DiMare v. Capaldi

146 N.E.2d 517, 336 Mass. 497, 1957 Mass. LEXIS 676
CourtMassachusetts Supreme Judicial Court
DecidedDecember 11, 1957
StatusPublished
Cited by29 cases

This text of 146 N.E.2d 517 (DiMare v. Capaldi) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DiMare v. Capaldi, 146 N.E.2d 517, 336 Mass. 497, 1957 Mass. LEXIS 676 (Mass. 1957).

Opinion

Cutter, J.

The plaintiffs, by their bill for declaratory relief against one Frank Capaldi and his father, ask that the court determine (a) what persons are parties to a written contract with the plaintiffs for the construction of a dwelling in Belmont and (b) “the validity and construction of” the contract and “the damage sustained ... by the fraud, negligence, improper and faulty construction, delay and improper materials, and the wilful and deliberate departure from the plans and specifications, in connection with the construction.” The somewhat ambiguous contract for the construction of the house in about 120 working days recites that “many changes . . . have been . . . mutually agreed” and that the “specifications and plans will be used as a guide only.” The agreed price was to be $35,500.

The bill alleged, among other things, that the “work was done in a slovenly and unworkmanlike manner by subcontractors of defendants’ choice and the materials used were not according to specifications”; that “construction dragged on and was not completed in about 120 working days” (as required by the contract); and that in “many other respects, there was a deliberate . . . departure . . . from the requirements of the plans and specifications.”

The case was referred to a master (to be heard with an action at law brought by the defendant Frank Capaldi against the present plaintiffs) to “find the facts and the subsidiary facts upon which his ultimate conclusions are based.” Despite the terms of the order referring the cases *499 to him, the master filed a report which contained excessive recitals of evidence (see Jameson v. Hayes, 250 Mass. 302, 306-307; Joyner v. Lenox Savings Bank, 322 Mass. 46, 57-58; note to Rule 90 of the Superior Court [1932] at pages 280-281) and somewhat meager subsidiary findings of fact. To this report, Frank Capaldi (hereinafter called the defendant) filed some forty objections, but the defendant did not (see Rule 90 of the Superior Court [1954]) file any written request with any of his objections for a summary of the evidence relevant to such objections. A motion to recommit was denied and the report was confirmed. Appeals then were taken from the interlocutory decrees denying the motion to recommit and confirming the master’s report and from a final decree 1 adjudging that the defendant is indebted to the plaintiffs in the sum of $7,750 with interest (see note 3, infra).

The master made the following findings, among others, (a) “that there was no substantial performance in good faith” by Frank Capaldi (specifying certain deficiencies); (b) that the payments made by the plaintiffs “were made promptly” and Frank Capaldi “was not justified in leaving the work which ... he did not complete” (specifying the work which he did not complete); (c) “that under the circumstances” the plaintiffs were “justified in calling off the contract and taking possession of the premises ”; (d) that Frank Capaldi is “responsible for the . . . reasonable costs . . . of completing the work . . . left undone” (specifying work in the aggregate sum of $2,397.26); (e) that the “fist of defects [apparently referring to a table of defects stated in his recitals of the testimony] included above in detail are directly related to the failure of Frank Capaldi to build such of the house as he did build in a . . . workmanlike manner and that the cost of repairing the same was” $5,160.80; (f) “that the value of the house had the contract been completed would have been” $35,500 and that “the value of the house as left by . . . Capaldi” was *500 $27,991.94; and (g) that the plaintiffs are entitled to judgment against Frank Capaldi in the sum of $7,558.06 with interest from the date of entry of the bill of complaint. The master had previously found as a subsidiary finding that the plaintiffs had paid to the defendant under the contract the sum of $33,981.58.

1. We need not consider those objections (now exceptions under Rule 90 of the Superior Court [1954]) to the master’s report which seek merely revisions in the master’s recitals of the testimony, or which assert that particular findings had no support in the evidence. No transcript appears to have been taken by a stenographer selected or approved by the master before any evidence was introduced and summaries of evidence to determine “whether the evidence was sufficient in law to support a finding of fact” could not be obtained under Rule 90 for that purpose.

