Dahlstrom Metallic Door Co. v. Evatt Construction Co.

152 N.E. 715, 256 Mass. 404, 1926 Mass. LEXIS 1260
CourtMassachusetts Supreme Judicial Court
DecidedJune 12, 1926
StatusPublished
Cited by31 cases

This text of 152 N.E. 715 (Dahlstrom Metallic Door Co. v. Evatt Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dahlstrom Metallic Door Co. v. Evatt Construction Co., 152 N.E. 715, 256 Mass. 404, 1926 Mass. LEXIS 1260 (Mass. 1926).

Opinion

Crosby, J.

These are suits in equity arising out of an alleged breach of contract between the Dahlstrom Metallic Door Company and the Evatt Construction Company, the former hereinafter being referred to as the subcontractor, and the latter as the contractor. The cases are before us on exceptions to the master’s report and appeals from certain interlocutory and final decrees entered in the Superior Court.

In October, 1922, the trustees of the Boston Chamber of Commerce Realty Trust, entered into a contract with the contractor for the erection of the new Chamber of Commerce Building in Boston, which contained the following provision:

“ALTERATIONS, EXTRAS, AND DEDUCTIONS.
ALTERATIONS NOT INCREASING COST.
“The Architect may from time to time, by an instrument in writing signed by him and approved by the Owner in writing, order the Contractor to make any changes in the work; but shall otherwise have no power to make any change in this contract. In case the changes thus ordered make the work less expensive to the Contractor, a proportional deduction shall be made from the contract price above specified; and, in case said changes make the work more expensive, a proportional addition shall be made to said contract price.”

The contract between the owner and the contractor called for the installation of elevators essential to the use of the building. The contractor entered into an agreement with the subcontractor for the fabrication and installation of elevator enclosures and interior hollow metal doors called for in the specifications and addenda thereto, the erection of which the contractor had undertaken in its contract with the owner. The subcontractor agreed that it would “abide by and be subject to all of the terms, requirements, liabilities and conditions of the Principal Agreement entered into between the Contractor and the Owners and the General conditions of the specifications of the Architects, in so far as the same relate or may be applied to the work of the SubContractor ...” The seventh paragraph of the subcontractor’s contract provided as follows: “Should the Sub-Contractor at any time refuse or neglect to supply a sufficient number of properly skilled workmen, or sufficient [411]*411materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements herein contained, the Contractor shall be at liberty to provide any such labor or materials, and to deduct the cost thereof from any money then due or hereafter to become due ...” and the contractor was given the right to terminate the contract and “enter upon the premises and take possession for the purpose of completing the work ... of all materials, tools and appliances thereon, and to employ any other person or persons to finish the work and to provide the materials therefor. ...” The thirteenth paragraph of the subcontract provided in part that “in the performance of all work . . . the SubContractor will employ labor under conditions satisfactory to the Contractor. The Sub-Contractor agrees to discontinue the employment on this work of any of its employees who may be unsatisfactory to the Contractor.” The sixteenth paragraph provided that as to certain differences between the parties they should be settled by arbitration. It was in evidence that the work which the subcontractor was called upon to perform could be done either by carpenters or iron workers, and that it could be done at less expense by the former. The subcontractor previously had employed carpenters in doing this class of work, but it appeared that at this time a controversy existed between the carpenters’ union and the metal workers’ union relating to work of this character. These suits arise by reason of that controversy.

On March 24, 1924, the contractor telephoned to the general manager of the subcontractor, instructing him to use iron workers in the erection of the elevator enclosures as the contractor, to protect itself, had promised that this work should be given to the iron workers; he insisted that in doing the work iron workers should be employed, but the subcontractor refused to accede to this request and insisted that carpenters should be so employed. In making this demand, the contractor relied upon the clause of the contract by which the subcontractor expressly agreed to discontinue the employment of labor unsatisfactory to the former. The trial judge found that the contractor, in demanding that iron [412]*412workers be employed, was entitled to compliance with his request in view of the terms of the contract if the contractor acted in good faith, which is expressly found. The contractor is found to have been justified in fearing that if carpenters were employed the iron workers would hold up and delay other parts of the work. The business agent of the iron workers’ union threatened the contractor with a strike of all the iron workers on the building unless they were allowed to install the elevator fronts and doors. The contractor notified the subcontractor that under the thirteenth paragraph of the contract it would expect the work to be done by iron workers. On March 25, 1924, the subcontractor, disregarding the contractor’s demand, appeared with carpenters to do the work; the contractor refused to permit them to proceed and they withdrew; whereupon the subcontractor refused to deliver the doors and other materials which had been specially fabricated for the building. The contractor then replevined certain of the materials which were in Boston, and the subcontractor re-replevined them and then brought this bill to compel the contractor to allow the material to be installed by carpenters. A cross bill was brought to enjoin further interference and to compel the subcontractor to deliver the balance of the material. The court dismissed the bill and ordered a decree to be entered for the contractor on the cross bill.

