Richardson Electrical Co. v. Peter Francese & Son, Inc.

484 N.E.2d 108, 21 Mass. App. Ct. 47
CourtMassachusetts Appeals Court
DecidedOctober 21, 1985
StatusPublished
Cited by7 cases

This text of 484 N.E.2d 108 (Richardson Electrical Co. v. Peter Francese & Son, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richardson Electrical Co. v. Peter Francese & Son, Inc., 484 N.E.2d 108, 21 Mass. App. Ct. 47 (Mass. Ct. App. 1985).

Opinion

Kass, J.

Four parties are involved in these consolidated appeals, but, as the cases were presented in the briefs and argument, the controversy devolves into one in which the town *48 of Lenox, as owner of a water pumping station, and Richardson Electrical Company, Inc. (Richardson), an electrical work subcontractor, are the disputants. The question to be decided is whether the construction plans and specifications used by Lenox to obtain bids for construction of the pumping station failed to put Richardson on notice that the electrical subcontractor would have to dig an 11,000-foot trench across rocky terrain to accommodate a telephone cable.

Richardson’s complaint against the general contractor, Peter Francese & Son, Inc. (Francese), sought payment for extra work and materials. Conformably with G. L. c. 149, § 29, Richardson named the bonding company, The Hartford Accident and Indemnity Company (Hartford), a codefendant. Francese impleaded Lenox as a third-party defendant, and Lenox, in turn, brought in Whitman & Howard, Inc. (Whitman & Howard), the engineers who prepared the bid documents, as a fourth-party defendant. After trial in the Superior Court without a jury, Richardson obtained a judgment of $34,112.05 against Francese and Hartford, from which both appeal. Francese obtained a judgment of $53,803.38 against Lenox, from which Lenox appeals. 2

A summary of the facts found by the judge who heard the primary case 3 follows:

Richardson’s subbid, dated May 17, 1978, undertook to furnish all the labor and materials required by § 29 (“Electrical Work”) of the specifications. Those specifications included *49 trenching for an “[ejmpty telephone conduit from contact pole to telephone terminal cabinets.” The plans showed a contact pole about fifty feet from the pumping structure. Section 29 (s) 11 of the specifications called upon the subcontractor to make arrangements with New England Telephone (NET) for extension of their telephone line to the station site, and § 29 (s) (9) (a) required the subcontractor to arrange with Western Massachusetts Electric Company (WMEC) for extension of primary power lines “from their nearest three phase supply (near the Richmond town line) to the station site. Western Massachusetts Electric Co. will install the pole line, last contact pole and the pad mounted transformer.”

Before bidding, Richardson did, indeed, make inquiries of the respective utilities. NET told Richardson it would make no charge to bring in telephone service. 4 That was pertinent to Richardson’s bid because the specifications required the electrical subcontractor to pay charges and fees levied by the utilities. WMEC informed Richardson it would charge $28,906 to bring power to the contact pole. Nothing on the plans or in the specifications showed precisely how NET would bring its service to the contact pole, although Richardson could reasonably assume that the telephone lines would hang, as they generally did, alongside the power lines. NET’S “no charge” response to Richardson was consistent with that assumption.

An essential premise, however, was faulty. The town of Richmond, from which WMEC was extending power lines, was not served by NET, but by an independent local company. NET lines did not run on the power line poles in that town; consequently, there were no NET telephone wires to extend. 5 Whitman & Howard, the project engineer preparing the bid documents, had known that there was some uncertainty about *50 the source of telephone service. It had made inquiry of NET on March 27,1978, but received no reply until November 20.

There were choices for telephone transmission: overhead lines, underground lines, or microwave. Whitman & Howard, on behalf of the town, opted for underground lines after the town rejected a microwave link. That decision was made late in 1978, well after Richardson had submitted its bid. Richardson, when directed to excavate the necessary trench for an underground line, did so under protest, i.e., claiming that the work was not in the contract and that it would file a claim for it as an extra. As matters developed, some of the terrain contained ledge whose removal was beyond Richardson’s technology. The general contractor had to complete the trench and back charged Richardson accordingly. Richardson had not visited the project site before making its bid, as required by § 12 (1) of the general conditions of the contract, but, the trial judge remarked, “there is nothing to indicate that a visit to the station site by Richardson would have overcome the insufficiency.” The judge concluded that the specifications were “hardly sufficient to convey to bidders the information that they needed to make intelligent bids. Failure by Whitman & Howard to resolve the questions about telephone service left the specifications seriously inadequate and unjustifiably indefinite.”

As to facts we, of course, accept the findings of the trial judge unless clearly erroneous. Mass.R.Civ.P. 52(a), 365 Mass. 816 (1974). First Pa. Mortgage Trust v. Dorchester Sav. Bank, 395 Mass. 614, 621 (1985). C.C. & T. Constr. Co. v. Coleman Bros., 8 Mass. App. Ct. 133, 135 (1979). Whether the terms of the construction contract were impermissibly vague is a mixed question of fact and law. Cf. Markell v. Sidney B. Pfeifer Foundation, Inc., 9 Mass. App. Ct. 412, 429 (1980); Patry v. Harmony Homes, Inc., 10 Mass. App. Ct. 1, 6 (1980). There is implied in a set of construction plans and specifications a warranty that they are accurate as to descriptions of the kind and quantity of work required. See M.L. Shalloo, Inc. v. Ricciardi & Sons Constr., 348 Mass. 682, 686-688 (1965); Alpert v. Commonwealth, 357 Mass. 306, 321 (1970). Contrast D. Federico Co. v. Commonwealth, 11 *51 Mass. App. Ct. 248, 251-252 (1981), in which the contract expressly stated that estimates of quantities of excavation and replacement fill required on the job were not guaranteed, thus precluding warranty of, or reliance on, the furnished estimates. Contrast also Daniel O’ Connell’s Sons v. Commonwealth, 349 Mass. 642, 644-648 (1965) (contract disclaimed accuracy of “limited geologic data” and warned that reliance on the information furnished would be solely at the bidders’ risk).

No disclaimer or warning of corresponding force bearing on the telephone line needed appears as part of the contract documents in the instant case. To be sure, the information for bidders provided that “[t]he bidder . . . shall visit the site and shall satisfy himself as to the type and quantity of the work to be done,” but, as the judge found, a site visit would not have raised an alarm that a telephone contact pole would not be available, as the drawings suggested and as inquiry of NET seemed to confirm.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coghlin Electrical Contractors, Inc. v. Gilbane Building Co.
472 Mass. 549 (Massachusetts Supreme Judicial Court, 2015)
Division of Capital Planning & Operations v. TLT Construction Corp.
7 Mass. L. Rptr. 311 (Massachusetts Superior Court, 1997)
Ryan Iron Works, Inc. v. J.F. White Contracting Co.
6 Mass. L. Rptr. 377 (Massachusetts Superior Court, 1997)
J. F. White Contracting Co. v. Massachusetts Bay Transportation Authority
666 N.E.2d 518 (Massachusetts Appeals Court, 1996)
J.F. White Contracting Co. v. Massachusetts Bay Transportation Authority
4 Mass. L. Rptr. 37 (Massachusetts Superior Court, 1995)
B. J. Harland Electrical Co. v. Granger Bros.
510 N.E.2d 765 (Massachusetts Appeals Court, 1987)
First Safety Fund National Bank v. Friel
504 N.E.2d 664 (Massachusetts Appeals Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
484 N.E.2d 108, 21 Mass. App. Ct. 47, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richardson-electrical-co-v-peter-francese-son-inc-massappct-1985.