Alaska State Housing Auth. v. Walsh & Co., Inc.

625 P.2d 831, 1980 Alas. LEXIS 669
CourtAlaska Supreme Court
DecidedDecember 19, 1980
Docket3679, 3680
StatusPublished
Cited by7 cases

This text of 625 P.2d 831 (Alaska State Housing Auth. v. Walsh & Co., Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alaska State Housing Auth. v. Walsh & Co., Inc., 625 P.2d 831, 1980 Alas. LEXIS 669 (Ala. 1980).

Opinion

OPINION

CONNOR, Justice.

On July 28, 1972, Walsh & Co., Inc., entered into a contract with the Alaska State Housing Authority whereby Walsh agreed to construct a gravel surface road in the Bethel Heights Low Rent Housing Project, a subdivision of Bethel, Alaska. According to the plans and technical specifications incorporated into the contract, the road was to be constructed of twelve inches of crushed rock surfacing. Specifications for the grade and facet characteristics of this surfacing were also included in the contract. In addition, the agreement provided that the road was to be completed on or before December 30, 1972, and contained a liquidated damages clause which provided that the contractor would be assessed damages of $100 each calendar day, beyond the deadline, until completion, in the event the road was not completed on time.

The contract also required that a 12-inch layer of compacted wood chips be placed below the gravel surface, in order to insulate the gravel surface course from the tundra material below. 1

A pre-construction conference was held on August 21, 1972. During the course of that meeting, an executive officer of Walsh, Edmund C. Enders, indicated that the contractor intended to obtain base material for the crushed surfacing to be used in the project from federal government property at Platinum, Alaska. Chalmers Ekness, ASHA’s architect for the project, asked Enders to arrange to have a sample of the Platinum material submitted to him for approval. Although there is conflict over whether Enders actually refused this request, no such sample was provided to Ekness.

Walsh subsequently barged substantial quantities of the Platinum material to the Bethel jobsite. The first load arrived on or about August 30, 1972. Approximately three weeks later it was examined by ASHA inspectors who concluded that it would not satisfy the technical specifications of the contract.

On September 22, 1972, ASHA informed Walsh in writing that the Platinum material was “non-compliant” and directed the contractor not to incorporate it into the project. Walsh responded that the material did' comply with the requirements of Technical Specification § 2.4, according to independent testing which the contractor had procured. Shortly thereafter it became clear that the central issue of the controversy was whether the specification required the surfacing to be one hundred per cent mechanically crushed. Walsh claimed that the surfacing merely had to satisfy the grading specifications of Alaska Method T-7, with at least fifty per cent of the material retained on the No. 4 screen possessing two or more fractured faces. ASHA, on the other hand, took the position that the material not only had to satisfy these requirements, but also had to be the product of mechanical crushing so as to ensure that all gradations within the composite material contained particles possessing fractured faces. This issue was important insofar as increased particulate angularity improves the degree to which the particles interlock, a factor directly related to the overall suitability of the aggregate as a road surface.

On September 26, 1972, Walsh advised ASHA by letter that none of the Platinum material would be used in the project, stating: “We have no alternative but to comply *834 with your directive.” Shortly thereafter, Walsh clarified its position in another letter to ASHA which stated in pertinent part:

“A thorough study of the specification and of your interpretation as we understand it, leaves us no alternative but to advise you that we cannot accept your interpretation.
In order for Walsh & Co., Inc. to proceed in accordance with your interpretation of the specifications, we would have to import additional gravel. The importation of additional gravel at this late date is impossible because of the freeze-up of the Kuskaquim [sic] River. It now follows that the Project must be shut down for the winter.”

Walsh was not able to import the additional base material until the following summer when the Kuskokwim River finally thawed. The processing of this material was then interrupted a number of times because of equipment failure and the contractor did not seek final inspection and approval of the work until early September, 1973. The final inspection, however, revealed that the average thickness of the wood chip layer underlying the crushed surface was only nine inches, whereas the specifications required a wood chip layer twelve inches thick, and the gravel layer had an average thickness of 14.6 inches.

On May 1, 1974, Walsh filed suit against ASHA seeking recovery of added expenses it allegedly incurred by reason of the controversy over the Platinum material. In addition, Walsh sought recovery of approximately $138,000.00, that portion of the contract price which had no,t been paid. ASHA responded by denying liability for these damages and by filing a counterclaim against Walsh for recovery of “an amount in excess of $100,000.00” in damages, allegedly incurred by reason of the “deficiency” of the contractor’s performance.

At the conclusion of trial, the court found that Walsh had substantially performed its obligations under the contract, and, therefore, was entitled to the remainder of the contract price. In addition, the court found § 2.4 of the Technical Specifications did not clearly require the crushed surfacing to be one hundred per cent manufactured, but rather it was ambiguous on that point. Relying on past decisions of this court, 2 the trial judge construed the provision against ASHA, the drafter of the contract, and held that Walsh was entitled to $607,716.23 in added costs incurred when ASHA “modified” the agreement to require Crushed Surfacing Type A to be one hundred per cent mechanically crushed. Consistent with this, the court also denied ASHA’s claim for $27,100.00 in liquidated damages. The court further found, however, that ASHA was entitled to set-offs totalling $106,793.59 as a result of deficiencies in the contractor’s performance and indicated that an additional $53,260.00 would be added to that sum in the event that ASHA did not accept an offer by Walsh to replace two thousand cubic yards of gravel.

Pursuant to Rule 82, Alaska R.Civ.P., 3 Walsh moved for an additional award of *835 $73,023.41 in attorney’s fees, an amount based on the total of the basic award, $585,-853.79, and prejudgment interest, $136,-699.59. The trial court, however, refused to include the amount of prejudgment interest in computing the basic attorney’s fees award, and therefore determined that the standard award would be $59,435.00. Finding that this amount “may be excessive,” the court then reduced the award to $45,-000.00. The appeal and cross-appeal to this court followed.

I

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
625 P.2d 831, 1980 Alas. LEXIS 669, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alaska-state-housing-auth-v-walsh-co-inc-alaska-1980.