Oman Construction Company v. City of Nashville

353 S.W.2d 97, 49 Tenn. App. 171, 1961 Tenn. App. LEXIS 103
CourtCourt of Appeals of Tennessee
DecidedJune 30, 1961
StatusPublished
Cited by4 cases

This text of 353 S.W.2d 97 (Oman Construction Company v. City of Nashville) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oman Construction Company v. City of Nashville, 353 S.W.2d 97, 49 Tenn. App. 171, 1961 Tenn. App. LEXIS 103 (Tenn. Ct. App. 1961).

Opinion

I

SHRIVER, J.

The bill in this cause was filed March 29, 1957, and, as amended, sought a recovery of $326,-001.14 as damages suffered by reason of a breach of contract.

The answer of the City generally denied the right of the complainant to recover and when the cause came on to be heard before the Chancellor an order was entered reciting among other things as follows;

“And it appearing to the Court that counsel for the defendant admits that the defendant caused the complainant to be delayed in the performance of its work on the Kerrigan property, the Court holds and finds that said delay was a breach of contract between the parties, and the remaining question *173 before tbe Court is the amount of damages to compensate the complainant for said breach.
“It is therefore ordered, adjudged and decreed by the Court that the defendant breached his contract with the complainant by delaying the complainant in the performance of its contract on the Kerrigan property.
“It is further ordered by the Court that this cause be, and the same hereby is, referred to the Clerk and Master, who, from the proof filed in this cause, will ascertain the amount of damages due the complainant for said breach and report his findings to the Court. ’ ’

Thereafter, the report of the Clerk and Master was filed and, as amended, found damages accruing to the complainant as the result of defendant’s breach in the amount of $176,229.86.

Exceptions were filed by complainant and defendant as a result of which the Master modified his report and found the damages due the complainant from the defendant to be $170,077.35. On appeal to the Chancellor from the ruling of the Clerk and Master on said exceptions a final decree was entered confirming the report as finally made assessing damages in the above amount and, in addition thereto, the Chancellor allowed interest from the date of the filing of the original bill, to wit, March 29, 1957, in the amount of $34,950.60, or a total of $205,-027.95 together with the cost of the cause. From the final decree awarding judgment for the foregoing amount the defendant excepted and perfected his appeal to this Court and has assigned errors.

*174 II

The Master, Honorable A. P. Ottarson, Jr., in his report of May 10, 1960, makes such an excellent statement of his findings of fact which were confirmed by the Chancellor, that we quote with approval from said report as follows;

“TO THE CHANCELLOR:
In this cause an order was entered on May 20, 1959 in Minute Book 184, page 367, requiring the Master to hear proof and report as to what damages, if any, the complainant is entitled to recover from the defendant for a breach of contract entered into between them.
Pursuant to said order I report as follows;”

(Here follows a detailed finding of facts covering about five pages quoted in the original opinion of this Court but which we deem it unnecessary to include in the published opinion.)

The report then takes up the various schedules filed by the complainant setting forth the items of damage claimed. These schedules “A” through “M” are discussed and allowed or disallowed, as the case may be, as to each separate amount claimed. The Master then concludes his report as follows;

“Total days after January 1, 1956, CO m co
Less 15% of days »n
Total days allowed for Interest on Investment 304
The Master allows interest of 5% for 304 days on $135,641.44 or the amount the Master finds to be
*175 due to the complainant because of the breach on the part of the defendant.
5% interest on $135,641.44 for 304 days_$ 5,676.38
Total allowed on contract breach_$161,664.04.”

The report was subsequently amended and, after exceptions were passed on, the final amount hereinabove set forth of $170,077.35 was arrived at by the Master and confirmed by the Chancellor with interest from the filing of the bill and costs added in the final decree.

Ill

Assignments of Error

There are ten assignments of error the first of which is, that there was no material evidence to support the concurrent finding of the Master and Chancellor as to the amount of damages.

The second assignment is that the Master did not apply the proper rule for estimating damages.

The third, fourth mid fifth assignments are to the effect that the report of the Master showed that damages were arrived at by speculation.

Assignment six, complains of the allowance of 15% for overhead and profit as being remote and not the direct result of the non-fulfilment of the contract and because there was no provision in the contract to pay loss of profit in case of default.

Assignments seven and eight, are a reiteration of assignment six.

Assignment nine, complains of the allowance of the salaries of personnel who performed work on a Louis *176 ville, Kentucky, job at the same time that the Nashville job was in progress.

Assignment ten, avers that the Chancellor abused his discretion in allowing complainant 6% interest on the amount allowed from the date of the filing of the bill.

IV

The rule is too well settled in this state to require citation of authority that a concurrent finding of fact by the Master and Chancellor are binding on this Court if supported by any substantial, material evidence.

The facts as set forth in the Master’s report are supported by competent and material evidence, hence, if the defendant is to succeed in having us sustain its assignments, such success must be based on a proposition of law or on the ground that the Master applied the wrong rule or method in assessing damages.

We think it would serve no good purpose to discuss each of the assignments separately, nor is it necessary to take up each of the separate schedules “A” through “M” passed on by the Master and his findings confirmed by the Chancellor and which were discussed at great length in the brief of counsel for defendant and replied to by counsel for complainant.

The items set forth in these various schedules which were allowed as damages by the Master and Chancellor are supported by the proof and we concur in these findings as to schedules “A” through “L”.

As to schedule “M” which deals with insurance and taxes on labor and overhead and with profits and interest on capital invested, we think there is some question.

*177

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cecil Corley Motor Co., Inc. v. General Motors Corp.
380 F. Supp. 819 (M.D. Tennessee, 1974)
Southern Roofing & Petroleum Co. v. Aetna Insurance Co.
293 F. Supp. 725 (E.D. Tennessee, 1968)
Engert v. Peerless Insurance Company
382 S.W.2d 541 (Court of Appeals of Tennessee, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
353 S.W.2d 97, 49 Tenn. App. 171, 1961 Tenn. App. LEXIS 103, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oman-construction-company-v-city-of-nashville-tennctapp-1961.