Albre Marble & Tile Co. Inc. v. John Bowen Co. Inc.

155 N.E.2d 437, 338 Mass. 394, 1959 Mass. LEXIS 654
CourtMassachusetts Supreme Judicial Court
DecidedJanuary 15, 1959
StatusPublished
Cited by31 cases

This text of 155 N.E.2d 437 (Albre Marble & Tile Co. Inc. v. John Bowen Co. Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Albre Marble & Tile Co. Inc. v. John Bowen Co. Inc., 155 N.E.2d 437, 338 Mass. 394, 1959 Mass. LEXIS 654 (Mass. 1959).

Opinion

Spalding, J.

The declaration in this action of contract contains four counts. The plaintiff in counts 1 and 2 seeks damages for the defendant’s alleged breach of two subcontracts under which the plaintiff agreed to supply labor and materials to the defendant as general contractor of the Chronic Disease Hospital and Nurses’ Home in Boston. 1 In counts 3 and 4 the plaintiff seeks to recover the value of work and labor furnished by it to the defendant at the defendant’s request. The defendant’s substitute answer in defence to the first two counts states that the performance of the subcontracts became impossible when the defendant’s general contract with the Commonwealth was declared invalid by this court in Gifford v. Commissioner of Pub. Health, 328 Mass. 608. The defendant’s answer to counts 3 and 4 (based on quantum meruit) states that no payment could be demanded because the plaintiff did not possess an architect’s certificate for the work done; and that in no event could the defendant be required to pay the plaintiff until it was itself paid by the Commonwealth, and it had received no such payments except those which had been made before the Gifford decision.

*396 The defendant filed a motion, accompanied by an affidavit, for the immediate entry of judgment in its favor under G. L. c. 231, § 59, as appearing in St. 1955, c. 674, § 1. The plaintiff filed a counter affidavit. After hearing, the motion was allowed, and the plaintiff duly claimed an exception. The plaintiff also appealed from the order for judgment. Since all of the questions raised are open under the exceptions there is no need to consider the appeal.

The first question is whether the pleadings and affidavits show that a genuine issue of fact exists as to counts 1 and 2, alleging breach of contract.

The affidavit submitted by the defendant amplifies the defence of impossibility set up in its answer. The facts and circumstances leading to the declaration of the invalidity of the defendant’s general contract with the Commonwealth have been recited in prior decisions and need not be recounted here. See Gifford v. Commissioner of Pub. Health, 328 Mass. 608; M. Ahern Co. v. John Bowen Co. Inc. 334 Mass. 36; Boston Plate & Window Glass Co. v. John Bowen Co. Inc. 335 Mass. 697. The counter affidavit submitted by the plaintiff asserts that the defendant wilfully submitted a bid that was contrary to law in that the cost of performance bonds for the subcontractors was not included; that the general contract awarded to the defendant was procured by fraud; and that the defendant, with knowledge of the infirmities of the general contract, fraudulently induced the plaintiff to enter into the subcontracts. The plaintiff thus attempted to avoid the defence of impossibility by asserting that the invalidity of the general contract was caused by the wrongful acts of the defendant.

The facts upon which the plaintiff relies to avoid the defence of impossibility are set forth upon information and belief. The statute requires that affidavits be “on personal knowledge of admissible facts as to which it appears affirmatively that the affiants would be competent to testify.” G. L. c. 231, § 59. Obviously, statements made upon information and belief do not satisfy these requirements. But there is an alternative provision in the statute which reads:

*397 “. . . [OJr the opposing party shall file an affidavit showing specifically and clearly reasonable grounds for believing that contradiction can be presented at the trial but cannot be furnished by affidavits.” G. L. c. 231, § 59.

We are of opinion that the counter affidavit filed by the plaintiff does not meet the requirements of the statute. It is true that the facts asserted upon information and belief in the affidavit concern to a considerable extent the defendant’s knowledge and intentions, and evidence, of these is usually within the control of the defendant. But the statute provides that interrogatories, and admissions under G. L. c. 231, § 69, or in the pleadings will be considered along with affidavits and stipulations, if any, in deciding whether no genuine issue of material fact exists. Here there is no showing that the plaintiff even attempted to seek answers to interrogatories or that it filed any demand to admit facts. For that matter, no affidavit was filed other than that of its own vice-president. It is to be noted that under the alternative method of opposing the motion for summary judgment the “reasonable grounds for beheving that contradiction can be presented at the trial” must be set forth “specifically” and “clearly.” If the plaintiff’s counter affidavit is treated as satisfying this requirement there would be comparatively few situations in which the statute would operate; the salutary purpose of the statute — which is to avoid the delay and expense of trials in cases where there is no genuine issue of fact — would be set at naught, for it would almost always be possible for a party to file an affidavit containing on information and belief vague and general allegations of expected proof. We are of opinion, therefore, that the granting of the defendant’s motion for judgment on counts 1 and 2 was right.

