Southeast Alaska Construction Co. v. State, Department of Transportation & Public Facilities

791 P.2d 339, 1990 Alas. LEXIS 51
CourtAlaska Supreme Court
DecidedApril 27, 1990
DocketS-2781, S-2804
StatusPublished
Cited by8 cases

This text of 791 P.2d 339 (Southeast Alaska Construction Co. v. State, Department of Transportation & Public Facilities) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southeast Alaska Construction Co. v. State, Department of Transportation & Public Facilities, 791 P.2d 339, 1990 Alas. LEXIS 51 (Ala. 1990).

Opinion

MOORE, Justice.

This case concerns a public construction project to improve the airport runway in Ruby, Alaska. The project suffered from design and material problems, and the contractor never completed the work. The contractor filed a claim against the State Department of Transportation and Public Facilities (“DOTPF”) for additional com *340 pensation, and DOTPF sought liquidated damages from the contractor. The superi- or court, Judge James R. Blair, entered summary judgment for DOTPF, and the contractor appealed. We affirm.

I.

Southeast Alaska Construction Company (“SEACO”) was the successful bidder on a public construction contract to improve an existing airport runway in Ruby, Alaska. The project was to be completed by October 15, 1985 at a total cost of $546,870.30.

Soon after SEACO began work, it informed DOTPF that the project design contained grading errors and that designated stockpiles of surface course and embankment materials were inadequate or unavailable. SEACO and DOTPF met to resolve these problems during August 1985 and substantially redesigned and expanded the scope of the project. SEACO began work on the expanded project almost immediately-

On September 4, DOTPF issued change order number 1 which purported to set forth the agreement negotiated in August. However, SEACO refused to sign the change order, and the precise terms of the August agreement remain in dispute. SEACO demobilized for the winter without meeting the October 1985 completion deadline.

In December 1985, SEACO submitted a claim for delay damages and compensation for extra work totaling $596,095.85 and requested an extension of the completion deadline to July 15, 1986. The contracting officer adjusted certain unit prices and extended the completion deadline for the expanded project to July 31, 1986. The contracting officer’s decision entitled SEACO to a payment of $33,968 for work already performed.

In the meantime, the company which provided SEACO’s performance and payment bonds became insolvent and was liquidated. SEACO filed a petition in bankruptcy in May 1986. SEACO .actively opposed DOTPF’s motion to lift the automatic stay in bankruptcy to permit termination of the contract. See 11 U.S.C. § 362 (1988).

In June 1986, DOTPF filed a complaint in superior court seeking a declaration that it was entitled to withhold payment on the contract until SEACO provided replacement bonds. SEACO answered and counterclaimed for damages based on the same facts underlying the December 1985 administrative claim. The superior court ruled that SEACO’s counterclaim should have been prosecuted as an administrative appeal from the decision of the contracting officer. SEACO perfected its claim under the applicable procedures and requested a trial de novo. The superior court consolidated the cases and granted a trial de novo.

The superior court ruled that the measure of damages for extra work was out-of-pocket expenses plus reasonable compensation for using SEACO-owned equipment and reasonable overhead and profit. 1 The court also ruled that damages for use of SEACO-owned equipment would be calculated at actual bid rates rather than Blue Book rental rates. The court precluded SEACO from recovering damages exceeding those supported by documents produced in discovery. The court then ruled that based on SEACO’s own records SEACO’s maximum possible recovery was $130,-478.02.

DOTPF moved for summary judgment that it was entitled to recover liquidated damages for delay after the extended contract deadline4 of July 31, 1986. The court ruled that DOTPF was entitled to recover liquidated damages for the period between the extended contract deadline of July 31, 1986 and June 23, 1987 when the bankruptcy court deemed SEACO to have abandoned the contract. At $750 per day, the *341 court calculated that the total liquidated damages award was $207,750.

The court entered final judgment for DOTPF for $76,750, the amount by which DOTPF’s liquidated damages exceeded SEACO’s maximum potential recovery of $131,000.

SEACO appealed. It contends that the superior court erred in entering summary judgment limiting its maximum potential recovery and awarding the state liquidated damages for delay. 2

II.

SEACO argues that the superior court erred in concluding that its recovery for extra equipment costs was limited to the actual rates which SEACO bid for equipment use in the original contract rather than Blue Book rental rates. SEACO relies on our decision in State v. Northwestern Construction, 741 P.2d 235 (Alaska 1987). In that case, errors in state soil-testing procedures increased the amount of work necessary to construct a new runway at Anchorage International Airport. 741 P.2d at 236-37. The trial court relied on Blue Book rates to determine the increased equipment costs resulting from the extra work. 741 P.2d at 237. On appeal, we ruled that the use of Blue Book rates was not clearly erroneous because (1) the contract provided for the use of Blue Book rates to measure extra equipment costs, and (2) Blue Book rates were commonly used to adjust disputes in the local construction industry. Id.

More recently, in Kandik Construction, we reviewed a contract which expressly stated that excess equipment costs would be compensated at the prevailing Fairbanks equipment rental rates. Op. No. 3571 at 13-14. The jury was permitted to award damages based on either Blue Book or prevailing Fairbanks rates. Id. We disapproved the jury instruction on the ground that it conflicted with the measure of recovery set forth in the contract. Id.

These cases permit recovery for extra equipment costs according to the agreement of the parties. Thus, we must examine the contract to determine whether it requires compensation at Blue Book rates.

Sections 10-13 and 40-03 of the contract authorize the contracting officer to issue a change order to require the contractor to perform work within the original scope of the contract. Under section 10-47, work which is not within the original scope of the contract must be covered by a supplemental agreement. Section 40-06 defines “extra work” as work for which there is no basis of payment in the original contract, change orders, or supplemental agreements. When acceptable completion of the contract requires the performance of extra work, the project engineer may issue a change order or order the contractor to perform the extra work according to section 90-05. Section 90-05 provides that extra work will be compensated at the rates set forth in the order authorizing the work, or, if no rate is established, the engineer may require the contractor to perform the work on a time and materials basis. Subsection 90-05(3) provides that the contractor shall receive Blue Book rental rates for machinery and equipment provided on a time and materials basis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alaska Fish & Wildlife Conservation Fund v. State
347 P.3d 97 (Court of Appeals of Alaska, 2015)
Sun v. State
830 P.2d 772 (Alaska Supreme Court, 1992)
State v. Will
807 P.2d 467 (Alaska Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
791 P.2d 339, 1990 Alas. LEXIS 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southeast-alaska-construction-co-v-state-department-of-transportation-alaska-1990.