While these proceedings were pending, the owners, being apprehensive that the labor controversy, above referred to, would materially delay the construction of the building and involve it in great loss, at a meeting held on April 8, 1924, voted that the architect be instructed to notify the contractor that the agreement was altered by omitting therefrom the installation of elevator doors and enclosures, so that the subcontractor should be required merely to furnish the material therefor; and on the following day an order, referred to as “Order No. 81” was issued by the architects directing the contractor to omit all labor for elevator doors and enclosures except so far as already furnished. This order is dated April 9, 1924, and was duly approved by the owners on April 10, 1924. The trial judge found that the order was [413]*413issued in good faith and was intended to take from the general contractor the authority to install elevator enclosures and thereby prevent delay caused by the said labor controversy. The contractor immediately notified the subcontractor of the order and demanded delivery of all materials called for by its contract. As these materials were specially made for the Chamber of Commerce Building, they were of limited value or usefulness elsewhere. The power to change the contract did not give the owner the right to abrogate it, but the provision in question entitled the owner to make such reasonable changes as would render the work when completed satisfactory to it. Gaffey v. United Shoe Machinery Co. 202 Mass. 48, 53.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lyman v. Lanser
Massachusetts Appeals Court, 2024
I.Lan Systems, Inc. v. Netscout Service Level Corp.
183 F. Supp. 2d 328 (D. Massachusetts, 2002)
Chelsea Industries, Inc. v. Gaffney
449 N.E.2d 320 (Massachusetts Supreme Judicial Court, 1983)
Barnes v. Orange Foundry, Inc.
1982 Mass. App. Div. 266 (Mass. Dist. Ct., App. Div., 1982)
R. Zoppo Co. Inc. v. Commonwealth
232 N.E.2d 346 (Massachusetts Supreme Judicial Court, 1967)
Oman Construction Company v. City of Nashville
353 S.W.2d 97 (Court of Appeals of Tennessee, 1961)
Goff v. MacDonald
129 N.E.2d 115 (Massachusetts Supreme Judicial Court, 1955)
Goldberg v. Curhan
124 N.E.2d 926 (Massachusetts Supreme Judicial Court, 1955)
In re Seaboyer
116 F. Supp. 780 (D. Massachusetts, 1953)
Gustafson v. Doyle
109 N.E.2d 465 (Massachusetts Supreme Judicial Court, 1952)
P. A. Dolan Co. v. P. S. Thorsen Co.
86 N.E.2d 652 (Massachusetts Supreme Judicial Court, 1949)
Benjamin Foster Co. v. Commonwealth
61 N.E.2d 147 (Massachusetts Supreme Judicial Court, 1945)
Morgan v. Town of Burlington
55 N.E.2d 758 (Massachusetts Supreme Judicial Court, 1944)
Carrig v. Gilbert-Varker Corp.
50 N.E.2d 59 (Massachusetts Supreme Judicial Court, 1943)
Cain's Lobster House, Inc. v. Cain
45 N.E.2d 397 (Massachusetts Supreme Judicial Court, 1942)
J. F. Fitzgerald Construction Co. v. Southbridge Water Supply Co.
23 N.E.2d 165 (Massachusetts Supreme Judicial Court, 1939)
American Hawaiian Steampship Co. v. Columbia Cornice Co.
3 Mass. App. Div. 2 (Mass. Dist. Ct., App. Div., 1937)
Green v. Green
9 N.E.2d 413 (Massachusetts Supreme Judicial Court, 1937)
Connor v. Desjardins
2 Mass. App. Div. 172 (Mass. Dist. Ct., App. Div., 1937)
Brooks v. Davis
1 N.E.2d 17 (Massachusetts Supreme Judicial Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
152 N.E. 715, 256 Mass. 404, 1926 Mass. LEXIS 1260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dahlstrom-metallic-door-co-v-evatt-construction-co-mass-1926.