Chinese Hospital Association v. Jacobs Engineering Group, Inc.

District Court, N.D. California·Decided November 15, 2019·No. 3:18-cv-05403·Unknown

Opinion

CHINESE HOSPITAL ASSOCIATION, Case No. 18-cv-05403-JSC

Plaintiff, ORDER RE: DEFENDANT’S MOTION v. FOR PARTIAL SUMMARY JUDGMENT ON CONSEQUENTIAL Defendant. Re: Dkt. No. 48

Plaintiff Chinese Hospital Association alleges that Defendant Jacobs Engineering Group, Inc. breached its written agreement with Plaintiff for architectural services. Defendant’s motion for partial summary judgment on Plaintiff’s right to recover consequential damages is now pending before the Court.1 (Dkt. No. 48.2) Having considered the parties’ briefs and having had the benefit of oral argument on November 14, 2019, the Court GRANTS IN PART and DENIES IN PART Defendant’s motion for summary judgment. The express language of the parties’ contract bars Plaintiff’s claim for lost profits, increased operational costs, and construction delay damages. In Spring 2007, Chinese Hospital, a nonprofit healthcare services corporation, contracted with Carter & Burgess, Inc., an architecture firm, to design a new hospital. (Dkt. No. 29 at 23, McFarlin Decl. at ¶ 3; Dkt. No. 29 at 57.) At some point thereafter, Carter & Burgess was 1 All parties have consented to the jurisdiction of a magistrate judge pursuant to 28 U.S.C. § 636(c). (Dkt. Nos. 10, 16.) acquired by Jacobs Engineering Group, Inc. (“Jacobs”) and under a novation agreement between Chinese Hospital, Carter & Burgess, and Jacobs, Jacobs took over Carter & Burgess’ rights and responsibilities under the Design Contract. (Dkt. No. 29 at 23, McFarlin Decl. at ¶ 4.) In the Fall of 2013, Plaintiff “became aware of serious defects in the construction documents” and terminated the parties’ contract as of November 7, 2013. (Complaint at ¶ 11.) Plaintiff thereafter hired another architectural firm to complete the project. (Id. at ¶ 13.) Five years later, Plaintiff filed a certificate of merit in the Superior Court of the County of San Francisco pursuant to California Code of Civil Procedure § 411.35(b)(1). (Dkt. No. 1-5.) The next day, it filed this action in that same court pleading a single cause of action for breach of contract against Defendant. (Dkt. No. 1-3.) Defendant thereafter removed the action based on diversity jurisdiction and four days later filed a motion to dismiss for failure to state a claim. (Id.) The Court granted the motion to dismiss to the extent Plaintiff’s breach of contract claim rests on Defendant’s ordinary obligation to perform work consistent with the standard of care imposed on an architect, but denied the motion to the extent Plaintiff’s claim is based on a different breach of the contract. (Dkt. No. 20.) Defendant thereafter moved for summary judgment on the affirmative defense of waiver, but the Court denied the motion on the grounds that Defendant had not met its burden of proving as a matter of law that Plaintiff waived its right to recover damages by terminating the parties’ contract “for convenience.” (Dkt. No. 41.) Defendant requested the opportunity to separately move for summary judgment on its claim that under the contract Plaintiff is limited to general damages and cannot recover consequential damages. Plaintiff has since filed a statement of damages sought and the parties have submitted briefing on the consequential damages issue. (Dkt. Nos. 45, 48, 53, 54.) Defendant moves for summary judgment on the issue of consequential damages. In particular, Defendant contends that certain of the damages sought by Plaintiff are barred by the 1 A. Damages for Breach of Contract 2 “Contract damages seek to approximate the agreed-upon performance.” Applied Equip. 3 Corp. v. Litton Saudi Arabia Ltd., 7 Cal. 4th 503, 515 (1994); see also Cal. Civ. Code, § 3300 4 (flor the breach of an obligation arising from contract, the measure of damages ... is the amount 5 which will compensate the party aggrieved for all the detriment proximately caused thereby, or 6 which, in the ordinary course of things, would be likely to result therefrom.”). The injured party’s 7 damages cannot, however, exceed that which it would have received if the contract had been fully 8 performed on both sides. Cal. Civ. Code, § 3358. 9 “Contractual damages are of two types—general damages (sometimes called direct 10 damages) and special damages (sometimes called consequential damages).” Lewis Jorge Constr. 11 Memt., Inc. v. Pomona Unified Sch. Dist., 34 Cal. 4th 960, 968 (2004). General damages are 12 “those that flow directly and necessarily from a breach of contract, or that are a natural result of a 13 breach.” Jd. Because general damages are “a natural and necessary consequence” of a breach, 14 they “are often said to be within the contemplation of the parties, meaning that because their 15 occurrence is sufficiently predictable the parties at the time of contracting are ‘deemed’ to have 16 contemplated them.” /d. In contrast, consequential damages “are those losses that do not arise 3 17 directly and inevitably from any similar breach of any similar agreement. Instead, they are

Z 18 secondary or derivative losses arising from circumstances that are particular to the contract or to 19 the parties.” Id. 20 B. Plaintiff’s Damages 21 1. The Design Contract 22 As relevant to the current motion, the Design Contract includes the following damages 23 provision: 24 § 1.3.6 CLAIMS FOR CONSEQUENTIAL DAMAGES 25 Notwithstanding any other provision of this Agreement to the contrary, the parties hereto mutually agree that neither party shall be liable to the other for any damages in the nature of lost profits, lost opportunity or 26 ec = arising directly or indirectly from any breach of duty created by 27 28 (Dkt. No. 48-2 at 18.)

Free access — add to your briefcase to read the full text and ask questions with AI

Chinese Hospital Association v. Jacobs Engineering Group, Inc., (N.D. Cal. 2019).

Chinese Hospital Association v. Jacobs Engineering Group, Inc. (Chinese Hospital Association v. Jacobs Engineering Group, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Applied Equipment Corp. v. Litton Saudi Arabia Ltd.
869 P.2d 454 (California Supreme Court, 1994)
Pacific Coast Engineering Co. v. St. Paul Fire & Marine Insurance
9 Cal. App. 3d 270 (California Court of Appeal, 1970)
Lambert v. Superior Court
228 Cal. App. 3d 383 (California Court of Appeal, 1991)
AIU Insurance v. Superior Court
799 P.2d 1253 (California Supreme Court, 1990)
People v. Coffman
96 P.3d 30 (California Supreme Court, 2004)
Mycogen Corp. v. Monsanto Co.
51 P.3d 297 (California Supreme Court, 2002)
Zalkind v. Ceradyne, Inc.
194 Cal. App. 4th 1010 (California Court of Appeal, 2011)
Cortez v. Doty Bros. Equip. Co.
222 Cal. Rptr. 3d 649 (California Court of Appeals, 5th District, 2017)