends that under Section 1.1.2.1. of the 21 Design Contract Defendant was required to develop quality and efficient architectural and 22 engineering systems for implementation and Defendant’s layout of the loading dock was not 23 efficient such that the loading dock cannot maintain a trash compactor. 24 These damages are not recoverable under the Design Contract for two reasons. First, 25 drawing all reasonable inferences in Plaintiff’s favor, they are unrecoverable “consequential 26 damages of any description” as a matter of law. Special, or consequential damages, are those that 27 “are secondary or derivative losses arising from circumstances that are particular to the contract or 1 “General damages for breach of a contract are based on the value of the performance itself, not the 2 value of some consequence that performance would produce.” Id. at 971 (internal citation and 3 quotation marks omitted). The damages sought here are consequential as they are based on the 4 value of some consequence that performance would produce; namely, a licensed central sterile 5 services department that would not require washing carts by hand, a licensed in-patient pharmacy, 6 and efficiencies from a trash compactor that fits in the loading dock. 7 Atlantic City Associates, LLC v. Carter & Burgess Consultants, Inc., 453 Fed. Appx. 174 8 (3d Cir. 2011), is instructive. There a developer hired the defendant consultants to oversee 9 construction of a development in Atlantic City, New Jersey. Id. at 176. The developer sued the 10 consultants for breach of contract and professional negligence and a jury awarded damages. Id. at 11 177. The contract at issue excluded any recovery for consequential damages. Id. On appeal, the 12 Third Circuit held that damages for lost rental income, additional payments to contractors due to 13 delay, and additional administrative costs were non-recoverable consequential damages, while the 14 additional construction costs to fix the consultants’ errors were recoverable direct costs. Id. at 15 178-79. Citing to the Second Restatement of Contracts, the court explained that “the difference 16 between direct and consequential damages depends on whether the damages represent (1) a loss in 17 value of the other party’s performance, in which case the damages are direct, or (2) or collateral 18 losses following the breach, in which case the damages are consequential.” Id. at 180. The same 19 reasoning applies here. Direct damages are the value of Jacobs’ performance, namely, the cost of 20 getting a code-compliant hospital design, whereas consequential damages are the damages sought 21 above. 22 Plaintiff’s argument that Defendant “as a designer experienced in the medical facility 23 industry, would have reason to know that the type of damages would flow from inefficient and un- 24 licensable designs” (Dkt. No. 53 at 17), confuses the definition of special/consequential damages 25 with direct damages. Special/consequential damages are those that the defendant “knew or 26 reasonably should have known of the special circumstances leading to the harm.” Judicial Council 27 of California Civil Jury Instructions, CACI No. 351 (2019 Ed.); see also Lewis Jorge, 34 Cal. 4th 1 they arise were actually communicated to or known by the breaching party (a subjective test) or 2 were matters of which the breaching party should have been aware at the time of contracting (an 3 objective test)”). The damages sought may well qualify as special/consequential damages, but 4 Plaintiff waived its right to recover such damages. 5 b. Delayed Project Completion Damages 6 Plaintiff also seeks damages due to construction being completed later than anticipated 7 because of Defendant’s alleged breach. Defendant contends that the consequential damages waiver 8 bars recovery of these damages as well. In general, delay damages are viewed as consequential 9 damages under California law. See Glob. Modular, Inc. v. Kadena Pac., Inc., 15 Cal. App. 5th 10 127, 145 (Cal. Ct. App. 2017), review denied (Dec. 13, 2017) (“delay constitutes a consequential 11 loss”); Lambert v. Superior Court, 228 Cal.App.3d 383, 389 (1991) (stating that the mechanic’s 12 lien statute “does not permit a lien for delay damages,” because “[t]he function of the mechanic’s 13 lien is to secure reimbursement for services and materials actually contributed to a construction 14 site, not to facilitate recovery of consequential damages”); see also Mycogen Corp. v. Monsanto 15 Co., 28 Cal.4th 888, 906 (2002) (describing “delay damages” as “damages for delay in the 16 commencement of the defendant’s performance”). 