We turn now to counts 3 and 4 by which the plaintiff seeks a recovery for the fair value of work and labor furnished to the defendant prior to the termination of the general contract. The plaintiff seeks recovery in count 3 for “preparation of samples, shop drawings, tests and affidavits” in connection with the tile work; in count 4 recov *398 cry for similar work in connection with the marble contract is sought.

The defendant in its affidavit maintains that the tile and marble work to be furnished by the plaintiff could not have been done until late in the construction process; that no tile or marble was actually installed in the building; and that the expenses incurred by the plaintiff prior to the time the general contract was declared invalid consisted solely of expenditures in preparation for performance. Relying on the decision in Young v. Chicopee, 186 Mass. 518, the defendant maintains that where a building contract has been rendered impossible of performance a plaintiff may not recover for expenses incurred in preparation for performance, but may recover only for the labor and materials “wrought into” the structure. Therefore, the defendant says, the plaintiff should take nothing here.

The plaintiff places its reliance upon a clause appearing in both contracts which provides in part: “It is agreed you ¡[the plaintiff] will furnish and submit all necessary or required samples, shop drawings, tests, affidavits, etc., for approval, all as ordered or specified . . . .” The plaintiff in effect concedes that no labor or materials were actually wrought into the structure, but argues that the contract provision quoted above placed its preparatory efforts under the supervision of the defendant, and that this circumstance removes this case from the ambit of those decisions which apply the “wrought-in” principle.

In Boston Plate & Window Glass Co. v. John Bowen Co. Inc. 335 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilson v. Robertson
29 Mass. L. Rptr. 484 (Massachusetts Superior Court, 2012)
Lanton v. Lin
27 Mass. L. Rptr. 184 (Massachusetts Superior Court, 2010)
HTA Ltd. Partnership v. Massachusetts Turnpike Authority
747 N.E.2d 707 (Massachusetts Appeals Court, 2001)
Building Commissioner v. Dispatch Communications of New England, Inc.
725 N.E.2d 1059 (Massachusetts Appeals Court, 2000)
Lord's & Lady's Enterprises, Inc. v. John Paul Mitchell Systems
705 N.E.2d 302 (Massachusetts Appeals Court, 1999)
VMark Software, Inc. v. EMC Corp.
642 N.E.2d 587 (Massachusetts Appeals Court, 1994)
Volpe Construction Co. v. First National Bank
567 N.E.2d 1244 (Massachusetts Appeals Court, 1991)
Chase Precast Corp. v. John J. Paonessa Co.
554 N.E.2d 868 (Massachusetts Appeals Court, 1990)
Andrade v. Jablonski
1985 Mass. App. Div. 159 (Mass. Dist. Ct., App. Div., 1985)
Acmat Corp. v. DANIEL O'CONNELL'S SONS, INC.
455 N.E.2d 652 (Massachusetts Appeals Court, 1983)
Baybank Valley Trust Co. v. Block's Women's Shop, Inc.
1982 Mass. App. Div. 264 (Mass. Dist. Ct., App. Div., 1982)
Burkhardt v. Hartford Accident & Indemnity Co.
3 Mass. Supp. 649 (Massachusetts District Court, 1982)
Burkhardt v. Hartford Accident & Indemnity Co.
1982 Mass. App. Div. 163 (Mass. Dist. Ct., App. Div., 1982)
Armand Engineering Co., Inc. v. Adrien A. Labrie, Inc.
427 A.2d 15 (Supreme Court of New Hampshire, 1981)
First National Bank v. Bergreen
417 N.E.2d 50 (Massachusetts Appeals Court, 1981)
Shawmut First County v. Paul Richards Bank, N.A.
1981 Mass. App. Div. 27 (Mass. Dist. Ct., App. Div., 1981)
Framingham Clinic, Inc. v. Zoning Board of Appeals
415 N.E.2d 840 (Massachusetts Supreme Judicial Court, 1981)
Settle v. Keene Savings Bank
423 A.2d 986 (Supreme Court of New Hampshire, 1980)
Cowles v. T & M Equipment Corp.
1980 Mass. App. Div. 138 (Mass. Dist. Ct., App. Div., 1980)
Royal Bank of Canada v. Connolly
403 N.E.2d 423 (Massachusetts Appeals Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
155 N.E.2d 437, 338 Mass. 394, 1959 Mass. LEXIS 654, Counsel Stack Legal Research, https://law.counselstack.com/opinion/albre-marble-tile-co-inc-v-john-bowen-co-inc-mass-1959.