B&M Siding Corp. v. Sucu

3 Mass. Supp. 428
CourtMassachusetts District Court
DecidedMarch 3, 1982
DocketNo. 8695
StatusPublished

This text of 3 Mass. Supp. 428 (B&M Siding Corp. v. Sucu) is published on Counsel Stack Legal Research, covering Massachusetts District Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B&M Siding Corp. v. Sucu, 3 Mass. Supp. 428 (Mass. Ct. App. 1982).

Opinion

OPINION

Cowdrey, P.I.

This is an action in contract to recover a balance allegedly due for work performed by the plaintiff corporation on the defendant’s residence. The trial court.entered judgment for the, plaintiff in the amount of $1,537.50.

On August 8, 1977 the parties executed a written contract for the installation of vinyl siding and styrofoam insulation, and for certain roofing and downspout work on the defendant’s home for a total cost of $6,375.00. The agreement was expressly rendered conditional upon the defendant’s securing of a $5,000.00 construction loan. Additional miscellaneous clauses of the printed form contract provided for the plaintiff’s procurement of Workmen’s Compensation and Public Liability Insurance, and for plaintiff’s furnishing its customary guarantee upon completion of the project.

• The report indicates that in October, 1977 the plaintiff installed vinyl siding and three-quarter inch, tongue'-in-groove installation on all exterior walls of the defendant’s home; installed new downspouts; and covered all trim around the windows, overhangs and doors of the dwelling with aluminum. The defendant was present on the property during the course of the plaintiff’s performance.

The defendant, at the commencement of the repair work, requested the installation of aluminum foil under the vinyl siding despite the plaintiff’s assurances that the same was unnecessary. Both parties ultimately agreed to the installation at a cost of $8.00 per roll of foil. After the plaintiff’s completion of three sides of the house, which entailed the, use of a total of ten rolls of foil, the defendant informed the plaintiff that he would not pay for the foil. Accordingly, the plaintiff did not install aluminum foil on the forth side of the house. Additional extra labor and materials valued at $82.60 were furnished by the plaintiff at the defendant’s request.

The defendant paid the plaintiff the sum of $5,000.00, leaving a contract balance of $1,375.00 for the principal work and $162.60 for extras for a total sum due of $1,537.60.

The evidence at trial consisted of the testimony of the plaintiff corporation’s president and the written contract. The trial justice took a view of the premises. The defendant presented no evidence in the lower court.

The trial court initially entered subsidiary findings of fact that the parties’ agreement called for “siding, insulation, roofing and downspout work” on the defendant’s residence in addition to “mutually agreed upon extras” and that the “work was performed according to the contract specifications in a good and workmanlike fashion.”

The defendant thereafter moved pursuant to Dist./Mun. Cts. R. Civ. P. 52 to amend the above subsidiary findings to reflect a lack of evidence, as alleged by the defendant, that the plaintiff made a full and complete performance under the contract in a good and workmanlike manner. The defendant requested specific findings of fact that there was no evidence: (1) that the defendant obtained [430]*430a loan, of $5,000.00; (2) that the plaintiff carried Workmen’s Compensation and Public Liability Insurance; or that (3) the plaintiff furnished a guarantee upon the completion of its work. The trial court denied the defendant’s Rule 52 motion, but clarified its findings, in relevant part, as follows:

“Plaintiff installed insulation and siding on Defendant’s home in a workmanlike manner in accordance with the specifications of a written contract....after trial and a view of the property in question, the Court entered a finding for the plaintiff and assessed damages at $1,537.50.
“The written instrument contained a clause which provided that Plaintiff would carry worker’s compensation and public liability insurance, and that the job was conditional upon Defendant’s obtaining a $5,000.00 loan. Defendant does not assert that Plaintiff failed to purchase the requisite insurance for the job or. that Defendant failed to receive the loan. Defendant asserts that Plaintiff did not proye these facts in its case in chief. There is no report of any accident on the job or any claim or potential claim against Defendant by any of Plaintiff’s workers. In addition, Defendant was on the job site, authorized the work to begin and supervised the progress of the work.
“Apart from the contract, the Court also finds that the benefit conferred on the Defendant was equal to the contract price plus $162.50 or $6,537.50.”

The defendant now claims to be aggrieved by the denial of his Rule 52(b) motion, and by the court’s disposition of various requests for rulings of law.

1. We are compalled in the interests of substantial justice to order a new trial in this case. G.L.c. 231, s. 110; Kupferschmid v. Sonus Corp., 44 Mass. App. Dec. 196, 203 (1970); Berger & Co., Inc. v. Alcock Admx., 35 Mass. App. Dec. 66, 71 (1966).

