Clark-Fitzpatrick, Inc./Franki Foundation Co. v. Gill

652 A.2d 440, 1994 R.I. LEXIS 302, 1994 WL 720869
CourtSupreme Court of Rhode Island
DecidedDecember 29, 1994
Docket93-258-Appeal, 94-81-Appeal
StatusPublished
Cited by79 cases

This text of 652 A.2d 440 (Clark-Fitzpatrick, Inc./Franki Foundation Co. v. Gill) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clark-Fitzpatrick, Inc./Franki Foundation Co. v. Gill, 652 A.2d 440, 1994 R.I. LEXIS 302, 1994 WL 720869 (R.I. 1994).

Opinion

OPINION

MURRAY, Justice.

This matter is before us on appeal by the Rhode Island Department of Transportation (state or DOT) and on cross-appeal by Clark-Fitzpatrick, Ine./Franki Foundation Co., a joint venture (CFF), and Consolidated Prestressed Concrete, Inc. (CPC), from two Superior Court judgments entered against the state for damages arising from the construction of the Jamestown-Verrazzano Bridge. For the reasons that follow, the state’s appeal is sustained in part and denied in part, and the cross-appeals of CFF and CPC are denied and dismissed.

We have gleaned the following facts from the trial justice’s decision and other portions of the very extensive record in the case. On September 28, 1984, DOT released contract-bid documents to potential bidders for the construction of the replacement for the Jamestown Bridge connecting the island of Jamestown with the mainland at North Kingstown. The replacement-bridge design comprised three components: (1) a trestle approach (two alternatives) for the horizontal roadway running from North Kingstown out over the water to the bridge itself, (2) a steel main-bridge alternate, and (3) a concrete main-bridge alternate. Gordon R. Archibald, Inc. (Archibald), and T.Y. Lin International (T.Y. Lin) each submitted a trestle design. Howard, Needles, Tammen and Bergdorf designed the steel alternate, and T.Y. Lin designed the concrete alternate. Contractors bidding for the project could choose between two alternatives for each portion of the bridge.

Bids were originally scheduled to open December 7, 1984, but were deferred by DOT to December 19, 1984. The lowest bid, $63,-944,000, was submitted by CFF, which bid Archibald’s trestle design with T.Y. Lin’s concrete main-bridge alternate. Proposing to build a prestressed, posttensioned concrete-box girder bridge, CFF planned to perform the substructure work and to subcontract the work on the superstructure to Moseman Construction Co. (Moseman), a specialist in cast-in-place and precast segmental concrete construction. In addition, CFF also subcontracted the job of manufacturing prestressed concrete piles and girders to CPC.

The DOT’s specifications required it to award the contract within thirty days; however, award was not made to CFF until June 12, 1985. By agreement CFF waived its claim for delay, and DOT changed the completion date from September 15, 1988, to December 15, 1988. The DOT issued CFF a notice to proceed on July 9, 1985.

The contract documents applicable to the project included the Standard Specifications for Road and Bridge Construction (the blue book), supplemental specifications, plans, and special provisions. The documents were to be considered complementary. In case of a discrepancy, calculated dimensions were to govern over scaled dimensions; plans were to govern over specifications; supplemental specifications were to govern over specifications and plans; and special provisions govern over both specifications and plans.

Almost immediately upon commencement of construction by CFF, problems arose which led to multiple disputes among the parties. The most significant problem was the unexpected behavior of the soils at the bottom of Narragansett Bay (bay). As a result of soil difficulty in the bay, DOT changed the pile-design concept from a friction-pile design to a more expensive composite-pile design. The DOT and CFF disagreed on the additional cost associated with employing the composite-pile design and CFF estimated the increased cost at $30 million. The DOT estimated the cost at twelve million dollars. DOT ordered CFF to continue working under a force account. On February 18, 1988, CFF filed suit in the Superior Court, seeking injunctive relief, termination of the contract, and damages, contending that the change in pile design amounted to a cardinal change of the contract.

In March of 1988 the parties entered into a termination agreement that relieved CFF of any further obligation to perform the con *443 tract and mutually released the parties from all claims except those reserved by the parties in the termination agreement. Then CPC brought suit against CFF separately, and CFF brought DOT into that action as a third-party defendant. The DOT brought counterclaims against CFF for damages arising from the termination of the contract. The cases were consolidated for a nonjury trial in the Superior Court on all unresolved claims, with CFF presenting CPC’s pass-through claim against DOT.