2. Various exceptions are directed to the issue, apparently much discussed before the master, whether the plaintiffs’ payments under the contract were made promptly. The master has found that they were made promptly under the circumstances. Since there are no summaries of the evidence, obtained in compliance with Rule 90 (see Sheppard Envelope Co. v. Arcade Malleable Iron Co. 335 Mass. 180, 184-185), we cannot say on the present record that this conclusion was erroneous. There is thus no basis on this record for considering whether delays in payments by the plaintiffs excused any performance required of the defendant under the contract.

3. The defendant argues that the bill should be dismissed because the master’s findings show a variance between the bill of complaint and the proof, in that the bill alleged misrepresentations by (or in behalf of) the defendant, leading the plaintiffs to make the contract, whereas the master found that these charges had not been sustained. The bill (designated as one for a declaratory judgment), however, also seeks (as already stated) a construction of the contract and a determination of the damages caused by the defendant’s somewhat generally alleged *501 negligence and faulty construction. The proof and findings appear to be consistent with these' allegations which are separate from the allegations of misrepresentation.

4. The defendant contends that the master’s finding that the plaintiffs were “justified in calling off the contract” is inconsistent with his finding that the defendant “was not justified in leaving the job.” Even if these findings are in fact inconsistent, the master has made definite findings with respect to the serious deficiencies of the defendant’s work which justify charging the defendant with the damages caused by those deficiencies without regard to whether he stopped work wrongfully, leaving work undone and badly done, or was prevented from further performance by the plaintiffs’ justified termination of the contract for cause. The materiality of the inconsistency, if one exists, has not been shown.

5. With respect to the issue of damages, the defendant filed various objections to the report, principally drawing attention to the inadequacy or absence of subsidiary findings. The matter of recommitting a master’s report for more complete subsidiary findings is normally a matter within the discretion of the court which appointed him (see Black v. Parker Manuf. Co. 329 Mass. 105, 117-118). Although the master’s subsidiary findings on damages are not as complete and clear as would be desirable, this is not a case (compare Turgeon v. Turgeon, 326 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fall River Hous. Auth. v. HV COLLINS CAPE COD LATH
604 N.E.2d 1310 (Massachusetts Supreme Judicial Court, 1992)
Lima v. Jeffrey
1989 Mass. App. Div. 201 (Mass. Dist. Ct., App. Div., 1989)
General Electric Co. v. Board of Assessors
472 N.E.2d 1329 (Massachusetts Supreme Judicial Court, 1984)
Bachman v. Parkin
19 Mass. App. Ct. 908 (Massachusetts Appeals Court, 1984)
Adams v. Elliott
1982 Mass. App. Div. 315 (Mass. Dist. Ct., App. Div., 1982)
Barnes v. Orange Foundry, Inc.
1982 Mass. App. Div. 266 (Mass. Dist. Ct., App. Div., 1982)
B&M Siding Corp. v. Sucu
3 Mass. Supp. 428 (Massachusetts District Court, 1982)
B & M Siding Corp. v. Sucu
1982 Mass. App. Div. 62 (Mass. Dist. Ct., App. Div., 1982)
Schleifstein v. Greenstein
401 N.E.2d 379 (Massachusetts Appeals Court, 1980)
In re Pew Memorial Trust No. 2
5 Pa. D. & C.3d 698 (Philadelphia County Court of Common Pleas, 1977)
McKenna v. Begin
362 N.E.2d 548 (Massachusetts Appeals Court, 1977)
Galaris v. Cohen
330 N.E.2d 224 (Massachusetts Appeals Court, 1975)
P. J. Riley & Co. v. Aberthaw Construction Co.
327 N.E.2d 909 (Massachusetts Appeals Court, 1975)
Sowle v. Empire Mutual Insurance
309 N.E.2d 895 (Massachusetts Appeals Court, 1974)
Paone v. Rogers
307 N.E.2d 350 (Massachusetts Appeals Court, 1974)
Louise Caroline Nursing Home, Inc. v. Dix Construction Corp.
285 N.E.2d 904 (Massachusetts Supreme Judicial Court, 1972)
Kass v. Todd
284 N.E.2d 590 (Massachusetts Supreme Judicial Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
146 N.E.2d 517, 336 Mass. 497, 1957 Mass. LEXIS 676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dimare-v-capaldi-mass-1957.