The plaintiff’s complaint sets forth a single count for breach of contract. It is familiar law that recovery on a contract theory of action requires evidence of the plaintiff’s complete and strict performance of all terms of the contract at issue, Hayceck Bldg. & Realty Co. v. Turcotte, 361 Mass. 785, 789 (1972); Andre v. Maguire, 305 Mass. 515, 516 (1940); Lantz v. Chandler, 17 Mass. App. Dec. 150, 154 (1959). The defendant is correct in his contention that the report herein is devoid of conclusive evidence as to the plaintiff’s compliance with each individual term and requirement of the parties’ written agreement. This evidentiary deficiency in the report appears, however, to be a function of the technical posture of the lower court proceedings rather than ,a compelling indication of any lack of merit in the plaintiff’s claim.1

Illustrative of the problem is the defendant’s contention that the plaintiff failed to satisfy its burden of establishing compliance with contract clauses requiring the procurement of Workmen’s Compensation and Public Liability Insurance for the project. It has been held that an unintentional failure to obtain such coverage does not necessarily constitute a dispositive breach of a building contract precluding recovery, even in those instances where an accident or other mishap in the course of construction rendered resort to such insurance necessary. See, DiMare v. Capaldi, 336 Mass. 497, 503-504 (1957); Baccari v. B. Perini & Sons Inc., 293 Mass. 297, 302 (1936). The trial court herein clearly utilized this approach in its disposition of the defendant’s Dist./Mun. Cts. R. Civ. P. 52(b) motion. The court effectively ruled that any possible failure of the plaintiff to secure insurance coverage [431]*431Was a de minimis contract deviation which did not bar the plaintiff’s recovery.

The de minimis rule for contract deviations is, however, applicable only where the claim for recovery is in quantum meruit rather than on the contract. See, Russo v. Charles I. Hosmer, Inc., 312 Mass. 231, 233-234 (1942); Zarthar v. Salibar, 282 Mass. 558, 561-562 (1933). Where, as in the instant case, there is no count in the complaint for quantum meruit, evidence of substantial performance in good faith under the contract is technically insufficient to sustain a finding for the plaintiff. Glazer v. Schwartz, 276 Mass. 54, 56 (1931); Cutter v. Arlington, 268 Mass. 88, 92 (1929). It was in-' cumbent upon the plaintiff herein to establish that it had obtained Workmen’s Compensation and Public Liability Insurance in accordance with the parties’ contract. See generally, Waldo Bros. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loranger Construction Corp. v. E. F. Hauserman Co.
384 N.E.2d 176 (Massachusetts Supreme Judicial Court, 1978)
DiMare v. Capaldi
146 N.E.2d 517 (Massachusetts Supreme Judicial Court, 1957)
Tisei v. Building Inspector of Marlborough
363 N.E.2d 262 (Massachusetts Appeals Court, 1977)
HAYECK BUILDING & REALTY CO. INC. v. Turcotte
282 N.E.2d 907 (Massachusetts Supreme Judicial Court, 1972)
Cantara v. Massachusetts Bay Transportation Authority
323 N.E.2d 759 (Massachusetts Appeals Court, 1975)
Lewis v. Vallis
255 N.E.2d 337 (Massachusetts Supreme Judicial Court, 1970)
Cutter v. Arlington Construction Co.
167 N.E. 266 (Massachusetts Supreme Judicial Court, 1929)
Glazer v. Schwartz
176 N.E. 613 (Massachusetts Supreme Judicial Court, 1931)
Zarthar v. Saliba
185 N.E. 367 (Massachusetts Supreme Judicial Court, 1933)
Gagnon v. Ainsworth
186 N.E. 498 (Massachusetts Supreme Judicial Court, 1933)
Baccari v. B. Perini & Sons, Inc.
199 N.E. 912 (Massachusetts Supreme Judicial Court, 1936)
Andre v. Maguire
26 N.E.2d 347 (Massachusetts Supreme Judicial Court, 1940)
Russo v. Charles I. Hosmer, Inc.
44 N.E.2d 641 (Massachusetts Supreme Judicial Court, 1942)
Nevins v. Ward
67 N.E.2d 673 (Massachusetts Supreme Judicial Court, 1946)
Avis Rent-a-Car System, Inc. v. Vogel
16 Mass. App. Dec. 133 (Mass. Dist. Ct., App. Div., 1959)
Nadeau v. Clough
47 Mass. App. Dec. 33 (Mass. Dist. Ct., App. Div., 1971)
Kupferschmid v. Sonus Corp.
44 Mass. App. Dec. 196 (Mass. Dist. Ct., App. Div., 1970)
Lantz v. Chandler
17 Mass. App. Dec. 150 (Mass. Dist. Ct., App. Div., 1958)
Harry Berger & Co. v. Estelle Alcock Admx.
35 Mass. App. Dec. 66 (Mass. Dist. Ct., App. Div., 1966)

Cite This Page — Counsel Stack

Bluebook (online)
3 Mass. Supp. 428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bm-siding-corp-v-sucu-massdistct-1982.