Chinese Hospital Association v. Jacobs Engineering Group, Inc.

CourtDistrict Court, N.D. California
DecidedNovember 15, 2019
Docket3:18-cv-05403
StatusUnknown

This text of Chinese Hospital Association v. Jacobs Engineering Group, Inc. (Chinese Hospital Association v. Jacobs Engineering Group, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chinese Hospital Association v. Jacobs Engineering Group, Inc., (N.D. Cal. 2019).

Opinion

1 2 3 4 5 UNITED STATES DISTRICT COURT 6 NORTHERN DISTRICT OF CALIFORNIA 7 8 CHINESE HOSPITAL ASSOCIATION, Case No. 18-cv-05403-JSC

9 Plaintiff, ORDER RE: DEFENDANT’S MOTION 10 v. FOR PARTIAL SUMMARY JUDGMENT ON CONSEQUENTIAL 11 JACOBS ENGINEERING GROUP, INC., DAMAGES 12 Defendant. Re: Dkt. No. 48

13 14 Plaintiff Chinese Hospital Association alleges that Defendant Jacobs Engineering Group, 15 Inc. breached its written agreement with Plaintiff for architectural services. Defendant’s motion 16 for partial summary judgment on Plaintiff’s right to recover consequential damages is now 17 pending before the Court.1 (Dkt. No. 48.2) Having considered the parties’ briefs and having had 18 the benefit of oral argument on November 14, 2019, the Court GRANTS IN PART and DENIES 19 IN PART Defendant’s motion for summary judgment. The express language of the parties’ 20 contract bars Plaintiff’s claim for lost profits, increased operational costs, and construction delay 21 damages. 22 FACTUAL BACKGROUND 23 In Spring 2007, Chinese Hospital, a nonprofit healthcare services corporation, contracted 24 with Carter & Burgess, Inc., an architecture firm, to design a new hospital. (Dkt. No. 29 at 23, 25 McFarlin Decl. at ¶ 3; Dkt. No. 29 at 57.) At some point thereafter, Carter & Burgess was 26 1 All parties have consented to the jurisdiction of a magistrate judge pursuant to 28 U.S.C. § 27 636(c). (Dkt. Nos. 10, 16.) 1 acquired by Jacobs Engineering Group, Inc. (“Jacobs”) and under a novation agreement between 2 Chinese Hospital, Carter & Burgess, and Jacobs, Jacobs took over Carter & Burgess’ rights and 3 responsibilities under the Design Contract. (Dkt. No. 29 at 23, McFarlin Decl. at ¶ 4.) In the Fall 4 of 2013, Plaintiff “became aware of serious defects in the construction documents” and terminated 5 the parties’ contract as of November 7, 2013. (Complaint at ¶ 11.) Plaintiff thereafter hired 6 another architectural firm to complete the project. (Id. at ¶ 13.) 7 PROCEDURAL BACKGROUND 8 Five years later, Plaintiff filed a certificate of merit in the Superior Court of the County of 9 San Francisco pursuant to California Code of Civil Procedure § 411.35(b)(1). (Dkt. No. 1-5.) The 10 next day, it filed this action in that same court pleading a single cause of action for breach of 11 contract against Defendant. (Dkt. No. 1-3.) Defendant thereafter removed the action based on 12 diversity jurisdiction and four days later filed a motion to dismiss for failure to state a claim. (Id.) 13 The Court granted the motion to dismiss to the extent Plaintiff’s breach of contract claim rests on 14 Defendant’s ordinary obligation to perform work consistent with the standard of care imposed on 15 an architect, but denied the motion to the extent Plaintiff’s claim is based on a different breach of 16 the contract. (Dkt. No. 20.) 17 Defendant thereafter moved for summary judgment on the affirmative defense of waiver, 18 but the Court denied the motion on the grounds that Defendant had not met its burden of proving 19 as a matter of law that Plaintiff waived its right to recover damages by terminating the parties’ 20 contract “for convenience.” (Dkt. No. 41.) Defendant requested the opportunity to separately 21 move for summary judgment on its claim that under the contract Plaintiff is limited to general 22 damages and cannot recover consequential damages. Plaintiff has since filed a statement of 23 damages sought and the parties have submitted briefing on the consequential damages issue. (Dkt. 24 Nos. 45, 48, 53, 54.) 25 DISCUSSION 26 Defendant moves for summary judgment on the issue of consequential damages. In 27 particular, Defendant contends that certain of the damages sought by Plaintiff are barred by the 1 A. Damages for Breach of Contract 2 “Contract damages seek to approximate the agreed-upon performance.” Applied Equip. 3 Corp. v. Litton Saudi Arabia Ltd., 7 Cal. 4th 503, 515 (1994); see also Cal. Civ. Code, § 3300 4 || (flor the breach of an obligation arising from contract, the measure of damages ... is the amount 5 which will compensate the party aggrieved for all the detriment proximately caused thereby, or 6 || which, in the ordinary course of things, would be likely to result therefrom.”). The injured party’s 7 || damages cannot, however, exceed that which it would have received if the contract had been fully 8 || performed on both sides. Cal. Civ. Code, § 3358. 9 “Contractual damages are of two types—general damages (sometimes called direct 10 || damages) and special damages (sometimes called consequential damages).” Lewis Jorge Constr. 11 Memt., Inc. v. Pomona Unified Sch. Dist., 34 Cal. 4th 960, 968 (2004). General damages are 12 || “those that flow directly and necessarily from a breach of contract, or that are a natural result of a 13 || breach.” Jd. Because general damages are “a natural and necessary consequence” of a breach, 14 || they “are often said to be within the contemplation of the parties, meaning that because their 15 occurrence is sufficiently predictable the parties at the time of contracting are ‘deemed’ to have 16 || contemplated them.” /d. In contrast, consequential damages “are those losses that do not arise 3 17 directly and inevitably from any similar breach of any similar agreement. Instead, they are