The trial commenced in January of 1991 and continued for several months, during which time more than 4000 pages of complex testimony were produced and approximately 500 exhibits were introduced. In March of 1993, approximately twenty-one months after the trial ended, the trial justice rendered a 205-page written decision with a 132-page appendix containing findings of fact. The parties suggested a few minor revisions of the trial justice’s decision, and a revised decision was entered in April of 1993. We do not summarize here each of the findings of fact by the trial justice but shall address them below as they relate to the issues before us.

Two judgments were entered in the Superior Court: (1) judgment for CFF against the state in the amount of $22,551,754, without interest, which represents $22,476,914 in compensatory damages plus $74,840 in funds withheld by the state on its counterclaims against CFF, and (2) judgment for CPC in the amount of $1,261,544, without interest, against CFF and passed through to the state. The net result of both judgments is that the state owes to CFF $23,813,298, without interest. The state, CFF, and CPC appeal from the entry of the two Superior Court judgments in this consolidated action. We shall first address the state’s appeal; then we shall turn to the cross-appeals of CFF and CPC.

In this jurisdiction the standard of review of the findings of a trial justice sitting without the intervention of a jury is extremely deferential. On appeal we do not disturb the findings of the trial justice unless he or she overlooked or misconceived material evidence or was otherwise clearly wrong. Cerilli v. Newport Offshore Ltd., 612 A.2d 35 (R.I.1992). Contract interpretation is a question of law; it is only when contract terms are ambiguous that construction of terms becomes a question of fact. Judd Realty, Inc. v. Tedesco, 400 A.2d 952 (R.I.1979). In situations in which the language of a contractual agreement is plain and unambiguous, its meaning should be determined without reference to extrinsic facts or aids. Greenwald v. Selya & Iannuccillo, 491 A.2d 988 (R.I.1985).

The state contends that the trial justice erred in awarding damages to CFF for the cost and delay associated with excavating the foundations of piers 14 through 20. The state argues that the contract required the-foundations of those piers to be on suitably sound bedrock and contemplated embedment.

By way of background we discuss briefly the bridge-design concept at issue. Piers 14 through 20, the water piers on the Jamestown side of the bridge, were to be constructed using cofferdams and tremie seals made of concrete without pile support.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adebamowo v. Liberty Insurance
Supreme Court of Rhode Island, 2024
Management Capital, L.L.C. v. F.A.F., Inc.
209 A.3d 1162 (Supreme Court of Rhode Island, 2019)
John Rocchio Corporation v. Pare Engineering Corporation
201 A.3d 316 (Supreme Court of Rhode Island, 2019)
Governor of the Bank of Scotland v. Wasserman
928 F. Supp. 2d 400 (D. Rhode Island, 2013)
Cappalli v. BJ's Wholesale Club, Inc.
904 F. Supp. 2d 184 (D. Rhode Island, 2012)
Cheaters, Inc. v. United National Insurance
41 A.3d 637 (Supreme Court of Rhode Island, 2012)
Ferris Avenue Realty v. Huhtamaki, Inc.
Superior Court of Rhode Island, 2011
B.S. International Ltd. v. JMAM, LLC
13 A.3d 1057 (Supreme Court of Rhode Island, 2011)
Greenwich Northeast v. E.W. Burman
Superior Court of Rhode Island, 2011
Horbet v. New Penn, Inc.
Superior Court of Rhode Island, 2011
Dipaolo v. Marques
Superior Court of Rhode Island, 2010
Haffenreffer v. Haffenreffer
994 A.2d 1226 (Supreme Court of Rhode Island, 2010)
ADP Marshall, Inc. v. NORESCO, LLC
710 F. Supp. 2d 197 (D. Rhode Island, 2010)
Young v. Warwick Rollermagic Skating Center, Inc.
973 A.2d 553 (Supreme Court of Rhode Island, 2009)
Irene Realty Corp. v. Travelers Property Casualty Co. of America
973 A.2d 1118 (Supreme Court of Rhode Island, 2009)
Erinakes v. Zahreddine
Superior Court of Rhode Island, 2009
State v. Lead Industries Association
Superior Court of Rhode Island, 2009
Cathay Cathay, Inc. v. VINDALU, LLC
962 A.2d 740 (Supreme Court of Rhode Island, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
652 A.2d 440, 1994 R.I. LEXIS 302, 1994 WL 720869, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clark-fitzpatrick-incfranki-foundation-co-v-gill-ri-1994.