Barnes v. Orange Foundry, Inc.

1982 Mass. App. Div. 266, 4 Mass. Supp. 39
CourtMassachusetts District Court, Appellate Division
DecidedNovember 8, 1982
StatusPublished

This text of 1982 Mass. App. Div. 266 (Barnes v. Orange Foundry, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barnes v. Orange Foundry, Inc., 1982 Mass. App. Div. 266, 4 Mass. Supp. 39 (Mass. Ct. App. 1982).

Opinion

Larkin, J.

This appeal involves issues of law generated by a claim by the plaintiff, Thomas A. Barnes, a building contractor (hereinafter referred to as the “contractor”) for payment for certain construction work and materials furnished to the defendants, Orange Foundry, Inc. (hereinafter referred to as the “Owner”) and Richard W. Peterson (hereinafter referred to as “Peterson”).

This action was commenced when the contractor filed his complaint against the Owner and Peterson. The complaint sought damages of $10,699.00 and was brought on three counts. The first count sought damages on a written agreement, the secord count sought damages under a theory of quantum meruit, and the third count sought damages under the provisions of G.L.c 93A, §2. The Owner and Peterson filed an answer and counterclaim denying the allegations made in Counts I, II and III of the Contractor’s complaint and alleging as affirmative defenses that Peterson was at all times relevant acting as an officer and agent of the Owner; that the construction work performed by the Contractor was not done in a workmanlike manner and the Contractor failed to complete all of the work under the contract; and that the Contractor was in breach of the contract which provided that final payment was to be made only upon completion of the work. By way of counterclaim, the Owner asserted that the Contractor failed to complete the work by September 3, 1979 as arguably required by the contract, and owed the Owner $300.00 per day for liquidated damages, and the Contractor owed the Owner additional damages as a result of the Contractor's incomplete, defective and unworkmanlike work. The Contractor filed an answer to the Owner’s counterclaims denying the allegations of both counterclaims.

The Court found for the Contractor and against the Owner on Count I of the complaint and fixed damages in the sum of $4,405.00. The Court further found for the Owner on Counts II and III of the complaint and found for the defendant Peterson on all counts of the complaint (on the basis that Peterson, at all relevant times, had acted in a representative capacity). The Court found for the Contractor on both the first and second counterclaims.

The record indicates that the Contractor had been engaged in the construction business in the Orange area for approximately ten years. The individual defendant Peterson was [267]*267an officer of the Owner — a corporation engaged in the foundry business in Orange, Massachusetts. In the summer of 1979, the Owner decided to convert “attic space” in a foundry building into a six room office suite. In furtherance of this objective, the Owner submitted a detailed floor plan for the projected renovation. Thereafter, the Contractor and the Owner inspected the situs of the proposed work. During the latter part of July, 1979, the parties again met at which time the Contractor submitted a written “proposal’ ’ to the Owner. This “proposal,” set forth in handwriting on a single sheet of paper, outlined the work to be done and established a projected price of $38,500.00 for the proposed work.

On August 6, 1979, Peterson, on behalf of the Owner, presented the Contractor another handwritten single sheet of paper containing the following language:

8/6/79
Orange Foundry - Tom Barnes
Job complete turn key operation by September 3rd for $35,800. Three hundred dollars per day will be deducted from the above price for every day past September 3rd.
Payment Scheudule
9,000 25% payment when floor complete
9,000 25% payment when studding complete
9,000 25% payment when tile laid and paneling up
8,800 25% payment when complete
Everything stated in quote plus $800. — front doors and stairs, but not including air-conditioning.
Orange Foundry
si Richard W. Peterson
si Thomas A. Barnes

The record reflects that after reviewing the agreement and before signing it, the Contractor and the Owner had some discussion concerning the proposed completion date. Prior to entering into the contract, the record indicates that the parties had met with the local building inspector. This meeting resulted in the realization that in order to locate the projected office suite in the second floor attic area of the foundry building, it would be necessary to undertake considerable work in order to alter the existing support trusses then present in the attic area. As a result of the alteration of the trusses, it became apparent that it would be necessary for the Contractor to put in place steel support columns to support the floor of the office suite to be constructed under the contract.