Z 18 secondary or derivative losses arising from circumstances that are particular to the contract or to 19 || the parties.” Id. 20 B. Plaintiff’s Damages 21 1. The Design Contract 22 As relevant to the current motion, the Design Contract includes the following damages 23 provision: 24 § 1.3.6 CLAIMS FOR CONSEQUENTIAL DAMAGES 25 Notwithstanding any other provision of this Agreement to the contrary, the parties hereto mutually agree that neither party shall be liable to the other for any damages in the nature of lost profits, lost opportunity or 26 ec = arising directly or indirectly from any breach of duty created by 27 28 || (Dkt. No. 48-2 at 18.)

1 2. Plaintiff’s Recoverable Damages 2 “Generally, provisions limiting liability in construction contracts are enforceable under 3 California law so long as the parties negotiated and expressly agreed to the limitations.” Civic 4 Ctr. Drive Apartments Ltd. P’ship v. Sw. Bell Video Servs., 295 F. Supp. 2d 1091, 1105–06 (N.D. 5 Cal. 2003) (citing Cal. Civ. Code § 2782.5). Defendant insists that in light of the above 6 contractual language, three of the categories of damages Plaintiff seeks are not recoverable: (1) 7 increased operational costs/lost revenue, (2) delayed project completion costs, and (3) construction 8 costs except rework costs. The Court addresses each in turn. 9 a) Increased Operational Costs/Lost Revenue 10 Defendant contends the following are non-recoverable consequential/lost profit damages: 11 “having to pay additional personnel to operate pharmacy facilities and to wash and sterilize carts,” 12 “paying more for garbage collection” because there is no “trash compactor at the loading dock,” 13 and “not being able to operate a skilled nursing facility.” (Dkt. No. 48 at 18:6-9.) Defendant’s 14 argument is twofold: (1) that operational costs and lost revenues are consequential damages and 15 therefore not recoverable under the waiver; and (2) even if lost profits are not consequential 16 damages, the express language of the parties’ agreement bars recovery for “lost profits” and “lost 17 opportunity.” 18 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Applied Equipment Corp. v. Litton Saudi Arabia Ltd.
869 P.2d 454 (California Supreme Court, 1994)
Pacific Coast Engineering Co. v. St. Paul Fire & Marine Insurance
9 Cal. App. 3d 270 (California Court of Appeal, 1970)
Lambert v. Superior Court
228 Cal. App. 3d 383 (California Court of Appeal, 1991)
AIU Insurance v. Superior Court
799 P.2d 1253 (California Supreme Court, 1990)
People v. Coffman
96 P.3d 30 (California Supreme Court, 2004)
Mycogen Corp. v. Monsanto Co.
51 P.3d 297 (California Supreme Court, 2002)
Zalkind v. Ceradyne, Inc.
194 Cal. App. 4th 1010 (California Court of Appeal, 2011)
Cortez v. Doty Bros. Equip. Co.
222 Cal. Rptr. 3d 649 (California Court of Appeals, 5th District, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Chinese Hospital Association v. Jacobs Engineering Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/chinese-hospital-association-v-jacobs-engineering-group-inc-cand-2019.