R. Zoppo Co. Inc. v. Commonwealth

232 N.E.2d 346, 353 Mass. 401, 1967 Mass. LEXIS 746
CourtMassachusetts Supreme Judicial Court
DecidedDecember 12, 1967
StatusPublished
Cited by15 cases

This text of 232 N.E.2d 346 (R. Zoppo Co. Inc. v. Commonwealth) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. Zoppo Co. Inc. v. Commonwealth, 232 N.E.2d 346, 353 Mass. 401, 1967 Mass. LEXIS 746 (Mass. 1967).

Opinion

Reardon, J.

This is a petition under G. L. c. 258 to recover for work and expense allegedly incurred by the petitioner during the performance of a contract with the Commonwealth acting through the Metropolitan District Commission (Commission). Both the petitioner and the respondent filed motions for judgment on undisputed facts in the pleadings and affidavits of counsel, each seeking entry of judgment in its favor 1 under G. L. c. 231, § 59. A Superior Court judge denied the petitioner’s motion and allowed the respondent’s motion. The petitioner appealed. ■ The contract provided for the construction of a sewer for the Deer Island sewage treatment plant in the city of Boston. It included certain deep marine trench excavation •and provided in part for construction and installation of forty linear feet of sixty-inch precast reinforced concrete subaqueous pressure diffuser pipe between designated stations on the outfall sewer line. The petitioner subcontracted the construction of this pipe to the Perini Corporation (Perini).

*403 The diffuser pipe had unique design features and required the fabrication of special forms for its manufacture. To avoid unnecessary delay it was ordered on August 10, 1959, by Perini and it was received on September 28, 1961, according to an affidavit filed in support of the petitioner’s motion for judgment. The affidavit further stated that in accordance with requirements in the prime contract Perini, through the petitioner, submitted to the Commission’s engineer detailed drawings for the sixty-inch pipe with anticipated construction and delivery schedules, all of which were approved by the engineer. The deep marine trench excavation along the line of the pipe as required by the subcontract with Perini was completed.

After manufacture of the pipe and its delivery to the job site and payment in full for it by the subcontractor, certain tidal actions created a condition which in the opinion of the engineer necessitated the deletion of the final twenty-four linear feet of the pipe. The deleted pipe was subsequently transported by the petitioner to its storage yard in East Boston and later, at the direction of the engineer, to the Commission’s storage area on Deer Island. In a letter from the engineer to the Commission dated May 1, 1963, he stated the cost of the contractor’s claim for the twenty-four feet of sixty-inch pipe to be $4,075.63, and further averred that the work performed by the petitioner was extra to the prime contract and should be approved for payment as an extra work claim. The Commission approved the claim in that amount on May 2, 1963, but subsequently requested an opinion of the Attorney General “as to the proper method of payment” for the unused pipe. Acting on the advice of the Attorney General, the Commission thereafter refused payment to the petitioner. The opinion of the Attorney General referred to the advertisement for bids (which became a part of the contract) which indicated that the work to be done consisted of the construction of approximately 5,454 linear feet of outfall sewer, that quantities to be excavated were approximate only, that the work under certain items might be materially greater or less than indicated, and *404 that the contractor agreed that he would accept unit prices as full payment. Reference was also made to the prime contract provisions that the contractor should be paid only for pipe satisfactorily built into place in the completed work, and that if the engineer made any alterations in the work to be done “the Contractor shall have no claim for damages or for anticipated profits on the work that thus may be dispensed with.” There was reference also to that article in the contract relative to payment for extra work, with the observation that selling unused pipe “can hardly be considered ‘work.’ ” The claim presented by the petitioner is for the cost of the twenty-four linear feet of sixty-inch pipe, with additional storage costs and charges for the subcontractor’s and the petitioner’s overhead and profit allocable solely to the delivery of the pipe to the job site.

