American Fire & Safety, Inc. v. City of North Las Vegas

849 P.2d 352, 109 Nev. 357, 1993 Nev. LEXIS 57
CourtNevada Supreme Court
DecidedMarch 25, 1993
Docket22990
StatusPublished
Cited by7 cases

This text of 849 P.2d 352 (American Fire & Safety, Inc. v. City of North Las Vegas) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Fire & Safety, Inc. v. City of North Las Vegas, 849 P.2d 352, 109 Nev. 357, 1993 Nev. LEXIS 57 (Neb. 1993).

Opinion

*358 OPINION

Per Curiam:

American Fire & Safety, Inc. (“appellant”) appeals from a judgment of the district court denying appellant’s claim for a refund of its bid guarantee (“bid bond”), and awarding the City of North Las Vegas (“the city”) $14,544 on its counterclaim for breach of contract. We affirm the trial court’s decision denying a refund of the bid bond. However, we reverse the $14,544 award of additional damages.

The city solicited closed bids for a job remodeling and installing a fire sprinkler system in the city jail. The city required all bidders to post a bond in the amount of five percent of their bid prices and subject to the following terms:

CONTRACT AND BONDS: The BIDDER to whom the award is made shall, within 10 days after he has received notice of the acceptance of his bid, enter into a written contract with the OWNER. If the successful BIDDER refuses to execute and deliver to the OWNER the contract and bonds required, he shall forfeit the bid guarantee deposited with his bid.
Simultaneous with his delivery of the executed contract, the CONTRACTOR shall furnish a Performance Bond, a Payment Bond and a Guarantee Bond ....

The city’s bid documents did not state whether the forfeiture of the bid bond functioned as a penalty or as liquidated damages, nor did the documents state that a bidder’s liability could exceed the amount of the bond.

With its bid, appellant submitted a cashier’s check for $2,964, which represented five percent of its $59,280 bid. On February 17, 1989, the city notified appellant that the city council had awarded appellant the bid. In March, 1989, appellant demanded *359 that the city pay $1,778, the premium for the performance bond. The city refused to pay for the bond. Appellant likewise refused to pay for the bond, and therefore the parties were unable to execute a written contract. The city retained appellant’s bid bond and awarded the contract to the next lowest bidder, who performed the job for $76,788.

Appellant subsequently brought an action seeking damages for breach of contract, or alternatively for rescission of the bid and restitution of the bid bond. The city counterclaimed for breach of contract and prayed for $17,508 in damages, the difference between appellant’s bid and the next lowest bid. After a bench trial, the trial court denied appellant relief and awarded the city $14,544, which represented the difference between the bids offset by the amount of the bid bond which the city had retained.

Appellant claims that the forfeiture of the bid bond served as liquidated damages for failure to enter the written contract. As a general rule, an aggrieved party’s damages for breach of contract are limited to the amount specified in a valid liquidated damages clause. 5 Arthur L. Corbin, Corbin on Contracts § 1061 (1964). Thus, if the bond forfeiture served as liquidated damages, the trial court should not have awarded the city additional damages of $14,544.

The city contends that the bid bond was not liquidated damages, but rather a penalty. 1 “The principal obligor in a penal bond is often . . . bound by a separate contract to which the bond is merely collateral. The penalty named in the bond does not affect the damages recoverable for breach of that contract.” 5 Corbin on Contracts § 1056. Thus, if the bid bond were a penalty, the city could recover additional damages for appellant’s failure to enter the written contract.

The trial court’s interpretation of the bid documents did not depend upon weighing the credibility of conflicting extrinsic *360 evidence. Thus, this court may review the bid documents de novo:

It is . . . solely a judicial function to interpret a written instrument unless the interpretation turns upon the credibility of extrinsic evidence. Accordingly, “An appellate court is not bound by a construction of the contract based solely upon the terms of the written instrument without the aid of evidence, where there is no conflict in the evidence or a determination has been made upon incompetent evidence.”

Parsons v. Bristol Dev. Co., 402 P.2d 839, 842 (Cal. 1965) (quoting Estate of Platt, 131 P.2d 825, 830 (Cal. 1942)) (citations omitted); see also Mullis v. Nevada National Bank, 98 Nev. 510, 513, 654 P.2d 533, 536 (1982). The fact that the city is a government body does not entitle it to any special preference in our construction of the contract. Priebe & Sons v. United States, 332 U.S. 407, 411 (1947) (“It is customary, where Congress has not adopted a different standard, to apply to the construction of government contracts the principles of general contract law.”); see Cooke v. United States, 91 U.S. 389, 398 (1875) (“If [a government] comes down from its position of sovereignty, and enters the domain of commerce, it submits itself to the same laws that govern individuals there.”); R. Zoppo Co. v. Commonwealth, 232 N.E.2d 346, 349 (Mass. 1967); Bache Halsey Stuart v. University of Houston, 638 S.W.2d 920, 931 (Tex.Ct.App. 1982); Holtzendorff v. Housing Auth. of City of Los Angeles, 58 Cal.Rptr. 886, 893 (Cal.Ct.App. 1967). Forfeiture provisions are strictly construed. 4 Walter H. E. Jaeger, Williston on Contracts § 602A (3d ed. 1961). Forfeitures are disfavored by courts and “should be found only in language which is plain and clear, whose unequivocal character may render its exercise fair and rightful.” Id. (citations omitted). Finally, we note that the city was responsible for drafting the bid documents, and that the bid documents should be “construed most strongly against the authoring party.” Mullis, 98 Nev. at 513, 654 P.2d at 535 (citing Estwin Corp. v. Prescription Ctr. Pharmacy, 93 Nev. 251, 563 P.2d 78 (1977)).

Under some circumstances, it is a close question whether a contract provision constitutes a penalty or liquidated damages. In general,

[a] penalty is a sum named, which is disproportionate to the damage which could have been anticipated from breach of the contract, and which is agreed upon in order to enforce performance of the main purpose of the contract by the compulsion of this very disproportion. It is held in terrorem over the promisor to deter him from breaking his promise.

*361 5

Free access — add to your briefcase to read the full text and ask questions with AI

Related

VIRGIN VALLEY WATER DIST. v. PARADISE CANYON, LLC
141 Nev. Adv. Op. No. 19 (Nevada Supreme Court, 2025)
Jones v. Jones, Jr.
Nevada Supreme Court, 2016
Khan v. Bakhsh
306 P.3d 411 (Nevada Supreme Court, 2013)
State v. Haberstroh
69 P.3d 676 (Nevada Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
849 P.2d 352, 109 Nev. 357, 1993 Nev. LEXIS 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-fire-safety-inc-v-city-of-north-las-vegas-nev-1993.