At all events, there was evidence, which the trial judge obviously credited, that the Contractor commenced work on the job immediately upon execution of the contract, employed two shifts and had his crews working diligently through the weekends in order that the project might be completed in as timely a fashion as possible, considering the scope and extent of the work to be performed.

As of September 3, 1979, the Contractor had received periodic payments totaling $18,000.00 pursuant to the schedule. By that date, the record indicates that the Contractor informed the Owner that it might proceed to occupy the offices. Five days later, on September 8th, the Owner proceeded to move in and occupy the new suite of offices. At the time that the Owner moved in, there still remained some work to be performed. At or about this time, but clearly after September 3, 1979, the Owner paid an additional $9,000.00 to the Contractor, again, presumably pursuant to the periodic payment schedule. This $9,000.00 payment brought to $27,000.00 the total payments which the [268]*268Owner made to the Contractor as the Contractor proceeded towards ultimate completion of the job.

The Contractor continued to do work on the project until approximately January 1, 1980, at which time the Owner refused to pay any further amounts under the contract. With this refusal, the Contractor ceased his work on the premises and the instant action commenced in the District Court - the Contractor suing both the corporate and individual defendants for the balance assertedly remaining under the agreement and the Owner counterclaiming for the purportedly incomplete and defective work as well as seeking to invoke the strictures of the “penalty” clauses set forth above.

After the suit was entered and during the course of the trial, in January of 1981, the Court took a “view” of the premises and observed several aspects of the job which required correction, repair and further installation. The Court found that the reasonable cost of repairs, installation of additional columns and corrections of defective work was $6,294.00. The Court deducted this amount from the total of $10,699.00 which the Contractor was seeking and, accordingly, awarded him the sum of $4,405.00

It is the essence of the Owner's position that there was a basic inconsistency in the trial court's award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C. C. & T. Construction Co. v. Coleman Bros.
330 N.E.2d 216 (Massachusetts Appeals Court, 1975)
M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc.
205 N.E.2d 239 (Massachusetts Supreme Judicial Court, 1965)
DiMare v. Capaldi
146 N.E.2d 517 (Massachusetts Supreme Judicial Court, 1957)
A-Z Servicenter, Inc. v. Segall
138 N.E.2d 266 (Massachusetts Supreme Judicial Court, 1956)
Kauranen v. Mattaliano
199 N.E.2d 214 (Massachusetts Supreme Judicial Court, 1964)
Fox v. Harding
61 Mass. 516 (Massachusetts Supreme Judicial Court, 1851)
Sipley v. Stickney
76 N.E. 226 (Massachusetts Supreme Judicial Court, 1906)
Bowen v. Kimbell
203 Mass. 364 (Massachusetts Supreme Judicial Court, 1909)
Handy v. Bliss
90 N.E. 864 (Massachusetts Supreme Judicial Court, 1910)
Hennessey v. Preston
219 Mass. 61 (Massachusetts Supreme Judicial Court, 1914)
Dahlstrom Metallic Door Co. v. Evatt Construction Co.
152 N.E. 715 (Massachusetts Supreme Judicial Court, 1926)
Bucholz v. Green Bros. Co.
172 N.E. 101 (Massachusetts Supreme Judicial Court, 1930)
Hub Construction Co. v. Dudley Wood Works Co.
175 N.E. 48 (Massachusetts Supreme Judicial Court, 1931)
Nevins v. Ward
67 N.E.2d 673 (Massachusetts Supreme Judicial Court, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
1982 Mass. App. Div. 266, 4 Mass. Supp. 39, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barnes-v-orange-foundry-inc-massdistctapp-1982.