1. General Laws c. 258 contains the provisions of the statute law upon which the Commonwealth in general waives its sovereign immunity to lawsuits and consents that claims “'of the character which civilized governments have always recognized’ (Murdock Parlor Grate Co. v. Commonwealth, 152 Mass. 28, 31) be determined in its own courts by the same tests to which it forces its citizens to submit in the determination of their claims against each other. Nash v. Commonwealth, 174 Mass. 335, 339.” Chilton Club v. Commonwealth, 323 Mass. 543, 545. It has been settled that in general the law applicable to public contracts is the same as that applicable to private contracts. “If . . . [the United States^ comes down from its position of sovereignty, and enters the domain of commerce, it submits itself to the same laws that govern individuals there.” Cooke v. United States, 91 U. S. 389, 398. Hollerbach v. United States, 233 U. S. 165. United States v. S. S. Claiborne, 252 F. Supp. 897, 899 (S. D. Ala.). We approach decision of the matter raised by this petition with this in mind.

2. Under the provisions of the contract, an engineer was assigned to resolve all questions arising during its performance and, specifically, was empowered to make alterations either before or after the commencement of construction. *405 Not clear in the contract, however, was whether the parties contemplated that the Commonwealth would be liable for payment for work approved by the engineer and commenced before any item was deleted in whole or in part. The contract provisions relative to measurement for payment are not helpful on this question. In fact, they are irrelevant for in this instance the work of the petitioner became impossible solely due to the order of deletion issued by the engineer for the benefit of the Commonwealth. 2

3. Based upon the foregoing, we view this contract as an agreement best interpreted under Restatement: Contracts, § 236. Section 236 (a) calls for an interpretation “which gives a reasonable, lawful and effective meaning to all manifestations of intention” as against an interpretation “which leaves a part of such manifestations unreasonable, unlawful or of no effect.” Section 236 (d) provides additional guidance: “Where words or other manifestations of intention bear more than one reasonable meaning an interpretation is preferred which operates more strongly against the party from . . . [which] they proceed [the Commonwealth], unless their use by . . . [it] is prescribed by law.”

4. We pause to consider certain aspects of this contract and the item, the non-payment for which produced this action. The diffuser pipe, as has been stated, possessed unusual design features and required specialized manufacture. It had no salvage value and the only possible user of it was the Commission.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A.L. Prime Energy Consultant, Inc. v. Mass. Bay Transportation Authority
95 N.E.3d 547 (Massachusetts Supreme Judicial Court, 2018)
Cormier v. City of Lynn
91 N.E.3d 662 (Massachusetts Supreme Judicial Court, 2018)
Josey v. DuBois
6 Mass. L. Rptr. 287 (Massachusetts Superior Court, 1996)
American Fire & Safety, Inc. v. City of North Las Vegas
849 P.2d 352 (Nevada Supreme Court, 1993)
Chase Precast Corp. v. John J. Paonessa Co.
554 N.E.2d 868 (Massachusetts Appeals Court, 1990)
Campbell Hardware, Inc. v. R.W. Granger & Sons, Inc.
516 N.E.2d 150 (Massachusetts Supreme Judicial Court, 1987)
Minton Construction Corp. v. Commonwealth
494 N.E.2d 1031 (Massachusetts Supreme Judicial Court, 1986)
Swanson v. Bankers Life
3 Mass. Supp. 631 (Massachusetts District Court, 1982)
Swanson v. Bankers Life
1982 Mass. App. Div. 143 (Mass. Dist. Ct., App. Div., 1982)
First National Insurance Co. of America v. Commonwealth
380 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1978)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
Frank Fitzgerald, Inc. v. PACELLA BROTHERS, INC
310 N.E.2d 379 (Massachusetts Appeals Court, 1974)
Morash & Sons, Inc. v. Commonwealth
296 N.E.2d 461 (Massachusetts Supreme Judicial Court, 1973)
School Committee of Boston v. Board of Education
292 N.E.2d 338 (Massachusetts Supreme Judicial Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
232 N.E.2d 346, 353 Mass. 401, 1967 Mass. LEXIS 746, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-zoppo-co-inc-v-commonwealth-mass-1967.