17 In Pacific Coast Engineering Co. v. St. Paul & Marine Ins. Co., 9 Cal. App. 3d 270 18 (1970), for example, the plaintiff contracted to construct a steel barge. An explosion damaged the 19 barge when it was almost complete. The plaintiff’s insurers covered the physical damage from the 20 explosion, including the damage to the barge. The policy, however, did not cover “consequential 21 loss or remote loss.” The insurers accordingly refused to pay for the damage the plaintiff incurred 22 as a result in the delay in the delivery of the barge to its customer; namely, additional loan interest 23 paid by plaintiff as a result of the customer not making final payment until the barge was finally 24 delivered, and amounts paid by plaintiff to its barge customer as damages for delay in delivering 25 the barge. Id. at 273. The trial court held that such damages were noncovered consequential 26 damages and the appellate court affirmed. Id. at 273-74. Plaintiff seeks to recover the additional 27 monies it paid as a result of the delay caused by the faulty architectural plans just as the barge 1 the barge. Just as the latter damages were consequential, so too are the delay damages sought by 2 Plaintiff. 3 Plaintiff’s opposition does not address this legal argument. At oral argument, Plaintiff 4 insisted that the cases Defendant relied upon all address whether a party’s own delay damages 5 were recoverable and not whether the delay damages owed to a third party were recoverable. 6 However, Plaintiff was unable to cite to a case which draws this distinction; this omission is likely 7 because it is illogical to find that delay damages to a party are consequential damages, but delay 8 damages owed to a third-party are direct damages. In any event, in Pacific Coast Engineering, the 9 delay damages in form of increased interest paid to a lender were paid to a third party and the 10 courts nonetheless held that such damages were consequential. 11 “[C]onsequential damages are available for those delays that may fairly and reasonably be 12 supposed to have been in the contemplation of the parties to the contract at the time it was made, 13 as the probable result of the breach.” Atlantic City, 453 F. App’x at 179 (noting that New Jersey 14 has adopted the Hadley v. Baxendale rule) (internal quotation marks and citation omitted).3 Thus, 15 while Plaintiff’s delayed construction costs might be recoverable as consequential damages, they 16 are barred here by the parties’ consequential damages waiver. 17 c. Non-Rework Construction Costs 18 Defendant concedes that any costs Plaintiff may have paid to the general contractor to 19 demolish and replace construction performed by Defendant’s allegedly defective design constitute 20 direct damages. Defendant insists, however, that any other construction costs such as those 21 associated with “the allegedly more stringent and code-compliant requirements of the Revised 22 Design” are not recoverable. (Dkt. No. 48 at 19:26-27.) This issue is not related to the damages 23 waiver; instead, Defendant argues that construction that would have been performed regardless of 24 the alleged breach is not a damage at all. While this argument has some force, as discussed at oral 25 argument the Court does not have before it any particular construction demand and thus cannot 26 3 “The Hadley rule has long been applied by California courts, which view it as having been 27 incorporated into California Civil Code section 3300’s definition of the damages available for 1 rule. Such issue shall be raised more particularly on a motion in limine. Accordingly, Defendant’s 2 || motion for summary judgment on the question of whether Plaintiff is entitled to damages for 3 additional construction costs is denied without prejudice. 4 CONCLUSION 5 For the reasons stated above, Defendant’s motion for summary judgment is granted in part 6 || and denied in part. (Dkt. No. 48.) The motion is granted as to Plaintiff's claim for damages for 7 || lost profits, increased operational costs, and delay damages. The motion is otherwise denied. 8 9 IT IS SO ORDERED. 10 Dated: November 15, 2019 11
ACQUELINE SCOTT CORLE 13 United States Magistrate Judge
(«17
Z 18 19 20 21 22 23 24 25 26 27 28